{"id":25158,"date":"2023-04-28T11:48:03","date_gmt":"2023-04-28T08:48:03","guid":{"rendered":"https:\/\/www.bicakhukuk.com\/?p=25158"},"modified":"2026-07-25T17:16:04","modified_gmt":"2026-07-25T14:16:04","slug":"nuclear-power-plant-law-in-turkey","status":"publish","type":"post","link":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/","title":{"rendered":"Nuclear power plant law in Turkey"},"content":{"rendered":"<h3 class=\"PDq2pG_selectionAnchorContainer\" data-section-id=\"1k6ke8y\" data-start=\"1965\" data-end=\"2005\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye\u2019s Transition to Nuclear Power<\/span><\/h3>\n<p data-start=\"2007\" data-end=\"2454\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has considered the introduction of nuclear-generated electricity since the 1950s. The <a href=\"https:\/\/www.tenmak.gov.tr\/\" target=\"_blank\" rel=\"noopener\">Turkish Atomic Energy Commission<\/a> was established in 1956, and Akkuyu on T\u00fcrkiye\u2019s Mediterranean coast was subsequently identified as a potential nuclear power plant site. Several earlier procurement and development initiatives did not result in construction, however, and T\u00fcrkiye remained without an operating commercial nuclear power plant for decades.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A decisive change occurred with the agreement signed between T\u00fcrkiye and the Russian Federation on 12 May 2010 concerning the construction and operation of a nuclear power plant at Akkuyu. Unlike a conventional public procurement structure, the Akkuyu project was organised around a <strong data-start=\"2739\" data-end=\"2766\">build-own-operate model<\/strong> under which the project company would construct, own and operate the plant.<\/span><!--more--><\/p>\n<p data-start=\"2844\" data-end=\"3469\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The project comprises four VVER-1200 reactor units with an aggregate planned capacity of approximately 4.8 GW. Construction, regulatory approvals, commissioning preparations and power-system works have continued through successive phases. In January 2026, the project company reported completion of a connection operation intended to demonstrate the readiness of Unit 1\u2019s power-distribution system to transfer electricity. The precise date of first generation and commercial operation nevertheless remains dependent on completion of technical work, testing and regulatory authorisations.<\/span><\/p>\n<p data-start=\"3471\" data-end=\"3840\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye\u2019s nuclear strategy now extends beyond Akkuyu. Government policy envisages more than 20 GW of nuclear capacity by 2050, including conventional large reactors and potentially small modular reactors. Nuclear energy is expected to contribute to energy-security, decarbonisation and T\u00fcrkiye\u2019s net-zero emissions target for 2053. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The resulting legal landscape is no longer limited to the licensing of one nuclear facility. It includes:<\/span><\/p>\n<ul data-start=\"3949\" data-end=\"4494\">\n<li data-section-id=\"43c37q\" data-start=\"3949\" data-end=\"4009\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Akkuyu\u2019s construction, commissioning and future operation;<\/span><\/li>\n<li data-section-id=\"l3ywcc\" data-start=\"4010\" data-end=\"4060\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the development and licensing of the Sinop site;<\/span><\/li>\n<li data-section-id=\"enucod\" data-start=\"4061\" data-end=\"4116\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">negotiations concerning further large-scale capacity;<\/span><\/li>\n<li data-section-id=\"16b35h\" data-start=\"4117\" data-end=\"4162\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">potential small modular reactor deployment;<\/span><\/li>\n<li data-section-id=\"11yk1hs\" data-start=\"4163\" data-end=\"4224\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear component manufacturing and supplier qualification;<\/span><\/li>\n<li data-section-id=\"1boiw4f\" data-start=\"4225\" data-end=\"4264\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology transfer and localisation;<\/span><\/li>\n<li data-section-id=\"1sz36t9\" data-start=\"4265\" data-end=\"4323\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear fuel, radioactive material and waste management;<\/span><\/li>\n<li data-section-id=\"15n7ver\" data-start=\"4324\" data-end=\"4379\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity and critical-infrastructure protection;<\/span><\/li>\n<li data-section-id=\"1e6ko5o\" data-start=\"4380\" data-end=\"4428\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">project finance and investment protection; and<\/span><\/li>\n<li data-section-id=\"1u4zkbv\" data-start=\"4429\" data-end=\"4494\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the resolution of complex construction and commercial disputes.<\/span><\/li>\n<\/ul>\n<p data-start=\"4496\" data-end=\"4971\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The <a href=\"https:\/\/www.nuclearbusiness-platform.com\/store\/p\/turkey-report-2025\" target=\"_blank\" rel=\"noopener\"><strong data-start=\"4500\" data-end=\"4538\">Turkish Nuclear Market Report 2026<\/strong><\/a> accordingly characterises T\u00fcrkiye\u2019s nuclear programme as a multi-decade commercial market extending across construction, operation, maintenance, digital services, industrial participation and eventual lifecycle management. The report\u2019s commercial projections should be treated as market assessments rather than official legal findings, but they demonstrate the increasing breadth of the sector.<\/span><\/p>\n<h3 data-section-id=\"qfukmp\" data-start=\"4978\" data-end=\"5047\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Constitutional and Legislative Structure of Turkish Nuclear Law<\/span><\/h3>\n<p data-start=\"5049\" data-end=\"5302\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Turkish nuclear law is not contained in one statute. It consists of a hierarchy of constitutional principles, international agreements, legislation, presidential decrees, regulations, regulatory decisions, licences, approvals and technical requirements. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The principal layers are:<\/span><\/p>\n<ol data-start=\"5331\" data-end=\"5820\">\n<li data-section-id=\"e868le\" data-start=\"5331\" data-end=\"5378\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Constitution of the Republic of T\u00fcrkiye;<\/span><\/li>\n<li data-section-id=\"roaa5v\" data-start=\"5379\" data-end=\"5438\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">international treaties and intergovernmental agreements;<\/span><\/li>\n<li data-section-id=\"1yb2ns7\" data-start=\"5439\" data-end=\"5493\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><a href=\"https:\/\/www.oecd-nea.org\/jcms\/pl_81648\/unofficial-translation-of-the-turkish-law-no-7381-nuclear-regulation-law?details=true\" target=\"_blank\" rel=\"noopener\">Nuclear Regulation Law No. 7381<\/a> and other statutes;<\/span><\/li>\n<li data-section-id=\"1ntw78a\" data-start=\"5494\" data-end=\"5559\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">presidential decrees, particularly <a href=\"https:\/\/www.oecd-nea.org\/upload\/docs\/application\/pdf\/2025-02\/unofficial_translation_of_the_turkish_presidential_decree_no._95.pdf\" target=\"_blank\" rel=\"noopener\">Presidential Decree No. 95<\/a>;<\/span><\/li>\n<li data-section-id=\"1x5yczt\" data-start=\"5560\" data-end=\"5591\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">regulations and communiqu\u00e9s;<\/span><\/li>\n<li data-section-id=\"1hocghi\" data-start=\"5592\" data-end=\"5665\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">decisions and requirements issued by the <a href=\"https:\/\/www.ndk.gov.tr\/en-US\" target=\"_blank\" rel=\"noopener\">Nuclear Regulatory Authority<\/a>;<\/span><\/li>\n<li data-section-id=\"184tt6k\" data-start=\"5666\" data-end=\"5754\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">licences, permits and approvals relating to individual facilities and activities; and<\/span><\/li>\n<li data-section-id=\"rzg6d8\" data-start=\"5755\" data-end=\"5820\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">applicable technical codes, standards and regulatory guidance.<\/span><\/li>\n<\/ol>\n<p data-start=\"5822\" data-end=\"6292\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Article 90 of the <a href=\"https:\/\/www.bicakhukuk.com\/en\/english-translation-of-the-constitution-of-the-republic-of-turkiye\/\" target=\"_blank\" rel=\"noopener\">Constitution<\/a> gives duly ratified international agreements the force of law. Where an international agreement concerning fundamental rights conflicts with domestic legislation, the international agreement prevails. Intergovernmental nuclear project agreements may therefore have a particularly important role in determining project structure, ownership, electricity purchasing arrangements, state commitments and certain responsibilities of the parties. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">At the same time, an intergovernmental agreement does not remove the project from the generally applicable nuclear safety and licensing system. The project company and operator must still comply with mandatory Turkish regulatory requirements unless a valid and applicable legal provision establishes otherwise.<\/span><\/p>\n<h3 data-section-id=\"cjo58o\" data-start=\"6611\" data-end=\"6644\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Regulation Law No. 7381<\/span><\/h3>\n<p data-start=\"6680\" data-end=\"6912\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye reorganised its nuclear regulatory framework through Decree-Law No. 702 in 2018. That measure separated regulatory responsibilities from promotional and operational functions and established the Nuclear Regulatory Authority.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Following the Constitutional Court\u2019s annulment of the decree-law on procedural grounds, Parliament enacted <strong data-start=\"7021\" data-end=\"7056\">Nuclear Regulation Law No. 7381<\/strong>, which entered into force on 8 March 2022. Presidential Decree No. 95 separately regulates the organisation and duties of the Nuclear Regulatory Authority.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The OECD Nuclear Energy Agency identifies Law No. 7381 and Presidential Decree No. 95 as T\u00fcrkiye\u2019s primary nuclear legislation. Its updated 2025 country profile covers nuclear installations, radioactive substances, radiation protection, waste, transport, safeguards, physical protection and third-party liability. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Law No. 7381 applies broadly to activities involving nuclear energy and ionising radiation. It addresses, among other matters:<\/span><\/p>\n<ul data-start=\"7716\" data-end=\"8179\">\n<li data-section-id=\"z1ebha\" data-start=\"7716\" data-end=\"7740\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear installations;<\/span><\/li>\n<li data-section-id=\"1k6ya4z\" data-start=\"7741\" data-end=\"7788\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation facilities and radiation practices;<\/span><\/li>\n<li data-section-id=\"qmags9\" data-start=\"7789\" data-end=\"7820\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste facilities;<\/span><\/li>\n<li data-section-id=\"1w4p0jm\" data-start=\"7821\" data-end=\"7864\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear material and radioactive sources;<\/span><\/li>\n<li data-section-id=\"1vxpk1z\" data-start=\"7865\" data-end=\"7898\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">authorisation and notification;<\/span><\/li>\n<li data-section-id=\"bv5zhp\" data-start=\"7899\" data-end=\"7916\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear safety;<\/span><\/li>\n<li data-section-id=\"nu0x6v\" data-start=\"7917\" data-end=\"7936\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear security;<\/span><\/li>\n<li data-section-id=\"1akjn4k\" data-start=\"7937\" data-end=\"7950\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safeguards;<\/span><\/li>\n<li data-section-id=\"1ao19o3\" data-start=\"7951\" data-end=\"7974\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation protection;<\/span><\/li>\n<li data-section-id=\"1cm73dd\" data-start=\"7975\" data-end=\"8005\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">inspections and enforcement;<\/span><\/li>\n<li data-section-id=\"1lb9gs7\" data-start=\"8006\" data-end=\"8052\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste and decommissioning funds;<\/span><\/li>\n<li data-section-id=\"7yts3j\" data-start=\"8053\" data-end=\"8090\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">civil liability for nuclear damage;<\/span><\/li>\n<li data-section-id=\"1vcmqil\" data-start=\"8091\" data-end=\"8126\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">insurance and financial security;<\/span><\/li>\n<li data-section-id=\"1hpc7dg\" data-start=\"8127\" data-end=\"8158\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">administrative sanctions; and<\/span><\/li>\n<li data-section-id=\"1ej494\" data-start=\"8159\" data-end=\"8179\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">criminal offences.<\/span><\/li>\n<\/ul>\n<p data-start=\"8181\" data-end=\"8253\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The legislation reflects the internationally recognised <strong data-start=\"8237\" data-end=\"8252\">3S approach<\/strong>:<\/span><\/p>\n<ul data-start=\"8255\" data-end=\"8655\">\n<li data-section-id=\"1x8ck34\" data-start=\"8255\" data-end=\"8365\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><strong data-start=\"8257\" data-end=\"8267\">Safety<\/strong>, meaning protection against radiological risks arising from authorised activities and facilities;<\/span><\/li>\n<li data-section-id=\"dhdk33\" data-start=\"8366\" data-end=\"8502\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><strong data-start=\"8368\" data-end=\"8380\">Security<\/strong>, meaning prevention and detection of, and response to, theft, sabotage, unauthorised access and other malicious acts; and<\/span><\/li>\n<li data-section-id=\"ttjxet\" data-start=\"8503\" data-end=\"8655\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><strong data-start=\"8505\" data-end=\"8519\">Safeguards<\/strong>, meaning accounting, control and verification measures intended to ensure that nuclear material is not diverted from peaceful purposes.<\/span><\/li>\n<\/ul>\n<p data-start=\"8657\" data-end=\"8788\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">These concepts overlap but are legally and operationally distinct. Compliance with one does not replace compliance with the others.<\/span><\/p>\n<h3 data-section-id=\"kva92q\" data-start=\"8795\" data-end=\"8838\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Principal Nuclear Institutions in T\u00fcrkiye<\/span><\/h3>\n<h4 data-section-id=\"1mw4oua\" data-start=\"8840\" data-end=\"8883\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Ministry of Energy and Natural Resources<\/span><\/h4>\n<p data-start=\"8885\" data-end=\"9221\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Ministry of Energy and Natural Resources determines national energy policy and plays a central role in the development of T\u00fcrkiye\u2019s nuclear energy programme. Its responsibilities differ from those of the nuclear regulator: the Ministry promotes and coordinates energy policy, while the NDK performs independent regulatory functions. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The distinction between promotion and regulation is fundamental to the credibility of a national nuclear programme. A body responsible for developing or operating nuclear facilities should not also be responsible for making independent safety determinations about those facilities.<\/span><\/p>\n<h4 data-section-id=\"1j6j4ge\" data-start=\"9506\" data-end=\"9537\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Regulatory Authority<\/span><\/h4>\n<p data-start=\"9539\" data-end=\"9659\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The <strong data-start=\"9543\" data-end=\"9571\">N\u00fckleer D\u00fczenleme Kurumu<\/strong>, or <strong data-start=\"9576\" data-end=\"9583\">NDK<\/strong>, is the Turkish authority responsible for nuclear and radiation regulation.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Its principal powers include:<\/span><\/p>\n<ul data-start=\"9692\" data-end=\"10526\">\n<li data-section-id=\"1043xv\" data-start=\"9692\" data-end=\"9740\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">issuing regulatory requirements and decisions;<\/span><\/li>\n<li data-section-id=\"9ss42x\" data-start=\"9741\" data-end=\"9780\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">determining authorisation conditions;<\/span><\/li>\n<li data-section-id=\"1q3tpys\" data-start=\"9781\" data-end=\"9858\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">granting, restricting, suspending, terminating and revoking authorisations;<\/span><\/li>\n<li data-section-id=\"1qwwe0f\" data-start=\"9859\" data-end=\"9916\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">reviewing licence applications and technical documents;<\/span><\/li>\n<li data-section-id=\"zal4z8\" data-start=\"9917\" data-end=\"9971\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">carrying out inspections and on-site investigations;<\/span><\/li>\n<li data-section-id=\"nh9rv2\" data-start=\"9972\" data-end=\"10036\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">approving matters relating to safety, security and safeguards;<\/span><\/li>\n<li data-section-id=\"1l3fa1n\" data-start=\"10037\" data-end=\"10079\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">requiring additional safety assessments;<\/span><\/li>\n<li data-section-id=\"i8vnvh\" data-start=\"10080\" data-end=\"10148\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">verifying nuclear liability insurance or other financial security;<\/span><\/li>\n<li data-section-id=\"1csi180\" data-start=\"10149\" data-end=\"10215\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">monitoring radioactive sources and occupational radiation doses;<\/span><\/li>\n<li data-section-id=\"g51l94\" data-start=\"10216\" data-end=\"10278\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">maintaining nuclear material accounting and control systems;<\/span><\/li>\n<li data-section-id=\"1swpsvr\" data-start=\"10279\" data-end=\"10315\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">imposing administrative sanctions;<\/span><\/li>\n<li data-section-id=\"1fpm98c\" data-start=\"10316\" data-end=\"10386\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cooperating with foreign regulators and international organisations;<\/span><\/li>\n<li data-section-id=\"gr7vb6\" data-start=\"10387\" data-end=\"10454\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">communicating extraordinary events to competent institutions; and<\/span><\/li>\n<li data-section-id=\"d6fomz\" data-start=\"10455\" data-end=\"10526\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">requesting information and documents from public and private persons.<\/span><\/li>\n<\/ul>\n<p data-start=\"10528\" data-end=\"10710\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The OECD\/NEA\u2019s updated profile confirms that the current legal architecture is based principally on Law No. 7381 and Presidential Decree No. 95.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The NDK must make its licensing determinations on the basis of nuclear safety, security, safeguards and radiation-protection requirements. Commercial pressure, project schedules or political objectives do not legally replace the regulator\u2019s assessment.<\/span><\/p>\n<h4 data-section-id=\"scu3fq\" data-start=\"10966\" data-end=\"10999\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye Nuclear Energy Company<\/span><\/h4>\n<p data-start=\"11001\" data-end=\"11174\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><a href=\"https:\/\/www.tunas.gov.tr\/tr\" target=\"_blank\" rel=\"noopener\"><strong data-start=\"11001\" data-end=\"11042\">T\u00fcrkiye N\u00fckleer Enerji Anonim \u015eirketi<\/strong><\/a>, known as <strong data-start=\"11053\" data-end=\"11062\">T\u00dcNA\u015e<\/strong>, performs project-development, programme-management, supplier-development and infrastructure-related functions. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Its publicly described activities include:<\/span><\/p>\n<ul data-start=\"11220\" data-end=\"11629\">\n<li data-section-id=\"1q6wtr4\" data-start=\"11220\" data-end=\"11261\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Sinop nuclear power plant site studies;<\/span><\/li>\n<li data-section-id=\"cx9ipg\" data-start=\"11262\" data-end=\"11301\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">preparation of the Sinop site report;<\/span><\/li>\n<li data-section-id=\"1tqqbdq\" data-start=\"11302\" data-end=\"11341\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental impact assessment work;<\/span><\/li>\n<li data-section-id=\"u1q0oo\" data-start=\"11342\" data-end=\"11376\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Sinop ownership application;<\/span><\/li>\n<li data-section-id=\"59w7rp\" data-start=\"11377\" data-end=\"11410\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">zoning and planning activities;<\/span><\/li>\n<li data-section-id=\"yfkeio\" data-start=\"11411\" data-end=\"11454\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear project and programme management;<\/span><\/li>\n<li data-section-id=\"1i8kq1k\" data-start=\"11455\" data-end=\"11497\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">supplier and infrastructure development;<\/span><\/li>\n<li data-section-id=\"frvh50\" data-start=\"11498\" data-end=\"11536\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">preparation of owner\u2019s requirements;<\/span><\/li>\n<li data-section-id=\"dqggnb\" data-start=\"11537\" data-end=\"11582\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">human-resource and competency planning; and<\/span><\/li>\n<li data-section-id=\"40fkgn\" data-start=\"11583\" data-end=\"11629\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">assessment of small modular reactor designs.<\/span><\/li>\n<\/ul>\n<p data-start=\"11631\" data-end=\"11911\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00dcNA\u015e submitted an application to be recognised as the owner of the Sinop project on 31 December 2022. The NDK recognised T\u00dcNA\u015e as the project owner on 27 January 2023, and T\u00dcNA\u015e states that a site-licence application has also been submitted.<\/span><\/p>\n<h4 data-section-id=\"17q9a3h\" data-start=\"11913\" data-end=\"11922\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">TENMAK<\/span><\/h4>\n<p data-start=\"11924\" data-end=\"12279\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The <a href=\"https:\/\/www.tenmak.gov.tr\/\" target=\"_blank\" rel=\"noopener\">Turkish Energy, Nuclear and Mineral Research Agency<\/a>, or <strong data-start=\"11984\" data-end=\"11994\">TENMAK<\/strong>, conducts research, technology-development and technical activities in energy, nuclear science, ionising radiation, minerals and related fields. Its research and technical functions should be distinguished from the NDK\u2019s regulatory authority and from T\u00dcNA\u015e\u2019s project-development role.<\/span><\/p>\n<h2 data-section-id=\"xckqua\" data-start=\"12281\" data-end=\"12289\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">N\u00dcTED<\/span><\/h2>\n<p data-start=\"12291\" data-end=\"12563\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><a href=\"https:\/\/www.nuted.com.tr\/en-US\" target=\"_blank\" rel=\"noopener\">N\u00dcTED Nuclear Technical Support Joint Stock Company<\/a> was created to provide technical support services required by the regulatory authority. Such services may include examination, assessment, inspection, testing, certification, research, training and technical consultancy.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The use of a technical support organisation does not transfer the NDK\u2019s regulatory decision-making authority. Licensing and enforcement decisions remain the responsibility of the legally competent regulator.<\/span><\/p>\n<h4 data-section-id=\"qrvkv9\" data-start=\"12774\" data-end=\"12803\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Other Relevant Authorities<\/span><\/h4>\n<p data-start=\"12805\" data-end=\"12857\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A nuclear project may also require interaction with:<\/span><\/p>\n<ul data-start=\"12859\" data-end=\"13302\">\n<li data-section-id=\"1y8tfse\" data-start=\"12859\" data-end=\"12922\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Ministry of Environment, Urbanisation and Climate Change;<\/span><\/li>\n<li data-section-id=\"19f8ttx\" data-start=\"12923\" data-end=\"12964\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Energy Market Regulatory Authority;<\/span><\/li>\n<li data-section-id=\"14syt8q\" data-start=\"12965\" data-end=\"12989\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Ministry of Trade;<\/span><\/li>\n<li data-section-id=\"dng8e8\" data-start=\"12990\" data-end=\"13029\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Ministry of Treasury and Finance;<\/span><\/li>\n<li data-section-id=\"luqzz7\" data-start=\"13030\" data-end=\"13077\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Ministry of Transport and Infrastructure;<\/span><\/li>\n<li data-section-id=\"10gsfmk\" data-start=\"13078\" data-end=\"13129\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Disaster and Emergency Management Presidency;<\/span><\/li>\n<li data-section-id=\"4i7pjn\" data-start=\"13130\" data-end=\"13169\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">provincial and local administrations;<\/span><\/li>\n<li data-section-id=\"191tmf8\" data-start=\"13170\" data-end=\"13192\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">customs authorities;<\/span><\/li>\n<li data-section-id=\"rfxkbz\" data-start=\"13193\" data-end=\"13243\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">competition and data-protection authorities; and<\/span><\/li>\n<li data-section-id=\"18apudx\" data-start=\"13244\" data-end=\"13302\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">security, emergency-response and law-enforcement bodies.<\/span><\/li>\n<\/ul>\n<p data-start=\"13304\" data-end=\"13426\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The precise institutional map depends on the project stage, the activity involved and the corporate and contractual model.<\/span><\/p>\n<h3 data-section-id=\"1x7f4ez\" data-start=\"13433\" data-end=\"13464\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Secondary Nuclear Legislation<\/span><\/h3>\n<p data-start=\"13466\" data-end=\"13575\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has developed an extensive body of secondary legislation under the general framework of Law No. 7381.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The T\u00dcNA\u015e legislation database identifies regulations dealing with:<\/span><\/p>\n<ul data-start=\"13646\" data-end=\"14453\">\n<li data-section-id=\"15r1pn\" data-start=\"13646\" data-end=\"13693\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">authorisations concerning nuclear facilities;<\/span><\/li>\n<li data-section-id=\"1fywre9\" data-start=\"13694\" data-end=\"13722\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear power plant sites;<\/span><\/li>\n<li data-section-id=\"qff6qh\" data-start=\"13723\" data-end=\"13776\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">special safety principles for nuclear power plants;<\/span><\/li>\n<li data-section-id=\"b3ffzy\" data-start=\"13777\" data-end=\"13817\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear power plant design principles;<\/span><\/li>\n<li data-section-id=\"1mogivq\" data-start=\"13818\" data-end=\"13839\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear safeguards;<\/span><\/li>\n<li data-section-id=\"plnbjs\" data-start=\"13840\" data-end=\"13875\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">physical protection and security;<\/span><\/li>\n<li data-section-id=\"1ao19o3\" data-start=\"13876\" data-end=\"13899\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation protection;<\/span><\/li>\n<li data-section-id=\"t6yj6r\" data-start=\"13900\" data-end=\"13949\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear inspections and on-site investigations;<\/span><\/li>\n<li data-section-id=\"8c3b4i\" data-start=\"13950\" data-end=\"13975\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear export control;<\/span><\/li>\n<li data-section-id=\"10qzmm9\" data-start=\"13976\" data-end=\"14018\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear power plant building inspection;<\/span><\/li>\n<li data-section-id=\"16h5cr1\" data-start=\"14019\" data-end=\"14084\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">procurement of nuclear equipment and approval of manufacturers;<\/span><\/li>\n<li data-section-id=\"1b8og9i\" data-start=\"14085\" data-end=\"14106\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">management systems;<\/span><\/li>\n<li data-section-id=\"1veo0hs\" data-start=\"14107\" data-end=\"14148\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">organisational structure and personnel;<\/span><\/li>\n<li data-section-id=\"qdm8e4\" data-start=\"14149\" data-end=\"14186\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport of radioactive materials;<\/span><\/li>\n<li data-section-id=\"16jixmf\" data-start=\"14187\" data-end=\"14222\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste and spent fuel;<\/span><\/li>\n<li data-section-id=\"qmags9\" data-start=\"14223\" data-end=\"14254\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste facilities;<\/span><\/li>\n<li data-section-id=\"1lw180e\" data-start=\"14255\" data-end=\"14312\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste and decommissioning special accounts;<\/span><\/li>\n<li data-section-id=\"1qqw3mn\" data-start=\"14313\" data-end=\"14337\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation emergencies;<\/span><\/li>\n<li data-section-id=\"h9tnky\" data-start=\"14338\" data-end=\"14370\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">national radiation monitoring;<\/span><\/li>\n<li data-section-id=\"rt41tn\" data-start=\"14371\" data-end=\"14425\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">remediation of radioactively contaminated areas; and<\/span><\/li>\n<li data-section-id=\"1wwawqy\" data-start=\"14426\" data-end=\"14453\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">administrative sanctions.<\/span><\/li>\n<\/ul>\n<p data-start=\"14455\" data-end=\"14700\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">This demonstrates why nuclear development cannot be managed through general energy, construction or company law alone. Nuclear-specific regulatory requirements extend through the entire life of the facility.<\/span><\/p>\n<h3 data-section-id=\"4bihzm\" data-start=\"14707\" data-end=\"14750\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Licensing Nuclear Power Plants in T\u00fcrkiye<\/span><\/h3>\n<p data-start=\"14784\" data-end=\"15094\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Activities within the scope of Law No. 7381 may be subject to notification, registration, permission, approval or licensing. A nuclear facility cannot lawfully be constructed or operated solely on the basis of a company registration, electricity-market licence, construction contract or environmental approval. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A nuclear authorisation is a public-law instrument granted by the NDK. It may contain technical, legal, administrative and financial conditions. The NDK may alter, restrict, suspend, terminate or revoke an authorisation where the statutory conditions are met.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">An authorisation generally does not relieve its holder from obtaining other approvals required under:<\/span><\/p>\n<ul data-start=\"15460\" data-end=\"15720\">\n<li data-section-id=\"1j6znrl\" data-start=\"15460\" data-end=\"15480\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental law;<\/span><\/li>\n<li data-section-id=\"nji2ls\" data-start=\"15481\" data-end=\"15507\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">zoning and land-use law;<\/span><\/li>\n<li data-section-id=\"g7ymlj\" data-start=\"15508\" data-end=\"15547\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">coastal and construction legislation;<\/span><\/li>\n<li data-section-id=\"1sww1jd\" data-start=\"15548\" data-end=\"15580\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">electricity-market regulation;<\/span><\/li>\n<li data-section-id=\"xt0cs8\" data-start=\"15581\" data-end=\"15618\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">occupational health and safety law;<\/span><\/li>\n<li data-section-id=\"1t3v4pc\" data-start=\"15619\" data-end=\"15653\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">customs and foreign-trade rules;<\/span><\/li>\n<li data-section-id=\"vegnhk\" data-start=\"15654\" data-end=\"15681\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport legislation; or<\/span><\/li>\n<li data-section-id=\"1l9ymwl\" data-start=\"15682\" data-end=\"15720\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">other applicable regulatory regimes.<\/span><\/li>\n<\/ul>\n<p data-start=\"15751\" data-end=\"15879\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Before the principal licensing stages begin, the applicant must be recognised as the owner of the proposed nuclear installation. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Owner recognition allows the NDK to identify the legal person responsible for the project and to assess whether it possesses, or can establish, the organisational, technical and financial capacity necessary to discharge the owner\u2019s responsibilities. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Recognition as owner does not itself authorise construction or operation.<\/span><\/p>\n<p data-start=\"16224\" data-end=\"16327\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The site-licensing stage examines whether the proposed location is suitable for a nuclear installation.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Issues may include:<\/span><\/p>\n<ul data-start=\"16350\" data-end=\"16708\">\n<li data-section-id=\"klc0xn\" data-start=\"16350\" data-end=\"16375\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">geology and seismology;<\/span><\/li>\n<li data-section-id=\"4v1q5p\" data-start=\"16376\" data-end=\"16402\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">geotechnical conditions;<\/span><\/li>\n<li data-section-id=\"nzxtpx\" data-start=\"16403\" data-end=\"16432\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">hydrology and hydrogeology;<\/span><\/li>\n<li data-section-id=\"1x6ywqt\" data-start=\"16433\" data-end=\"16447\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">meteorology;<\/span><\/li>\n<li data-section-id=\"1ew6l46\" data-start=\"16448\" data-end=\"16479\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">flooding and coastal hazards;<\/span><\/li>\n<li data-section-id=\"mg8t6q\" data-start=\"16480\" data-end=\"16506\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">population distribution;<\/span><\/li>\n<li data-section-id=\"k3au9j\" data-start=\"16507\" data-end=\"16539\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">external human-induced events;<\/span><\/li>\n<li data-section-id=\"3i5u05\" data-start=\"16540\" data-end=\"16572\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental characteristics;<\/span><\/li>\n<li data-section-id=\"gao06f\" data-start=\"16573\" data-end=\"16594\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">emergency planning;<\/span><\/li>\n<li data-section-id=\"25hl97\" data-start=\"16595\" data-end=\"16623\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">access and infrastructure;<\/span><\/li>\n<li data-section-id=\"gwwblq\" data-start=\"16624\" data-end=\"16657\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cooling-water availability; and<\/span><\/li>\n<li data-section-id=\"lhay7\" data-start=\"16658\" data-end=\"16708\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">interaction with other facilities or activities.<\/span><\/li>\n<\/ul>\n<p data-start=\"16710\" data-end=\"16960\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Site suitability is a nuclear safety question distinct from an environmental impact assessment. A positive EIA decision does not automatically establish nuclear site suitability, and a nuclear site licence does not replace the environmental approval.<\/span><\/p>\n<p data-start=\"16987\" data-end=\"17117\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The construction-licensing process examines the proposed design and the applicant\u2019s arrangements for building the facility safely.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Relevant documentation may include:<\/span><\/p>\n<ul data-start=\"17156\" data-end=\"17577\">\n<li data-section-id=\"chzruq\" data-start=\"17156\" data-end=\"17194\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">preliminary safety analysis reports;<\/span><\/li>\n<li data-section-id=\"1k6zul0\" data-start=\"17195\" data-end=\"17217\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">design descriptions;<\/span><\/li>\n<li data-section-id=\"1fum2ga\" data-start=\"17218\" data-end=\"17243\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safety classifications;<\/span><\/li>\n<li data-section-id=\"1sn1ob1\" data-start=\"17244\" data-end=\"17278\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">quality-management arrangements;<\/span><\/li>\n<li data-section-id=\"jxepq9\" data-start=\"17279\" data-end=\"17305\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">construction programmes;<\/span><\/li>\n<li data-section-id=\"bfc5kx\" data-start=\"17306\" data-end=\"17342\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">organisational and staffing plans;<\/span><\/li>\n<li data-section-id=\"sbh205\" data-start=\"17343\" data-end=\"17378\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">physical-protection arrangements;<\/span><\/li>\n<li data-section-id=\"f1b46\" data-start=\"17379\" data-end=\"17406\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safeguards documentation;<\/span><\/li>\n<li data-section-id=\"1vumap2\" data-start=\"17407\" data-end=\"17440\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">emergency-planning information;<\/span><\/li>\n<li data-section-id=\"bm8jwn\" data-start=\"17441\" data-end=\"17472\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste strategies;<\/span><\/li>\n<li data-section-id=\"1u3lp6u\" data-start=\"17473\" data-end=\"17524\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">procurement and manufacturer-control systems; and<\/span><\/li>\n<li data-section-id=\"12jkn89\" data-start=\"17525\" data-end=\"17577\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">arrangements for inspection and regulatory access.<\/span><\/li>\n<\/ul>\n<p data-start=\"17579\" data-end=\"17778\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Construction may also be divided by regulatory hold points. Certain preparatory or limited works may be authorised before the full construction licence, but only within the scope expressly permitted.<\/span><\/p>\n<p data-start=\"17827\" data-end=\"17900\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Completion of physical construction does not authorise nuclear operation. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Commissioning normally includes staged testing of systems and structures to demonstrate that they perform in accordance with approved design and safety requirements. It may involve:<\/span><\/p>\n<ul data-start=\"18085\" data-end=\"18339\">\n<li data-section-id=\"5dezic\" data-start=\"18085\" data-end=\"18116\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">component and system testing;<\/span><\/li>\n<li data-section-id=\"1s5eby\" data-start=\"18117\" data-end=\"18143\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cold functional testing;<\/span><\/li>\n<li data-section-id=\"1b5w321\" data-start=\"18144\" data-end=\"18169\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">hot functional testing;<\/span><\/li>\n<li data-section-id=\"y9yshw\" data-start=\"18170\" data-end=\"18194\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">pre-operational tests;<\/span><\/li>\n<li data-section-id=\"1yvfb2q\" data-start=\"18195\" data-end=\"18220\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fuel-loading readiness;<\/span><\/li>\n<li data-section-id=\"1fo1sle\" data-start=\"18221\" data-end=\"18243\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">initial criticality;<\/span><\/li>\n<li data-section-id=\"1dtm20z\" data-start=\"18244\" data-end=\"18264\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">low-power testing;<\/span><\/li>\n<li data-section-id=\"17snzx9\" data-start=\"18265\" data-end=\"18295\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">power-ascension testing; and<\/span><\/li>\n<li data-section-id=\"p0tkq2\" data-start=\"18296\" data-end=\"18339\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">demonstration of operational performance.<\/span><\/li>\n<\/ul>\n<p data-start=\"18341\" data-end=\"18585\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Before nuclear material is brought onto the site, requirements concerning physical protection and nuclear material accounting and control must be satisfied. Emergency arrangements and operational readiness are also reviewed before fuel loading. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The operating-licence stage examines whether the facility, organisation and operating arrangements satisfy applicable regulatory requirements.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The NDK may review:<\/span><\/p>\n<ul data-start=\"18774\" data-end=\"19197\">\n<li data-section-id=\"1qyfl2\" data-start=\"18774\" data-end=\"18809\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the final safety analysis report;<\/span><\/li>\n<li data-section-id=\"1mwjbt0\" data-start=\"18810\" data-end=\"18834\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">commissioning results;<\/span><\/li>\n<li data-section-id=\"1x51ojn\" data-start=\"18835\" data-end=\"18869\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operating limits and conditions;<\/span><\/li>\n<li data-section-id=\"12jxchb\" data-start=\"18870\" data-end=\"18896\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">staffing and competency;<\/span><\/li>\n<li data-section-id=\"1b8og9i\" data-start=\"18897\" data-end=\"18918\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">management systems;<\/span><\/li>\n<li data-section-id=\"c1c0c7\" data-start=\"18919\" data-end=\"18944\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">emergency arrangements;<\/span><\/li>\n<li data-section-id=\"14kxgjq\" data-start=\"18945\" data-end=\"18982\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">security and safeguards programmes;<\/span><\/li>\n<li data-section-id=\"139zofh\" data-start=\"18983\" data-end=\"19025\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">maintenance and surveillance programmes;<\/span><\/li>\n<li data-section-id=\"1s89f0j\" data-start=\"19026\" data-end=\"19059\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ageing-management arrangements;<\/span><\/li>\n<li data-section-id=\"1lo9v5h\" data-start=\"19060\" data-end=\"19092\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation-protection measures;<\/span><\/li>\n<li data-section-id=\"13itmb8\" data-start=\"19093\" data-end=\"19125\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">waste-management arrangements;<\/span><\/li>\n<li data-section-id=\"1wjyr1c\" data-start=\"19126\" data-end=\"19164\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">insurance or financial security; and<\/span><\/li>\n<li data-section-id=\"bdu19i\" data-start=\"19165\" data-end=\"19197\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operational reporting systems.<\/span><\/li>\n<\/ul>\n<p data-start=\"19199\" data-end=\"19405\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The licence holder remains responsible for safety throughout operation. Responsibility cannot be transferred to a contractor merely through an EPC, operation and maintenance or technical-services agreement.<\/span><\/p>\n<p data-start=\"19448\" data-end=\"19571\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Significant modifications to plant design, operation, systems or safety arrangements may require prior regulatory approval.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Continued operation may also require:<\/span><\/p>\n<ul data-start=\"19612\" data-end=\"19840\">\n<li data-section-id=\"mw5ebt\" data-start=\"19612\" data-end=\"19638\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">periodic safety reviews;<\/span><\/li>\n<li data-section-id=\"1n1hy0x\" data-start=\"19639\" data-end=\"19670\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ageing-management programmes;<\/span><\/li>\n<li data-section-id=\"1u054so\" data-start=\"19671\" data-end=\"19697\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">equipment qualification;<\/span><\/li>\n<li data-section-id=\"1tris6f\" data-start=\"19698\" data-end=\"19727\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">updated hazard assessments;<\/span><\/li>\n<li data-section-id=\"yb6rxt\" data-start=\"19728\" data-end=\"19757\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity improvements;<\/span><\/li>\n<li data-section-id=\"yo2w4f\" data-start=\"19758\" data-end=\"19793\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operating-experience reviews; and<\/span><\/li>\n<li data-section-id=\"16v3e8h\" data-start=\"19794\" data-end=\"19840\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">compliance with new regulatory requirements.<\/span><\/li>\n<\/ul>\n<p data-start=\"19886\" data-end=\"19955\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The nuclear lifecycle does not end when electricity generation stops. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Decommissioning requires planning for:<\/span><\/p>\n<ul data-start=\"19997\" data-end=\"20269\">\n<li data-section-id=\"q7e7po\" data-start=\"19997\" data-end=\"20023\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">removal of nuclear fuel;<\/span><\/li>\n<li data-section-id=\"s5xy0t\" data-start=\"20024\" data-end=\"20058\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">dismantling and decontamination;<\/span><\/li>\n<li data-section-id=\"1eqw9us\" data-start=\"20059\" data-end=\"20096\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste characterisation;<\/span><\/li>\n<li data-section-id=\"eodxgx\" data-start=\"20097\" data-end=\"20131\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport, storage and disposal;<\/span><\/li>\n<li data-section-id=\"1ao19o3\" data-start=\"20132\" data-end=\"20155\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation protection;<\/span><\/li>\n<li data-section-id=\"s6ovqv\" data-start=\"20156\" data-end=\"20175\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">site remediation;<\/span><\/li>\n<li data-section-id=\"m6hv6v\" data-start=\"20176\" data-end=\"20203\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental monitoring;<\/span><\/li>\n<li data-section-id=\"1pfled1\" data-start=\"20204\" data-end=\"20220\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">financing; and<\/span><\/li>\n<li data-section-id=\"11joxsi\" data-start=\"20221\" data-end=\"20269\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">termination or transfer of regulatory control.<\/span><\/li>\n<\/ul>\n<p data-start=\"20271\" data-end=\"20444\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has adopted regulations concerning radioactive waste, spent fuel and special accounts for waste management and decommissioning.<\/span><\/p>\n<h3 data-section-id=\"ly0nfh\" data-start=\"20451\" data-end=\"20483\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Akkuyu Nuclear Power Plant<\/span><\/h3>\n<h4 data-section-id=\"1rigjus\" data-start=\"20485\" data-end=\"20529\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Intergovernmental and Corporate Structure<\/span><\/h4>\n<p data-start=\"20531\" data-end=\"20642\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Akkuyu project is based on the 2010 intergovernmental agreement between T\u00fcrkiye and the Russian Federation.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The agreement contemplated the establishment of a Turkish project company and required the Russian side\u2019s authorised entities to retain at least 51% of that company. Akkuyu Nuclear Joint Stock Company was subsequently established as the project company.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The project\u2019s build-own-operate structure differs from conventional models in which the state directly procures construction and subsequently owns and operates the completed plant. In Akkuyu, project development, ownership and future operation are concentrated in the project company, subject to Turkish licensing and regulatory control.<\/span><\/p>\n<h4 data-section-id=\"lmq2ec\" data-start=\"21238\" data-end=\"21274\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Electricity Purchase Arrangements<\/span><\/h4>\n<p data-start=\"21276\" data-end=\"21498\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The intergovernmental agreement provides for a long-term purchase arrangement covering specified proportions of electricity from the four units. The agreement\u2019s original framework contemplated the purchase for 15 years of:<\/span><\/p>\n<ul data-start=\"21500\" data-end=\"21585\">\n<li data-section-id=\"1iszhj3\" data-start=\"21500\" data-end=\"21544\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">70% of electricity from Units 1 and 2; and<\/span><\/li>\n<li data-section-id=\"uo1vqb\" data-start=\"21545\" data-end=\"21585\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">30% of electricity from Units 3 and 4,<\/span><\/li>\n<\/ul>\n<p data-start=\"21587\" data-end=\"21640\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">at the contractual price stipulated in the agreement.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Electricity outside the guaranteed quantities may be sold in the market in accordance with the applicable electricity-market framework. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">When describing these arrangements, it is important to distinguish between:<\/span><\/p>\n<ul data-start=\"21856\" data-end=\"22080\">\n<li data-section-id=\"1t83irl\" data-start=\"21856\" data-end=\"21912\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the rights created by the intergovernmental agreement;<\/span><\/li>\n<li data-section-id=\"vjr8u5\" data-start=\"21913\" data-end=\"21959\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the power-purchase implementation documents;<\/span><\/li>\n<li data-section-id=\"15ap2yt\" data-start=\"21960\" data-end=\"21990\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">electricity-market licences;<\/span><\/li>\n<li data-section-id=\"9fguwm\" data-start=\"21991\" data-end=\"22041\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">grid-connection and system-use arrangements; and<\/span><\/li>\n<li data-section-id=\"1gstavm\" data-start=\"22042\" data-end=\"22080\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the nuclear operating authorisation.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"9ddps2\" data-start=\"22082\" data-end=\"22117\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Localisation and Human Resources<\/span><\/h4>\n<p data-start=\"22119\" data-end=\"22287\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Akkuyu agreement contains provisions concerning the training of Turkish personnel and participation of Turkish businesses in procurement, services and construction. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Local participation has subsequently become an important feature of T\u00fcrkiye\u2019s broader nuclear strategy. The TNBP market report refers to substantial Turkish supplier participation and the development of a domestic nuclear industrial ecosystem. Such industry figures should be independently verified before being presented as official statistics, but localisation clearly raises important legal questions concerning supplier qualification, technology transfer, intellectual property and contractual performance.<\/span><\/p>\n<h3 data-section-id=\"fhe148\" data-start=\"22844\" data-end=\"22880\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Sinop and Further Nuclear Projects<\/span><\/h3>\n<p data-start=\"22882\" data-end=\"22961\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye\u2019s second major nuclear site is located at Sinop on the Black Sea coast. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">An earlier intergovernmental framework involving Japan was developed around a proposed project company and contemplated state participation, technology transfer and human-resource development. That particular commercial structure did not proceed to construction. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The project itself has not disappeared. T\u00dcNA\u015e has continued:<\/span><\/p>\n<ul data-start=\"23289\" data-end=\"23483\">\n<li data-section-id=\"kdqpw1\" data-start=\"23289\" data-end=\"23304\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">site studies;<\/span><\/li>\n<li data-section-id=\"ofzeql\" data-start=\"23305\" data-end=\"23332\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental assessment;<\/span><\/li>\n<li data-section-id=\"1ogec8u\" data-start=\"23333\" data-end=\"23355\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">zoning and planning;<\/span><\/li>\n<li data-section-id=\"frvh50\" data-start=\"23356\" data-end=\"23394\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">preparation of owner\u2019s requirements;<\/span><\/li>\n<li data-section-id=\"elt1rb\" data-start=\"23395\" data-end=\"23424\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">infrastructure development;<\/span><\/li>\n<li data-section-id=\"4t2vil\" data-start=\"23425\" data-end=\"23460\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">owner-recognition procedures; and<\/span><\/li>\n<li data-section-id=\"g4a5r3\" data-start=\"23461\" data-end=\"23483\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">site-licensing work.<\/span><\/li>\n<\/ul>\n<p data-start=\"23485\" data-end=\"23733\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00dcNA\u015e reports that Sinop obtained a positive environmental impact assessment decision in September 2020, that the NDK recognised T\u00dcNA\u015e as owner in January 2023 and that a site-licence application was submitted. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">This distinction should be maintained throughout the article &#8220;<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><em>The termination or non-implementation of an earlier commercial partnership does not necessarily terminate the state\u2019s nuclear project for that site<\/em>&#8220;.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has also considered additional nuclear capacity in Thrace. The precise vendor, technology, ownership, financing and contracting structure of any such project will depend on future agreements and regulatory processes.<\/span><\/p>\n<h3 data-section-id=\"74zlne\" data-start=\"24181\" data-end=\"24205\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Small Modular Reactors<\/span><\/h3>\n<p data-start=\"24207\" data-end=\"24330\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Small modular reactors, generally referred to as <strong data-start=\"24256\" data-end=\"24264\">SMRs<\/strong>, are increasingly relevant to T\u00fcrkiye\u2019s long-term nuclear policy. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">SMRs may differ from conventional large reactors in several respects:<\/span><\/p>\n<ul data-start=\"24403\" data-end=\"24689\">\n<li data-section-id=\"vc7m1e\" data-start=\"24403\" data-end=\"24429\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">lower output per module;<\/span><\/li>\n<li data-section-id=\"yb9bni\" data-start=\"24430\" data-end=\"24458\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">factory-based manufacture;<\/span><\/li>\n<li data-section-id=\"vpq9cg\" data-start=\"24459\" data-end=\"24490\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">modular or phased deployment;<\/span><\/li>\n<li data-section-id=\"hgpu5u\" data-start=\"24491\" data-end=\"24514\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">standardised designs;<\/span><\/li>\n<li data-section-id=\"7vw38o\" data-start=\"24515\" data-end=\"24564\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">potential deployment near industrial consumers;<\/span><\/li>\n<li data-section-id=\"2n6f91\" data-start=\"24565\" data-end=\"24640\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">possible use for electricity, process heat, hydrogen or desalination; and<\/span><\/li>\n<li data-section-id=\"dd2g5c\" data-start=\"24641\" data-end=\"24689\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">different financing and construction profiles.<\/span><\/li>\n<\/ul>\n<p data-start=\"24691\" data-end=\"24898\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has stated that its nuclear-capacity ambitions include SMRs, and T\u00dcNA\u015e has conducted a project assessing SMR designs from technical and financial perspectives. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The existing legal framework is sufficiently broad to subject an SMR to nuclear authorisation, safety, security, safeguards and liability requirements. Nevertheless, practical regulatory questions may arise concerning:<\/span><\/p>\n<ul data-start=\"25120\" data-end=\"25453\">\n<li data-section-id=\"1p071eu\" data-start=\"25120\" data-end=\"25138\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">design approval;<\/span><\/li>\n<li data-section-id=\"1sq6lnq\" data-start=\"25139\" data-end=\"25180\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">factory manufacture in another country;<\/span><\/li>\n<li data-section-id=\"zhu5ww\" data-start=\"25181\" data-end=\"25201\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">serial production;<\/span><\/li>\n<li data-section-id=\"17smhhs\" data-start=\"25202\" data-end=\"25225\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport of modules;<\/span><\/li>\n<li data-section-id=\"d5oiwt\" data-start=\"25226\" data-end=\"25263\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">licensing multiple identical units;<\/span><\/li>\n<li data-section-id=\"1ubeg4n\" data-start=\"25264\" data-end=\"25291\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">emergency-planning zones;<\/span><\/li>\n<li data-section-id=\"1942ufa\" data-start=\"25292\" data-end=\"25321\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">multi-module control rooms;<\/span><\/li>\n<li data-section-id=\"1fn8d2t\" data-start=\"25322\" data-end=\"25342\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operator staffing;<\/span><\/li>\n<li data-section-id=\"k48qix\" data-start=\"25343\" data-end=\"25384\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">co-location with industrial facilities;<\/span><\/li>\n<li data-section-id=\"1ip6tsc\" data-start=\"25385\" data-end=\"25402\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">shared systems;<\/span><\/li>\n<li data-section-id=\"1akjn4k\" data-start=\"25403\" data-end=\"25416\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safeguards;<\/span><\/li>\n<li data-section-id=\"hknbzy\" data-start=\"25417\" data-end=\"25434\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">spent fuel; and<\/span><\/li>\n<li data-section-id=\"1tvnv9m\" data-start=\"25435\" data-end=\"25453\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">decommissioning.<\/span><\/li>\n<\/ul>\n<p data-start=\"25455\" data-end=\"25795\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The legal treatment of an SMR project will depend not merely on its generating capacity but on its technology, site, fuel, intended application and risk profile. The IBA analysis similarly identifies the need to consider how T\u00fcrkiye\u2019s existing legal framework will apply to emerging SMR technologies.<\/span><\/p>\n<h3 data-section-id=\"src25q\" data-start=\"25802\" data-end=\"25843\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Safety, Security and Safeguards<\/span><\/h3>\n<h4 data-section-id=\"9pqnob\" data-start=\"25845\" data-end=\"25862\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Safety<\/span><\/h4>\n<p data-start=\"25864\" data-end=\"25966\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear safety concerns the prevention of accidents and mitigation of their radiological consequences. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The operator must maintain safety throughout:<\/span><\/p>\n<ul data-start=\"26015\" data-end=\"26190\">\n<li data-section-id=\"1rb370u\" data-start=\"26015\" data-end=\"26033\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">site evaluation;<\/span><\/li>\n<li data-section-id=\"1jmrugx\" data-start=\"26034\" data-end=\"26043\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">design;<\/span><\/li>\n<li data-section-id=\"e37ay5\" data-start=\"26044\" data-end=\"26058\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">procurement;<\/span><\/li>\n<li data-section-id=\"1evbjsm\" data-start=\"26059\" data-end=\"26073\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">manufacture;<\/span><\/li>\n<li data-section-id=\"1v9ydam\" data-start=\"26074\" data-end=\"26089\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">construction;<\/span><\/li>\n<li data-section-id=\"1ddd42m\" data-start=\"26090\" data-end=\"26106\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">commissioning;<\/span><\/li>\n<li data-section-id=\"muigkm\" data-start=\"26107\" data-end=\"26119\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operation;<\/span><\/li>\n<li data-section-id=\"18jbrql\" data-start=\"26120\" data-end=\"26135\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">modification;<\/span><\/li>\n<li data-section-id=\"r1ghkr\" data-start=\"26136\" data-end=\"26147\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">shutdown;<\/span><\/li>\n<li data-section-id=\"rt1i1g\" data-start=\"26148\" data-end=\"26170\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">decommissioning; and<\/span><\/li>\n<li data-section-id=\"1rsish\" data-start=\"26171\" data-end=\"26190\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">waste management.<\/span><\/li>\n<\/ul>\n<p data-start=\"26192\" data-end=\"26335\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The operator has primary responsibility for safety. Regulatory approval, inspection or review does not transfer that responsibility to the NDK.<\/span><\/p>\n<h4 data-section-id=\"1jjcks1\" data-start=\"26337\" data-end=\"26356\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Security<\/span><\/h4>\n<p data-start=\"26358\" data-end=\"26444\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear security concerns protection against intentional unauthorised acts, including:<\/span><\/p>\n<ul data-start=\"26446\" data-end=\"26621\">\n<li data-section-id=\"13hjogo\" data-start=\"26446\" data-end=\"26474\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">theft of nuclear material;<\/span><\/li>\n<li data-section-id=\"y6mtgb\" data-start=\"26475\" data-end=\"26486\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sabotage;<\/span><\/li>\n<li data-section-id=\"oasr8i\" data-start=\"26487\" data-end=\"26509\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">unauthorised access;<\/span><\/li>\n<li data-section-id=\"jlh66z\" data-start=\"26510\" data-end=\"26537\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">malicious cyber activity;<\/span><\/li>\n<li data-section-id=\"rclaxp\" data-start=\"26538\" data-end=\"26576\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">unlawful transport interference; and<\/span><\/li>\n<li data-section-id=\"u96ujg\" data-start=\"26577\" data-end=\"26621\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">acts of nuclear or radiological terrorism.<\/span><\/li>\n<\/ul>\n<p data-start=\"26623\" data-end=\"26657\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Security arrangements may involve:<\/span><\/p>\n<ul data-start=\"26659\" data-end=\"26890\">\n<li data-section-id=\"o7vkvc\" data-start=\"26659\" data-end=\"26679\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">physical barriers;<\/span><\/li>\n<li data-section-id=\"1qeh677\" data-start=\"26680\" data-end=\"26698\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">access controls;<\/span><\/li>\n<li data-section-id=\"3vvv69\" data-start=\"26699\" data-end=\"26723\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">personnel reliability;<\/span><\/li>\n<li data-section-id=\"ia2oq8\" data-start=\"26724\" data-end=\"26752\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">protected and vital areas;<\/span><\/li>\n<li data-section-id=\"11l1zuu\" data-start=\"26753\" data-end=\"26774\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport security;<\/span><\/li>\n<li data-section-id=\"1bjslze\" data-start=\"26775\" data-end=\"26791\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity;<\/span><\/li>\n<li data-section-id=\"23lxgp\" data-start=\"26792\" data-end=\"26815\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">contingency planning;<\/span><\/li>\n<li data-section-id=\"mwhs2\" data-start=\"26816\" data-end=\"26849\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">information classification; and<\/span><\/li>\n<li data-section-id=\"a5skc\" data-start=\"26850\" data-end=\"26890\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cooperation with security authorities.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"1vku4v\" data-start=\"26892\" data-end=\"26927\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Safeguards and Non-Proliferation<\/span><\/h4>\n<p data-start=\"26929\" data-end=\"27009\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Safeguards are intended to verify that nuclear material remains in peaceful use. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Relevant obligations may include:<\/span><\/p>\n<ul data-start=\"27046\" data-end=\"27219\">\n<li data-section-id=\"zvxda3\" data-start=\"27046\" data-end=\"27076\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear material accounting;<\/span><\/li>\n<li data-section-id=\"arljm0\" data-start=\"27077\" data-end=\"27094\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">record-keeping;<\/span><\/li>\n<li data-section-id=\"138dzr1\" data-start=\"27095\" data-end=\"27107\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">reporting;<\/span><\/li>\n<li data-section-id=\"1ka84nf\" data-start=\"27108\" data-end=\"27139\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">measurement and verification;<\/span><\/li>\n<li data-section-id=\"2fgw4e\" data-start=\"27140\" data-end=\"27154\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">inspections;<\/span><\/li>\n<li data-section-id=\"1o7akeu\" data-start=\"27155\" data-end=\"27190\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">containment and surveillance; and<\/span><\/li>\n<li data-section-id=\"1t4tyzs\" data-start=\"27191\" data-end=\"27219\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cooperation with the IAEA.<\/span><\/li>\n<\/ul>\n<p data-start=\"27221\" data-end=\"27357\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The legal and operational arrangements for safety, security and safeguards must be coordinated without treating them as interchangeable.<\/span><\/p>\n<h1 data-section-id=\"oenlti\" data-start=\"27364\" data-end=\"27413\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">International Nuclear Law Applicable to T\u00fcrkiye<\/span><\/h1>\n<p data-start=\"27415\" data-end=\"27515\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye participates in a broad international legal framework governing peaceful nuclear activities.<\/span><\/p>\n<h4 data-section-id=\"wyhafu\" data-start=\"27517\" data-end=\"27557\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Safety and Emergency Response<\/span><\/h4>\n<p data-start=\"27559\" data-end=\"27589\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Important instruments include:<\/span><\/p>\n<ul data-start=\"27591\" data-end=\"27897\">\n<li data-section-id=\"8i8fw6\" data-start=\"27591\" data-end=\"27626\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Convention on Nuclear Safety;<\/span><\/li>\n<li data-section-id=\"ooio7z\" data-start=\"27627\" data-end=\"27688\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Convention on Early Notification of a Nuclear Accident;<\/span><\/li>\n<li data-section-id=\"15drtf4\" data-start=\"27689\" data-end=\"27784\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Convention on Assistance in the Case of a Nuclear Accident or Radiological Emergency; and<\/span><\/li>\n<li data-section-id=\"mjhcku\" data-start=\"27785\" data-end=\"27897\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management.<\/span><\/li>\n<\/ul>\n<p data-start=\"27899\" data-end=\"28009\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">These instruments promote national safety responsibilities, international notification, assistance and review.<\/span><\/p>\n<h4 data-section-id=\"17v5eto\" data-start=\"28011\" data-end=\"28054\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Security and Physical Protection<\/span><\/h4>\n<p data-start=\"28056\" data-end=\"28085\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Relevant instruments include:<\/span><\/p>\n<ul data-start=\"28087\" data-end=\"28428\">\n<li data-section-id=\"83tsnb\" data-start=\"28087\" data-end=\"28151\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Convention on the Physical Protection of Nuclear Material;<\/span><\/li>\n<li data-section-id=\"10ln0ei\" data-start=\"28152\" data-end=\"28187\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the Amendment to that Convention;<\/span><\/li>\n<li data-section-id=\"1sq1kms\" data-start=\"28188\" data-end=\"28268\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the International Convention for the Suppression of Acts of Nuclear Terrorism;<\/span><\/li>\n<li data-section-id=\"gunk6x\" data-start=\"28269\" data-end=\"28346\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the International Convention for the Suppression of Terrorist Bombings; and<\/span><\/li>\n<li data-section-id=\"bmyc4y\" data-start=\"28347\" data-end=\"28428\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the International Convention for the Suppression of the Financing of Terrorism.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"g4bomn\" data-start=\"28430\" data-end=\"28465\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Non-Proliferation and Safeguards<\/span><\/h4>\n<p data-start=\"28467\" data-end=\"28591\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye is a party to the Treaty on the Non-Proliferation of Nuclear Weapons and is subject to IAEA safeguards arrangements. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">These obligations are particularly important when contracts involve:<\/span><\/p>\n<ul data-start=\"28663\" data-end=\"28858\">\n<li data-section-id=\"xr1856\" data-start=\"28663\" data-end=\"28682\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear material;<\/span><\/li>\n<li data-section-id=\"1ui3esz\" data-start=\"28683\" data-end=\"28706\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">controlled equipment;<\/span><\/li>\n<li data-section-id=\"kzrlcp\" data-start=\"28707\" data-end=\"28730\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sensitive technology;<\/span><\/li>\n<li data-section-id=\"1ll0g3c\" data-start=\"28731\" data-end=\"28756\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fuel-cycle information;<\/span><\/li>\n<li data-section-id=\"1j44kue\" data-start=\"28757\" data-end=\"28780\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technical assistance;<\/span><\/li>\n<li data-section-id=\"18gj4we\" data-start=\"28781\" data-end=\"28807\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">research cooperation; or<\/span><\/li>\n<li data-section-id=\"1iawd7c\" data-start=\"28808\" data-end=\"28858\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">international transfer of nuclear-related items.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"102x6ps\" data-start=\"28860\" data-end=\"28892\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Third-Party Liability<\/span><\/h4>\n<p data-start=\"28894\" data-end=\"29069\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye is a party to the Paris Convention on Third Party Liability in the Field of Nuclear Energy and to the Joint Protocol connecting the Paris and Vienna liability regimes. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Law No. 7381 provides the principal domestic rules concerning operator liability, compensation, insurance and jurisdiction. The OECD\/NEA country profile identifies the Law as T\u00fcrkiye\u2019s primary nuclear-liability legislation.<\/span><\/p>\n<h3 data-section-id=\"17ykgay\" data-start=\"29341\" data-end=\"29377\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Civil Liability for Nuclear Damage<\/span><\/h3>\n<h4 data-section-id=\"j68ouh\" data-start=\"29379\" data-end=\"29398\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Strict Liability<\/span><\/h4>\n<p data-start=\"29400\" data-end=\"29462\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Law No. 7381 imposes strict liability on the nuclear operator. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The injured person is not generally required to prove that the operator acted negligently. The claimant must establish the nuclear incident, recoverable nuclear damage and the necessary causal connection. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Strict liability reflects the exceptional nature of nuclear risk and the difficulty that injured parties might otherwise face in proving technical fault.<\/span><\/p>\n<h4 data-section-id=\"1ht88yz\" data-start=\"29825\" data-end=\"29861\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Legal Channelling to the Operator<\/span><\/h4>\n<p data-start=\"29863\" data-end=\"29979\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear-liability law generally channels liability to the operator rather than distributing primary liability among:<\/span><\/p>\n<ul data-start=\"29981\" data-end=\"30123\">\n<li data-section-id=\"ocbmqq\" data-start=\"29981\" data-end=\"29993\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">employees;<\/span><\/li>\n<li data-section-id=\"wtfwbp\" data-start=\"29994\" data-end=\"30006\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">designers;<\/span><\/li>\n<li data-section-id=\"1sdltg7\" data-start=\"30007\" data-end=\"30023\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">manufacturers;<\/span><\/li>\n<li data-section-id=\"wg8d5e\" data-start=\"30024\" data-end=\"30051\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">construction contractors;<\/span><\/li>\n<li data-section-id=\"fkjqm6\" data-start=\"30052\" data-end=\"30074\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">equipment suppliers;<\/span><\/li>\n<li data-section-id=\"1fa7ccs\" data-start=\"30075\" data-end=\"30102\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology providers; and<\/span><\/li>\n<li data-section-id=\"5fw5ru\" data-start=\"30103\" data-end=\"30123\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">service companies.<\/span><\/li>\n<\/ul>\n<p data-start=\"30125\" data-end=\"30225\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">This principle provides a clearly identifiable defendant and supports the availability of insurance. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Legal channelling does not mean that contractors have no contractual exposure. The operator may have contractual rights concerning:<\/span><\/p>\n<ul data-start=\"30360\" data-end=\"30464\">\n<li data-section-id=\"ybmijw\" data-start=\"30360\" data-end=\"30369\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">breach;<\/span><\/li>\n<li data-section-id=\"1avjj5y\" data-start=\"30370\" data-end=\"30378\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">delay;<\/span><\/li>\n<li data-section-id=\"anvu46\" data-start=\"30379\" data-end=\"30401\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">defective equipment;<\/span><\/li>\n<li data-section-id=\"1w67u4\" data-start=\"30402\" data-end=\"30419\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">non-compliance;<\/span><\/li>\n<li data-section-id=\"rc68no\" data-start=\"30420\" data-end=\"30434\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">indemnities;<\/span><\/li>\n<li data-section-id=\"1xu599m\" data-start=\"30435\" data-end=\"30452\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">warranties; and<\/span><\/li>\n<li data-section-id=\"1wye7vy\" data-start=\"30453\" data-end=\"30464\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">recourse,<\/span><\/li>\n<\/ul>\n<p data-start=\"30466\" data-end=\"30552\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">subject to mandatory nuclear-liability rules and the terms of the relevant agreements.<\/span><\/p>\n<h4 data-section-id=\"13xa91g\" data-start=\"30554\" data-end=\"30573\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Liability Limits<\/span><\/h4>\n<p data-start=\"30575\" data-end=\"30650\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Law establishes different limits according to the facility or activity. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The existing article identifies the following categories:<\/span><\/p>\n<ul data-start=\"30711\" data-end=\"31021\">\n<li data-section-id=\"5ue8os\" data-start=\"30711\" data-end=\"30851\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EUR 700 million for nuclear reactors exceeding the applicable thermal threshold and other facilities placed in the corresponding category;<\/span><\/li>\n<li data-section-id=\"nzzv50\" data-start=\"30852\" data-end=\"30898\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EUR 70 million for other nuclear facilities;<\/span><\/li>\n<li data-section-id=\"4645ye\" data-start=\"30899\" data-end=\"30954\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EUR 80 million for transport of nuclear material; and<\/span><\/li>\n<li data-section-id=\"15en5uk\" data-start=\"30955\" data-end=\"31021\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EUR 700 million for transit of nuclear material through T\u00fcrkiye.<\/span><\/li>\n<\/ul>\n<p data-start=\"31023\" data-end=\"31225\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The precise applicable amount should be confirmed against the current statutory text, the classification made by the NDK and any amendments or applicable international rules at the time of the incident.<\/span><\/p>\n<h4 data-section-id=\"1a2e18q\" data-start=\"31227\" data-end=\"31271\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Mandatory Insurance or Financial Security<\/span><\/h4>\n<p data-start=\"31273\" data-end=\"31392\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">An operator must maintain insurance or another acceptable financial guarantee corresponding to its potential liability. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The NDK is authorised to determine whether the operator has fulfilled its financial-security obligations. The insurance arrangements must be maintained in a manner consistent with the facility, activity, liability amount and licence conditions. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Potential claimants may, within the statutory framework, pursue claims against the operator and the relevant insurer or financial-guarantee provider.<\/span><\/p>\n<h4 data-section-id=\"pj208b\" data-start=\"31791\" data-end=\"31823\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Public Compensation Mechanism<\/span><\/h4>\n<p data-start=\"31825\" data-end=\"32027\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Where nuclear damage exceeds available operator liability and financial security, the Law contemplates a public compensation mechanism and the establishment of a Nuclear Damage Determination Commission.<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Commission\u2019s role may include receiving applications, assessing claims and administering compensation in accordance with the statutory framework.<\/span><\/p>\n<h4 data-section-id=\"1w10ikq\" data-start=\"32180\" data-end=\"32193\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Exclusions<\/span><\/h4>\n<p data-start=\"32195\" data-end=\"32320\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The operator may be exempt from liability where nuclear damage results directly from specified exceptional events, including:<\/span><\/p>\n<ul data-start=\"32322\" data-end=\"32386\">\n<li data-section-id=\"1sq0t8a\" data-start=\"32322\" data-end=\"32339\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">armed conflict;<\/span><\/li>\n<li data-section-id=\"m1qeac\" data-start=\"32340\" data-end=\"32354\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">hostilities;<\/span><\/li>\n<li data-section-id=\"1sxuu0j\" data-start=\"32355\" data-end=\"32370\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">civil war; or<\/span><\/li>\n<li data-section-id=\"1rowzct\" data-start=\"32371\" data-end=\"32386\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">insurrection.<\/span><\/li>\n<\/ul>\n<p data-start=\"32388\" data-end=\"32500\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Any exclusion should be interpreted within the text of Law No. 7381 and the applicable international convention.<\/span><\/p>\n<h4 data-section-id=\"2hq1iz\" data-start=\"32502\" data-end=\"32523\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Limitation Periods<\/span><\/h4>\n<p data-start=\"32525\" data-end=\"32600\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Law provides different long-stop periods for different types of damage. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The existing statutory framework provides:<\/span><\/p>\n<ul data-start=\"32646\" data-end=\"32751\">\n<li data-section-id=\"1ag1453\" data-start=\"32646\" data-end=\"32708\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">30 years for claims concerning death or personal injury; and<\/span><\/li>\n<li data-section-id=\"1ybfxn6\" data-start=\"32709\" data-end=\"32751\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">10 years for other categories of damage,<\/span><\/li>\n<\/ul>\n<p data-start=\"32753\" data-end=\"32873\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">calculated from the nuclear incident, subject to the full rules governing knowledge, filing and procedural requirements.<\/span><\/p>\n<h4 data-section-id=\"1y8arzq\" data-start=\"32875\" data-end=\"32894\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Competent Courts<\/span><\/h4>\n<p data-start=\"32896\" data-end=\"33131\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Turkish courts have jurisdiction over nuclear incidents occurring within T\u00fcrkiye in the circumstances defined by the applicable legal regime. Law No. 7381 assigns jurisdiction in covered nuclear-damage proceedings to the Ankara courts.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">This special jurisdiction should be distinguished from the resolution of contractual disputes between the operator, EPC contractor, supplier or other project participants, which may be subject to arbitration.<\/span><\/p>\n<h3 data-section-id=\"5l2yk5\" data-start=\"33348\" data-end=\"33393\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Environmental Assessment, Land and Planning<\/span><\/h3>\n<p data-start=\"33395\" data-end=\"33518\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A nuclear project requires compliance with both nuclear licensing rules and general environmental and planning legislation. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Relevant legal issues may include:<\/span><\/p>\n<ul data-start=\"33556\" data-end=\"33928\">\n<li data-section-id=\"k97n3z\" data-start=\"33556\" data-end=\"33590\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental impact assessment;<\/span><\/li>\n<li data-section-id=\"z2ycuj\" data-start=\"33591\" data-end=\"33614\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">public participation;<\/span><\/li>\n<li data-section-id=\"c5axma\" data-start=\"33615\" data-end=\"33644\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">coastal and marine impacts;<\/span><\/li>\n<li data-section-id=\"1b6jwhj\" data-start=\"33645\" data-end=\"33682\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cooling-water intake and discharge;<\/span><\/li>\n<li data-section-id=\"2x310s\" data-start=\"33683\" data-end=\"33698\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">biodiversity;<\/span><\/li>\n<li data-section-id=\"1e9cnp\" data-start=\"33699\" data-end=\"33714\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">water rights;<\/span><\/li>\n<li data-section-id=\"1sixlqu\" data-start=\"33715\" data-end=\"33737\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">waste and emissions;<\/span><\/li>\n<li data-section-id=\"1pxp3ag\" data-start=\"33738\" data-end=\"33753\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">zoning plans;<\/span><\/li>\n<li data-section-id=\"144nuxp\" data-start=\"33754\" data-end=\"33773\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">land acquisition;<\/span><\/li>\n<li data-section-id=\"123hl11\" data-start=\"33774\" data-end=\"33790\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">expropriation;<\/span><\/li>\n<li data-section-id=\"jgn4ay\" data-start=\"33791\" data-end=\"33814\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">construction permits;<\/span><\/li>\n<li data-section-id=\"dm2gen\" data-start=\"33815\" data-end=\"33852\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cultural and archaeological assets;<\/span><\/li>\n<li data-section-id=\"dksc81\" data-start=\"33853\" data-end=\"33864\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">forestry;<\/span><\/li>\n<li data-section-id=\"zhyir0\" data-start=\"33865\" data-end=\"33890\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">emergency planning; and<\/span><\/li>\n<li data-section-id=\"1fy948r\" data-start=\"33891\" data-end=\"33928\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">long-term environmental monitoring.<\/span><\/li>\n<\/ul>\n<p data-start=\"33930\" data-end=\"34010\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The EIA process and the nuclear site-licensing process serve different purposes. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">An EIA examines the project\u2019s environmental effects under environmental legislation. The NDK separately determines whether the site and proposed facility satisfy nuclear safety requirements. A project may therefore require both a positive EIA decision and a nuclear site licence, together with further administrative permits.<\/span><\/p>\n<h3 data-section-id=\"fgpcqp\" data-start=\"34344\" data-end=\"34382\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Procurement and Market Entry<\/span><\/h3>\n<h4 data-section-id=\"1bdqfn6\" data-start=\"34384\" data-end=\"34418\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Different Levels of Procurement<\/span><\/h4>\n<p data-start=\"34420\" data-end=\"34484\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear procurement in T\u00fcrkiye may take place at several levels. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">At the highest level, the selection of a reactor vendor and project structure may be influenced by:<\/span><\/p>\n<ul data-start=\"34587\" data-end=\"34806\">\n<li data-section-id=\"1ur42db\" data-start=\"34587\" data-end=\"34620\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">intergovernmental negotiations;<\/span><\/li>\n<li data-section-id=\"1fiekgr\" data-start=\"34621\" data-end=\"34645\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sovereign commitments;<\/span><\/li>\n<li data-section-id=\"ivat3\" data-start=\"34646\" data-end=\"34667\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">financing packages;<\/span><\/li>\n<li data-section-id=\"1n7q79o\" data-start=\"34668\" data-end=\"34700\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology-transfer proposals;<\/span><\/li>\n<li data-section-id=\"1ss6jdm\" data-start=\"34701\" data-end=\"34728\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fuel-supply arrangements;<\/span><\/li>\n<li data-section-id=\"esw6ex\" data-start=\"34729\" data-end=\"34744\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">localisation;<\/span><\/li>\n<li data-section-id=\"11uvkc9\" data-start=\"34745\" data-end=\"34779\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">geopolitical considerations; and<\/span><\/li>\n<li data-section-id=\"83msst\" data-start=\"34780\" data-end=\"34806\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">long-term energy policy.<\/span><\/li>\n<\/ul>\n<p data-start=\"34808\" data-end=\"34859\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Below that level, procurement may be undertaken by:<\/span><\/p>\n<ul data-start=\"34861\" data-end=\"35022\">\n<li data-section-id=\"1u8je6w\" data-start=\"34861\" data-end=\"34883\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the project company;<\/span><\/li>\n<li data-section-id=\"1ou5ywh\" data-start=\"34884\" data-end=\"34918\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the reactor technology provider;<\/span><\/li>\n<li data-section-id=\"flrvhv\" data-start=\"34919\" data-end=\"34940\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the EPC contractor;<\/span><\/li>\n<li data-section-id=\"s55ooe\" data-start=\"34941\" data-end=\"34969\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">major package contractors;<\/span><\/li>\n<li data-section-id=\"pskwd3\" data-start=\"34970\" data-end=\"34988\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the operator; or<\/span><\/li>\n<li data-section-id=\"uzmrxm\" data-start=\"34989\" data-end=\"35022\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">public or state-owned entities.<\/span><\/li>\n<\/ul>\n<p data-start=\"35024\" data-end=\"35251\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The applicable legal regime should be determined for each procurement. Not every procurement by a nuclear project company is automatically a public tender, and not every public-sector procurement is governed in the same manner.<\/span><\/p>\n<h4 data-section-id=\"1vguhw8\" data-start=\"35253\" data-end=\"35297\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear-Specific Procurement Requirements<\/span><\/h4>\n<p data-start=\"35299\" data-end=\"35331\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear procurement may require:<\/span><\/p>\n<ul data-start=\"35333\" data-end=\"35783\">\n<li data-section-id=\"1k3htbu\" data-start=\"35333\" data-end=\"35370\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safety classification of equipment;<\/span><\/li>\n<li data-section-id=\"13y8ywb\" data-start=\"35371\" data-end=\"35405\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear-grade quality assurance;<\/span><\/li>\n<li data-section-id=\"1s5ea49\" data-start=\"35406\" data-end=\"35434\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">approval of manufacturers;<\/span><\/li>\n<li data-section-id=\"ivv7ht\" data-start=\"35435\" data-end=\"35461\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technical qualification;<\/span><\/li>\n<li data-section-id=\"52wy9t\" data-start=\"35462\" data-end=\"35490\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">traceability of materials;<\/span><\/li>\n<li data-section-id=\"70ts84\" data-start=\"35491\" data-end=\"35515\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">configuration control;<\/span><\/li>\n<li data-section-id=\"1xdd0cw\" data-start=\"35516\" data-end=\"35541\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">inspection and testing;<\/span><\/li>\n<li data-section-id=\"10jluto\" data-start=\"35542\" data-end=\"35568\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">preservation of records;<\/span><\/li>\n<li data-section-id=\"c9t8b3\" data-start=\"35569\" data-end=\"35617\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">prevention of counterfeit or fraudulent items;<\/span><\/li>\n<li data-section-id=\"1jm4p2u\" data-start=\"35618\" data-end=\"35637\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">regulator access;<\/span><\/li>\n<li data-section-id=\"1g6dl17\" data-start=\"35638\" data-end=\"35671\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">approval before subcontracting;<\/span><\/li>\n<li data-section-id=\"18lnt0l\" data-start=\"35672\" data-end=\"35698\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity assurance;<\/span><\/li>\n<li data-section-id=\"sffva2\" data-start=\"35699\" data-end=\"35730\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export-control screening; and<\/span><\/li>\n<li data-section-id=\"18i62dy\" data-start=\"35731\" data-end=\"35783\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">flow-down of requirements to lower-tier suppliers.<\/span><\/li>\n<\/ul>\n<p data-start=\"35785\" data-end=\"35982\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has adopted a dedicated regulation governing the procurement process for equipment intended for nuclear facilities and the approval of manufacturers.<\/span><\/p>\n<h4 data-section-id=\"hidmzr\" data-start=\"35984\" data-end=\"36009\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Supplier Due Diligence<\/span><\/h4>\n<p data-start=\"36011\" data-end=\"36099\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">International and Turkish participants should conduct enhanced due diligence addressing:<\/span><\/p>\n<ul data-start=\"36101\" data-end=\"36482\">\n<li data-section-id=\"2wuysf\" data-start=\"36101\" data-end=\"36148\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">corporate ownership and beneficial ownership;<\/span><\/li>\n<li data-section-id=\"9xne1c\" data-start=\"36149\" data-end=\"36172\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technical capability;<\/span><\/li>\n<li data-section-id=\"j7x7m6\" data-start=\"36173\" data-end=\"36194\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">financial capacity;<\/span><\/li>\n<li data-section-id=\"14cqje\" data-start=\"36195\" data-end=\"36220\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear certifications;<\/span><\/li>\n<li data-section-id=\"bh9ftc\" data-start=\"36221\" data-end=\"36242\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sanctions exposure;<\/span><\/li>\n<li data-section-id=\"hylx8g\" data-start=\"36243\" data-end=\"36271\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export-control compliance;<\/span><\/li>\n<li data-section-id=\"d0b89b\" data-start=\"36272\" data-end=\"36295\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">anti-bribery systems;<\/span><\/li>\n<li data-section-id=\"17nwze5\" data-start=\"36296\" data-end=\"36317\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">quality management;<\/span><\/li>\n<li data-section-id=\"1bjslze\" data-start=\"36318\" data-end=\"36334\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity;<\/span><\/li>\n<li data-section-id=\"y2nu00\" data-start=\"36335\" data-end=\"36371\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">litigation and regulatory history;<\/span><\/li>\n<li data-section-id=\"1mtcpcl\" data-start=\"36372\" data-end=\"36394\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">occupational safety;<\/span><\/li>\n<li data-section-id=\"13batxf\" data-start=\"36395\" data-end=\"36420\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">document retention; and<\/span><\/li>\n<li data-section-id=\"5kzkxz\" data-start=\"36421\" data-end=\"36482\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ability to comply with nuclear safety culture requirements.<\/span><\/li>\n<\/ul>\n<p data-start=\"36484\" data-end=\"36620\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">In a nuclear project, a deficiency at a lower supplier tier may affect licensing, safety, commissioning and the entire project schedule.<\/span><\/p>\n<h3 data-section-id=\"enj7vp\" data-start=\"36627\" data-end=\"36667\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear EPC and Construction Contracts<\/span><\/h3>\n<h4 data-section-id=\"yojmo3\" data-start=\"36669\" data-end=\"36697\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Contractual Structure<\/span><\/h4>\n<p data-start=\"36699\" data-end=\"36795\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A nuclear project commonly involves a network of agreements rather than one standalone contract. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">These may include:<\/span><\/p>\n<ul data-start=\"36817\" data-end=\"37347\">\n<li data-section-id=\"1pn099i\" data-start=\"36817\" data-end=\"36850\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">an intergovernmental agreement;<\/span><\/li>\n<li data-section-id=\"vacp6h\" data-start=\"36851\" data-end=\"36902\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">shareholders\u2019 and project-development agreements;<\/span><\/li>\n<li data-section-id=\"1yegifw\" data-start=\"36903\" data-end=\"36935\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">reactor technology agreements;<\/span><\/li>\n<li data-section-id=\"1mbmkye\" data-start=\"36936\" data-end=\"36984\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EPC or engineering and construction contracts;<\/span><\/li>\n<li data-section-id=\"1x9rh89\" data-start=\"36985\" data-end=\"37009\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">civil works contracts;<\/span><\/li>\n<li data-section-id=\"oiz4sf\" data-start=\"37010\" data-end=\"37040\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">turbine-generator contracts;<\/span><\/li>\n<li data-section-id=\"1j5z7ly\" data-start=\"37041\" data-end=\"37088\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear island and balance-of-plant packages;<\/span><\/li>\n<li data-section-id=\"snsftx\" data-start=\"37089\" data-end=\"37118\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">grid-connection agreements;<\/span><\/li>\n<li data-section-id=\"ff86tm\" data-start=\"37119\" data-end=\"37144\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear fuel contracts;<\/span><\/li>\n<li data-section-id=\"awlnhu\" data-start=\"37145\" data-end=\"37175\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">equipment-supply agreements;<\/span><\/li>\n<li data-section-id=\"1pud80i\" data-start=\"37176\" data-end=\"37207\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">long-term service agreements;<\/span><\/li>\n<li data-section-id=\"1gtf20t\" data-start=\"37208\" data-end=\"37249\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operation and maintenance arrangements;<\/span><\/li>\n<li data-section-id=\"va57ra\" data-start=\"37250\" data-end=\"37272\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">training agreements;<\/span><\/li>\n<li data-section-id=\"nvgdin\" data-start=\"37273\" data-end=\"37294\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">insurance policies;<\/span><\/li>\n<li data-section-id=\"1w8x0gw\" data-start=\"37295\" data-end=\"37322\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">financing agreements; and<\/span><\/li>\n<li data-section-id=\"prxsob\" data-start=\"37323\" data-end=\"37347\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">numerous subcontracts.<\/span><\/li>\n<\/ul>\n<p data-start=\"37349\" data-end=\"37549\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The contracts should be designed as an integrated structure. Inconsistent provisions concerning completion, force majeure, liability or dispute resolution may generate gaps or conflicting obligations.<\/span><\/p>\n<h4 data-section-id=\"4sx6q\" data-start=\"37551\" data-end=\"37578\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Scope and Interface Risk<\/span><\/h4>\n<p data-start=\"37580\" data-end=\"37644\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A nuclear EPC contract must clearly allocate responsibility for:<\/span><\/p>\n<ul data-start=\"37646\" data-end=\"37970\">\n<li data-section-id=\"835us3\" data-start=\"37646\" data-end=\"37671\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">engineering and design;<\/span><\/li>\n<li data-section-id=\"jx4ed8\" data-start=\"37672\" data-end=\"37692\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">design adaptation;<\/span><\/li>\n<li data-section-id=\"e37ay5\" data-start=\"37693\" data-end=\"37707\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">procurement;<\/span><\/li>\n<li data-section-id=\"181ubkn\" data-start=\"37708\" data-end=\"37729\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">civil construction;<\/span><\/li>\n<li data-section-id=\"ybnx98\" data-start=\"37730\" data-end=\"37754\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">equipment manufacture;<\/span><\/li>\n<li data-section-id=\"6vwku3\" data-start=\"37755\" data-end=\"37779\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport and customs;<\/span><\/li>\n<li data-section-id=\"1iopea7\" data-start=\"37780\" data-end=\"37795\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">installation;<\/span><\/li>\n<li data-section-id=\"1aldiki\" data-start=\"37796\" data-end=\"37816\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">licensing support;<\/span><\/li>\n<li data-section-id=\"5r2neh\" data-start=\"37817\" data-end=\"37844\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">regulatory documentation;<\/span><\/li>\n<li data-section-id=\"p95tap\" data-start=\"37845\" data-end=\"37865\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">quality assurance;<\/span><\/li>\n<li data-section-id=\"nc6p6t\" data-start=\"37866\" data-end=\"37876\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">testing;<\/span><\/li>\n<li data-section-id=\"1ddd42m\" data-start=\"37877\" data-end=\"37893\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">commissioning;<\/span><\/li>\n<li data-section-id=\"1ypavcj\" data-start=\"37894\" data-end=\"37905\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">training;<\/span><\/li>\n<li data-section-id=\"slfvvm\" data-start=\"37906\" data-end=\"37920\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">spare parts;<\/span><\/li>\n<li data-section-id=\"11qtpps\" data-start=\"37921\" data-end=\"37949\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operational readiness; and<\/span><\/li>\n<li data-section-id=\"170akao\" data-start=\"37950\" data-end=\"37970\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">long-term support.<\/span><\/li>\n<\/ul>\n<p data-start=\"37972\" data-end=\"38101\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Where different contractors control different packages, interface risk becomes critical. Responsibility matrices should identify:<\/span><\/p>\n<ul data-start=\"38103\" data-end=\"38317\">\n<li data-section-id=\"164b1a7\" data-start=\"38103\" data-end=\"38123\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">design boundaries;<\/span><\/li>\n<li data-section-id=\"1h6o18k\" data-start=\"38124\" data-end=\"38147\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">information exchange;<\/span><\/li>\n<li data-section-id=\"1pvpomp\" data-start=\"38148\" data-end=\"38170\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">access and handover;<\/span><\/li>\n<li data-section-id=\"rl7r96\" data-start=\"38171\" data-end=\"38189\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">temporary works;<\/span><\/li>\n<li data-section-id=\"1w4zoy0\" data-start=\"38190\" data-end=\"38211\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">system integration;<\/span><\/li>\n<li data-section-id=\"fcgdhv\" data-start=\"38212\" data-end=\"38233\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">testing interfaces;<\/span><\/li>\n<li data-section-id=\"vy56ne\" data-start=\"38234\" data-end=\"38263\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">commissioning sequence; and<\/span><\/li>\n<li data-section-id=\"kcfjxi\" data-start=\"38264\" data-end=\"38317\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">responsibility for delay affecting another package.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"12tweep\" data-start=\"38319\" data-end=\"38347\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Regulatory Responsibility<\/span><\/h4>\n<p data-start=\"38349\" data-end=\"38570\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The parties may contractually allocate responsibility for preparing reports, responding to regulator questions and supporting licence applications. They cannot, however, contract out of mandatory statutory responsibility. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The owner and licence holder remain accountable to the NDK for matters assigned to them by law. The contract should therefore specify:<\/span><\/p>\n<ul data-start=\"38708\" data-end=\"39072\">\n<li data-section-id=\"1vzd6by\" data-start=\"38708\" data-end=\"38750\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">who prepares each regulatory submission;<\/span><\/li>\n<li data-section-id=\"17qagkf\" data-start=\"38751\" data-end=\"38795\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">who owns and controls the supporting data;<\/span><\/li>\n<li data-section-id=\"9cozm7\" data-start=\"38796\" data-end=\"38847\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">who bears the cost of regulator-required changes;<\/span><\/li>\n<li data-section-id=\"ijkes6\" data-start=\"38848\" data-end=\"38902\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">who responds to requests for additional information;<\/span><\/li>\n<li data-section-id=\"1ve61ui\" data-start=\"38903\" data-end=\"38976\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">what happens when a vendor refuses to disclose proprietary information;<\/span><\/li>\n<li data-section-id=\"1oun9g7\" data-start=\"38977\" data-end=\"39021\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">whether approval is a condition precedent;<\/span><\/li>\n<li data-section-id=\"h91g03\" data-start=\"39022\" data-end=\"39072\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and how regulatory delay affects time and price.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"12yhlur\" data-start=\"39074\" data-end=\"39102\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Completion and Acceptance<\/span><\/h4>\n<p data-start=\"39104\" data-end=\"39177\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear construction cannot ordinarily be reduced to one completion date. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Relevant milestones may include:<\/span><\/p>\n<ul data-start=\"39213\" data-end=\"39491\">\n<li data-section-id=\"tz3wdx\" data-start=\"39213\" data-end=\"39241\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">completion of civil works;<\/span><\/li>\n<li data-section-id=\"1jlbr7g\" data-start=\"39242\" data-end=\"39266\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">mechanical completion;<\/span><\/li>\n<li data-section-id=\"1c3say7\" data-start=\"39267\" data-end=\"39282\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">energisation;<\/span><\/li>\n<li data-section-id=\"1slngbp\" data-start=\"39283\" data-end=\"39301\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">system turnover;<\/span><\/li>\n<li data-section-id=\"k0b2v5\" data-start=\"39302\" data-end=\"39317\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cold testing;<\/span><\/li>\n<li data-section-id=\"t8ejrq\" data-start=\"39318\" data-end=\"39332\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">hot testing;<\/span><\/li>\n<li data-section-id=\"1yvfb2q\" data-start=\"39333\" data-end=\"39358\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fuel-loading readiness;<\/span><\/li>\n<li data-section-id=\"10cw97q\" data-start=\"39359\" data-end=\"39379\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">first criticality;<\/span><\/li>\n<li data-section-id=\"1suz0v1\" data-start=\"39380\" data-end=\"39398\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">grid connection;<\/span><\/li>\n<li data-section-id=\"1677nhp\" data-start=\"39399\" data-end=\"39417\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">power ascension;<\/span><\/li>\n<li data-section-id=\"17cagke\" data-start=\"39418\" data-end=\"39443\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">provisional acceptance;<\/span><\/li>\n<li data-section-id=\"xd8c8h\" data-start=\"39444\" data-end=\"39471\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">commercial operation; and<\/span><\/li>\n<li data-section-id=\"1tjngpv\" data-start=\"39472\" data-end=\"39491\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">final acceptance.<\/span><\/li>\n<\/ul>\n<p data-start=\"39493\" data-end=\"39574\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The contract should define the legal and financial consequence of each milestone.<\/span><\/p>\n<h4 data-section-id=\"2x6yaj\" data-start=\"39576\" data-end=\"39608\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Delay and Performance Damages<\/span><\/h4>\n<p data-start=\"39610\" data-end=\"39713\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Delay liquidated damages may apply where the contractor fails to achieve a specified milestone on time. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Performance liquidated damages may apply where the completed facility fails to achieve:<\/span><\/p>\n<ul data-start=\"39804\" data-end=\"39957\">\n<li data-section-id=\"niycyz\" data-start=\"39804\" data-end=\"39833\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">required electrical output;<\/span><\/li>\n<li data-section-id=\"yf3w3z\" data-start=\"39834\" data-end=\"39855\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">thermal efficiency;<\/span><\/li>\n<li data-section-id=\"1pbh31e\" data-start=\"39856\" data-end=\"39871\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">availability;<\/span><\/li>\n<li data-section-id=\"stqfyt\" data-start=\"39872\" data-end=\"39901\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safety-related performance;<\/span><\/li>\n<li data-section-id=\"1k9lymj\" data-start=\"39902\" data-end=\"39926\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fuel-cycle targets; or<\/span><\/li>\n<li data-section-id=\"qah90m\" data-start=\"39927\" data-end=\"39957\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">other guaranteed parameters.<\/span><\/li>\n<\/ul>\n<p data-start=\"39959\" data-end=\"39987\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The contract should address:<\/span><\/p>\n<ul data-start=\"39989\" data-end=\"40239\">\n<li data-section-id=\"13ac3sb\" data-start=\"39989\" data-end=\"40018\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">separate or aggregate caps;<\/span><\/li>\n<li data-section-id=\"6n0jdo\" data-start=\"40019\" data-end=\"40046\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">exclusive-remedy wording;<\/span><\/li>\n<li data-section-id=\"xx29sz\" data-start=\"40047\" data-end=\"40072\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">termination thresholds;<\/span><\/li>\n<li data-section-id=\"128ujel\" data-start=\"40073\" data-end=\"40089\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">relief events;<\/span><\/li>\n<li data-section-id=\"1so6ipd\" data-start=\"40090\" data-end=\"40119\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">interaction with insurance;<\/span><\/li>\n<li data-section-id=\"109xbpa\" data-start=\"40120\" data-end=\"40239\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and whether nuclear safety or regulatory non-compliance is excluded from ordinary limitation-of-liability provisions.<\/span><\/li>\n<\/ul>\n<h2 data-section-id=\"8rt4ym\" data-start=\"40241\" data-end=\"40257\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Change in Law<\/span><\/h2>\n<p data-start=\"40259\" data-end=\"40325\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Long project durations make legal change particularly significant. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A change-in-law clause should address:<\/span><\/p>\n<ul data-start=\"40367\" data-end=\"40647\">\n<li data-section-id=\"1o5hg3h\" data-start=\"40367\" data-end=\"40401\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">new nuclear safety requirements;<\/span><\/li>\n<li data-section-id=\"8ywmox\" data-start=\"40402\" data-end=\"40428\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">new regulatory guidance;<\/span><\/li>\n<li data-section-id=\"1lw33l6\" data-start=\"40429\" data-end=\"40457\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental obligations;<\/span><\/li>\n<li data-section-id=\"kzcdxc\" data-start=\"40458\" data-end=\"40484\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">customs and tax changes;<\/span><\/li>\n<li data-section-id=\"s1xs5f\" data-start=\"40485\" data-end=\"40497\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sanctions;<\/span><\/li>\n<li data-section-id=\"7gppyb\" data-start=\"40498\" data-end=\"40516\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export controls;<\/span><\/li>\n<li data-section-id=\"vw85xi\" data-start=\"40517\" data-end=\"40546\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity requirements;<\/span><\/li>\n<li data-section-id=\"16o9cm1\" data-start=\"40547\" data-end=\"40564\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">employment law;<\/span><\/li>\n<li data-section-id=\"1v92klx\" data-start=\"40565\" data-end=\"40593\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">localisation requirements;<\/span><\/li>\n<li data-section-id=\"1snqhgt\" data-start=\"40594\" data-end=\"40647\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and changes arising from international commitments.<\/span><\/li>\n<\/ul>\n<p data-start=\"40649\" data-end=\"40794\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The clause should distinguish between foreseeable regulatory development and an exceptional change occurring after the contractual baseline date.<\/span><\/p>\n<h4 data-section-id=\"goir78\" data-start=\"40796\" data-end=\"40840\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Force Majeure and Supply-Chain Disruption<\/span><\/h4>\n<p data-start=\"40842\" data-end=\"40923\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear projects depend on specialised components and cross-border supply chains. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Contracts should address:<\/span><\/p>\n<ul data-start=\"40952\" data-end=\"41251\">\n<li data-section-id=\"8g4m3d\" data-start=\"40952\" data-end=\"40964\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">pandemics;<\/span><\/li>\n<li data-section-id=\"1sq0t8a\" data-start=\"40965\" data-end=\"40982\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">armed conflict;<\/span><\/li>\n<li data-section-id=\"et1db1\" data-start=\"40983\" data-end=\"41001\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">border closures;<\/span><\/li>\n<li data-section-id=\"s1xs5f\" data-start=\"41002\" data-end=\"41014\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sanctions;<\/span><\/li>\n<li data-section-id=\"1el1ma3\" data-start=\"41015\" data-end=\"41040\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export-licence refusal;<\/span><\/li>\n<li data-section-id=\"qfl9wy\" data-start=\"41041\" data-end=\"41060\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">blocked payments;<\/span><\/li>\n<li data-section-id=\"zr75t\" data-start=\"41061\" data-end=\"41082\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">state intervention;<\/span><\/li>\n<li data-section-id=\"1z022t0\" data-start=\"41083\" data-end=\"41105\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">shipping disruption;<\/span><\/li>\n<li data-section-id=\"16zhkhw\" data-start=\"41106\" data-end=\"41140\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">loss of a critical manufacturer;<\/span><\/li>\n<li data-section-id=\"rvq8or\" data-start=\"41141\" data-end=\"41185\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">inability to source an approved component;<\/span><\/li>\n<li data-section-id=\"vv4w8j\" data-start=\"41186\" data-end=\"41219\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">prolonged regulatory delay; and<\/span><\/li>\n<li data-section-id=\"ing3vq\" data-start=\"41220\" data-end=\"41251\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">extraordinary natural events.<\/span><\/li>\n<\/ul>\n<p data-start=\"41253\" data-end=\"41625\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The TNBP report notes that Akkuyu\u2019s project timeline has been affected by pandemic disruption, equipment-supply constraints and financing complications. These assertions illustrate the contractual importance of supply-chain and payment risks, although individual causes and their legal consequences require independent verification.<\/span><\/p>\n<h3 data-section-id=\"1k5ycc9\" data-start=\"41632\" data-end=\"41675\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Localisation and Industrial Participation<\/span><\/h3>\n<p data-start=\"41677\" data-end=\"41755\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye\u2019s nuclear strategy places significant emphasis on domestic capability. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Localisation may involve:<\/span><\/p>\n<ul data-start=\"41784\" data-end=\"42052\">\n<li data-section-id=\"r2imzp\" data-start=\"41784\" data-end=\"41817\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Turkish construction companies;<\/span><\/li>\n<li data-section-id=\"1rjaabb\" data-start=\"41818\" data-end=\"41853\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">domestic equipment manufacturing;<\/span><\/li>\n<li data-section-id=\"hbi1j4\" data-start=\"41854\" data-end=\"41876\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Turkish engineering;<\/span><\/li>\n<li data-section-id=\"1f5xiho\" data-start=\"41877\" data-end=\"41901\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">workforce development;<\/span><\/li>\n<li data-section-id=\"1ypavcj\" data-start=\"41902\" data-end=\"41913\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">training;<\/span><\/li>\n<li data-section-id=\"1qgl15i\" data-start=\"41914\" data-end=\"41939\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">supplier qualification;<\/span><\/li>\n<li data-section-id=\"z60wn1\" data-start=\"41940\" data-end=\"41957\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">joint ventures;<\/span><\/li>\n<li data-section-id=\"1e9iz3n\" data-start=\"41958\" data-end=\"41981\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">research cooperation;<\/span><\/li>\n<li data-section-id=\"11tr0kg\" data-start=\"41982\" data-end=\"42009\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology licensing; and<\/span><\/li>\n<li data-section-id=\"24bwt5\" data-start=\"42010\" data-end=\"42052\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">development of regional export capacity.<\/span><\/li>\n<\/ul>\n<p data-start=\"42054\" data-end=\"42137\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Local-content obligations should be expressed through measurable contractual terms. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Issues include:<\/span><\/p>\n<ul data-start=\"42156\" data-end=\"42451\">\n<li data-section-id=\"g3x1z6\" data-start=\"42156\" data-end=\"42194\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">what expenditure qualifies as local;<\/span><\/li>\n<li data-section-id=\"v7kjz1\" data-start=\"42195\" data-end=\"42229\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">how local content is calculated;<\/span><\/li>\n<li data-section-id=\"itkag\" data-start=\"42230\" data-end=\"42262\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">whether imported inputs count;<\/span><\/li>\n<li data-section-id=\"1ua5a5t\" data-start=\"42263\" data-end=\"42300\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">required percentages or milestones;<\/span><\/li>\n<li data-section-id=\"g8h1p9\" data-start=\"42301\" data-end=\"42327\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">approved supplier lists;<\/span><\/li>\n<li data-section-id=\"138dzr1\" data-start=\"42328\" data-end=\"42340\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">reporting;<\/span><\/li>\n<li data-section-id=\"3nzvi\" data-start=\"42341\" data-end=\"42352\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">auditing;<\/span><\/li>\n<li data-section-id=\"rstkhl\" data-start=\"42353\" data-end=\"42378\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">remedies for shortfall;<\/span><\/li>\n<li data-section-id=\"ofbhav\" data-start=\"42379\" data-end=\"42395\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">substitutions;<\/span><\/li>\n<li data-section-id=\"l5bt9r\" data-start=\"42396\" data-end=\"42451\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and interaction with competition and procurement law.<\/span><\/li>\n<\/ul>\n<p data-start=\"42453\" data-end=\"42810\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The TNBP report presents Akkuyu as having generated substantial local participation and refers to hundreds of Turkish companies with nuclear construction exposure. These figures provide useful market context, but they should be attributed to the report unless confirmed through official project or government records.<\/span><\/p>\n<h3 data-section-id=\"2qqk4b\" data-start=\"42817\" data-end=\"42864\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Technology Transfer and Intellectual Property<\/span><\/h3>\n<p data-start=\"42866\" data-end=\"42949\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Technology transfer is likely to be central to future nuclear project negotiations. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">It may include:<\/span><\/p>\n<ul data-start=\"42968\" data-end=\"43276\">\n<li data-section-id=\"453v3v\" data-start=\"42968\" data-end=\"43018\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">licences to use reactor or component technology;<\/span><\/li>\n<li data-section-id=\"1vagxm4\" data-start=\"43019\" data-end=\"43052\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">access to design documentation;<\/span><\/li>\n<li data-section-id=\"cy75kj\" data-start=\"43053\" data-end=\"43078\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">manufacturing know-how;<\/span><\/li>\n<li data-section-id=\"1j44kue\" data-start=\"43079\" data-end=\"43102\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technical assistance;<\/span><\/li>\n<li data-section-id=\"2l0tc1\" data-start=\"43103\" data-end=\"43124\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">personnel training;<\/span><\/li>\n<li data-section-id=\"r49pmk\" data-start=\"43125\" data-end=\"43136\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">software;<\/span><\/li>\n<li data-section-id=\"e7y7mq\" data-start=\"43137\" data-end=\"43163\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">maintenance information;<\/span><\/li>\n<li data-section-id=\"178ibg\" data-start=\"43164\" data-end=\"43203\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">localisation of component production;<\/span><\/li>\n<li data-section-id=\"1aja9mg\" data-start=\"43204\" data-end=\"43231\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">research cooperation; and<\/span><\/li>\n<li data-section-id=\"1rjfwyp\" data-start=\"43232\" data-end=\"43276\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">rights to manufacture for regional export.<\/span><\/li>\n<\/ul>\n<p data-start=\"43278\" data-end=\"43316\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Agreements should distinguish between:<\/span><\/p>\n<ul data-start=\"43318\" data-end=\"43516\">\n<li data-section-id=\"1iho7dd\" data-start=\"43318\" data-end=\"43355\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">pre-existing intellectual property;<\/span><\/li>\n<li data-section-id=\"4fzrm8\" data-start=\"43356\" data-end=\"43397\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">project-specific intellectual property;<\/span><\/li>\n<li data-section-id=\"1d5gqqw\" data-start=\"43398\" data-end=\"43413\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">improvements;<\/span><\/li>\n<li data-section-id=\"kcxtuq\" data-start=\"43414\" data-end=\"43433\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">derivative works;<\/span><\/li>\n<li data-section-id=\"3mwv37\" data-start=\"43434\" data-end=\"43455\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">manufacturing data;<\/span><\/li>\n<li data-section-id=\"132xfa9\" data-start=\"43456\" data-end=\"43480\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">confidential know-how;<\/span><\/li>\n<li data-section-id=\"15pa7yz\" data-start=\"43481\" data-end=\"43500\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operational data;<\/span><\/li>\n<li data-section-id=\"3a67qa\" data-start=\"43501\" data-end=\"43516\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and software.<\/span><\/li>\n<\/ul>\n<p data-start=\"43518\" data-end=\"43557\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Particular attention should be paid to:<\/span><\/p>\n<ul data-start=\"43559\" data-end=\"43844\">\n<li data-section-id=\"1cqf7o2\" data-start=\"43559\" data-end=\"43575\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">permitted use;<\/span><\/li>\n<li data-section-id=\"1jjgscp\" data-start=\"43576\" data-end=\"43591\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sublicensing;<\/span><\/li>\n<li data-section-id=\"142mycg\" data-start=\"43592\" data-end=\"43613\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">territorial limits;<\/span><\/li>\n<li data-section-id=\"nke56q\" data-start=\"43614\" data-end=\"43642\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ownership of improvements;<\/span><\/li>\n<li data-section-id=\"isk8kk\" data-start=\"43643\" data-end=\"43665\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">employee inventions;<\/span><\/li>\n<li data-section-id=\"hfrmrl\" data-start=\"43666\" data-end=\"43692\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">post-termination rights;<\/span><\/li>\n<li data-section-id=\"1mlv17p\" data-start=\"43693\" data-end=\"43711\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">confidentiality;<\/span><\/li>\n<li data-section-id=\"1kcw37x\" data-start=\"43712\" data-end=\"43738\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">trade-secret protection;<\/span><\/li>\n<li data-section-id=\"1bjslze\" data-start=\"43739\" data-end=\"43755\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity;<\/span><\/li>\n<li data-section-id=\"11gjmq2\" data-start=\"43756\" data-end=\"43777\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">source-code access;<\/span><\/li>\n<li data-section-id=\"1snmg8h\" data-start=\"43778\" data-end=\"43812\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export-control restrictions; and<\/span><\/li>\n<li data-section-id=\"gbr2mx\" data-start=\"43813\" data-end=\"43844\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">unauthorised onward transfer.<\/span><\/li>\n<\/ul>\n<p data-start=\"43846\" data-end=\"44059\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Contractual access to technology remains subject to mandatory export controls and sanctions. A licence agreement cannot lawfully authorise transfer prohibited by the law of the exporting or importing jurisdiction.<\/span><\/p>\n<h3 data-section-id=\"lk6h9f\" data-start=\"44066\" data-end=\"44114\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Export Controls, Sanctions and Customs<\/span><\/h3>\n<h4 data-section-id=\"7gum3b\" data-start=\"44116\" data-end=\"44143\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Export-Control Framework<\/span><\/h4>\n<p data-start=\"44145\" data-end=\"44275\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear equipment, material, software and technical data may be subject to special export, import, transit and re-export controls.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has adopted a Regulation on Nuclear Export Control. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Depending on the transaction, parties may need to consider:<\/span><\/p>\n<ul data-start=\"44439\" data-end=\"44718\">\n<li data-section-id=\"uvq2tp\" data-start=\"44439\" data-end=\"44478\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Turkish nuclear export authorisation;<\/span><\/li>\n<li data-section-id=\"wzo5gl\" data-start=\"44479\" data-end=\"44504\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">customs classification;<\/span><\/li>\n<li data-section-id=\"1oqsi9h\" data-start=\"44505\" data-end=\"44525\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">dual-use controls;<\/span><\/li>\n<li data-section-id=\"17ajxxp\" data-start=\"44526\" data-end=\"44562\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">end-user and end-use restrictions;<\/span><\/li>\n<li data-section-id=\"1t14z7c\" data-start=\"44563\" data-end=\"44599\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear supplier-country licences;<\/span><\/li>\n<li data-section-id=\"13w11yb\" data-start=\"44600\" data-end=\"44620\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">re-export consent;<\/span><\/li>\n<li data-section-id=\"1w2y5v8\" data-start=\"44621\" data-end=\"44656\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology-transfer restrictions;<\/span><\/li>\n<li data-section-id=\"s1xs5f\" data-start=\"44657\" data-end=\"44669\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sanctions;<\/span><\/li>\n<li data-section-id=\"1qt7r67\" data-start=\"44670\" data-end=\"44696\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">anti-diversion controls;<\/span><\/li>\n<li data-section-id=\"19n8p3q\" data-start=\"44697\" data-end=\"44718\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and record-keeping.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"b1y72k\" data-start=\"44720\" data-end=\"44757\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Controlled Technology and Services<\/span><\/h4>\n<p data-start=\"44759\" data-end=\"44827\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Export controls can apply not only to physical products but also to:<\/span><\/p>\n<ul data-start=\"44829\" data-end=\"45001\">\n<li data-section-id=\"pa01o3\" data-start=\"44829\" data-end=\"44850\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technical drawings;<\/span><\/li>\n<li data-section-id=\"2wv9ab\" data-start=\"44851\" data-end=\"44865\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">source code;<\/span><\/li>\n<li data-section-id=\"bigc6w\" data-start=\"44866\" data-end=\"44883\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">remote support;<\/span><\/li>\n<li data-section-id=\"14t0qme\" data-start=\"44884\" data-end=\"44899\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cloud access;<\/span><\/li>\n<li data-section-id=\"wh5aec\" data-start=\"44900\" data-end=\"44923\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">engineering services;<\/span><\/li>\n<li data-section-id=\"1ypavcj\" data-start=\"44924\" data-end=\"44935\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">training;<\/span><\/li>\n<li data-section-id=\"1c9q3b7\" data-start=\"44936\" data-end=\"44966\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">electronic transfer of data;<\/span><\/li>\n<li data-section-id=\"os1hxd\" data-start=\"44967\" data-end=\"45001\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and access by foreign nationals.<\/span><\/li>\n<\/ul>\n<p data-start=\"45003\" data-end=\"45183\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Technology-transfer and procurement contracts should allocate responsibility for obtaining licences and should address the consequences of refusal, delay, suspension or revocation.<\/span><\/p>\n<h4 data-section-id=\"16cutdi\" data-start=\"45185\" data-end=\"45202\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Sanctions Risk<\/span><\/h4>\n<p data-start=\"45204\" data-end=\"45330\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear projects often involve multiple jurisdictions, state-owned entities, financial institutions and specialised suppliers.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Sanctions due diligence should cover:<\/span><\/p>\n<ul data-start=\"45371\" data-end=\"45534\">\n<li data-section-id=\"1c7ttov\" data-start=\"45371\" data-end=\"45388\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">counterparties;<\/span><\/li>\n<li data-section-id=\"5piq2t\" data-start=\"45389\" data-end=\"45409\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">beneficial owners;<\/span><\/li>\n<li data-section-id=\"1c63qpy\" data-start=\"45410\" data-end=\"45418\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">banks;<\/span><\/li>\n<li data-section-id=\"1b1lbh6\" data-start=\"45419\" data-end=\"45429\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">vessels;<\/span><\/li>\n<li data-section-id=\"1k9elt0\" data-start=\"45430\" data-end=\"45441\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">insurers;<\/span><\/li>\n<li data-section-id=\"17f8x05\" data-start=\"45442\" data-end=\"45455\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology;<\/span><\/li>\n<li data-section-id=\"46wgsy\" data-start=\"45456\" data-end=\"45479\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">origin of components;<\/span><\/li>\n<li data-section-id=\"lrne1a\" data-start=\"45480\" data-end=\"45499\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">payment currency;<\/span><\/li>\n<li data-section-id=\"yh9yim\" data-start=\"45500\" data-end=\"45517\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">intermediaries;<\/span><\/li>\n<li data-section-id=\"xhvmv4\" data-start=\"45518\" data-end=\"45534\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and end users.<\/span><\/li>\n<\/ul>\n<p data-start=\"45536\" data-end=\"45773\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The contract should not merely contain a general warranty of sanctions compliance. It should address blocked payments, alternative banks, licence applications, substitution, suspension, termination and responsibility for resulting costs.<\/span><\/p>\n<h3 data-section-id=\"qe4j7p\" data-start=\"45780\" data-end=\"45848\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Cybersecurity, Artificial Intelligence and Digital Nuclear Systems<\/span><\/h3>\n<p data-start=\"45850\" data-end=\"45994\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Modern nuclear facilities depend on digital instrumentation, control systems, communications, data platforms and software-supported maintenance. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Legal and contractual questions include:<\/span><\/p>\n<ul data-start=\"46038\" data-end=\"46451\">\n<li data-section-id=\"uinfg1\" data-start=\"46038\" data-end=\"46075\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">classification of critical systems;<\/span><\/li>\n<li data-section-id=\"14rper3\" data-start=\"46076\" data-end=\"46127\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">separation of operational and corporate networks;<\/span><\/li>\n<li data-section-id=\"fsszjn\" data-start=\"46128\" data-end=\"46144\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">remote access;<\/span><\/li>\n<li data-section-id=\"ynhpwz\" data-start=\"46145\" data-end=\"46161\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">vendor access;<\/span><\/li>\n<li data-section-id=\"4lqa66\" data-start=\"46162\" data-end=\"46181\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">software updates;<\/span><\/li>\n<li data-section-id=\"582pis\" data-start=\"46182\" data-end=\"46209\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">vulnerability management;<\/span><\/li>\n<li data-section-id=\"15bgqro\" data-start=\"46210\" data-end=\"46237\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cyber incident reporting;<\/span><\/li>\n<li data-section-id=\"vgsxu4\" data-start=\"46238\" data-end=\"46264\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">supply-chain cyber risk;<\/span><\/li>\n<li data-section-id=\"192qt55\" data-start=\"46265\" data-end=\"46285\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">data localisation;<\/span><\/li>\n<li data-section-id=\"s4sxpz\" data-start=\"46286\" data-end=\"46315\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cross-border data transfer;<\/span><\/li>\n<li data-section-id=\"1czkvb4\" data-start=\"46316\" data-end=\"46338\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">penetration testing;<\/span><\/li>\n<li data-section-id=\"1eud3s8\" data-start=\"46339\" data-end=\"46370\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">source-code access or escrow;<\/span><\/li>\n<li data-section-id=\"jgj1xg\" data-start=\"46371\" data-end=\"46403\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">maintenance of legacy systems;<\/span><\/li>\n<li data-section-id=\"1wn7720\" data-start=\"46404\" data-end=\"46451\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and allocation of liability for cyber events.<\/span><\/li>\n<\/ul>\n<p data-start=\"46453\" data-end=\"46492\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Artificial intelligence may be used in:<\/span><\/p>\n<ul data-start=\"46494\" data-end=\"46643\">\n<li data-section-id=\"1th5g95\" data-start=\"46494\" data-end=\"46519\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">predictive maintenance;<\/span><\/li>\n<li data-section-id=\"w1if6t\" data-start=\"46520\" data-end=\"46540\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">anomaly detection;<\/span><\/li>\n<li data-section-id=\"10qfevp\" data-start=\"46541\" data-end=\"46564\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">equipment monitoring;<\/span><\/li>\n<li data-section-id=\"1vcc5zm\" data-start=\"46565\" data-end=\"46586\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">workforce planning;<\/span><\/li>\n<li data-section-id=\"u0w6zy\" data-start=\"46587\" data-end=\"46607\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">document analysis;<\/span><\/li>\n<li data-section-id=\"8jhrze\" data-start=\"46608\" data-end=\"46643\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and operational decision support.<\/span><\/li>\n<\/ul>\n<p data-start=\"46645\" data-end=\"46882\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Use of AI does not displace the operator\u2019s regulatory responsibility. AI-supported systems should be assessed according to their function, safety significance, data quality, explainability, cybersecurity and human-oversight arrangements. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The TNBP report identifies cybersecurity, predictive maintenance and digital services as areas of increasing commercial importance in T\u00fcrkiye\u2019s developing nuclear market.<\/span><\/p>\n<h3 data-section-id=\"c3b536\" data-start=\"47101\" data-end=\"47135\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Radioactive Waste and Spent Fuel<\/span><\/h3>\n<p data-start=\"47137\" data-end=\"47259\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Radioactive waste management is a continuing legal responsibility, not a matter that may be postponed until plant closure. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Relevant requirements concern:<\/span><\/p>\n<ul data-start=\"47293\" data-end=\"47480\">\n<li data-section-id=\"1bumfcq\" data-start=\"47293\" data-end=\"47308\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">minimisation;<\/span><\/li>\n<li data-section-id=\"f9x691\" data-start=\"47309\" data-end=\"47326\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">classification;<\/span><\/li>\n<li data-section-id=\"1cy4393\" data-start=\"47327\" data-end=\"47339\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">treatment;<\/span><\/li>\n<li data-section-id=\"19jnd8g\" data-start=\"47340\" data-end=\"47355\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">conditioning;<\/span><\/li>\n<li data-section-id=\"12m0dgq\" data-start=\"47356\" data-end=\"47366\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">storage;<\/span><\/li>\n<li data-section-id=\"5p2bf4\" data-start=\"47367\" data-end=\"47379\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport;<\/span><\/li>\n<li data-section-id=\"bugtak\" data-start=\"47380\" data-end=\"47391\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">disposal;<\/span><\/li>\n<li data-section-id=\"arljm0\" data-start=\"47392\" data-end=\"47409\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">record-keeping;<\/span><\/li>\n<li data-section-id=\"3o9sud\" data-start=\"47410\" data-end=\"47421\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">security;<\/span><\/li>\n<li data-section-id=\"1akjn4k\" data-start=\"47422\" data-end=\"47435\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safeguards;<\/span><\/li>\n<li data-section-id=\"m6hv6v\" data-start=\"47436\" data-end=\"47463\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental monitoring;<\/span><\/li>\n<li data-section-id=\"1t3r1mo\" data-start=\"47464\" data-end=\"47480\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and financing.<\/span><\/li>\n<\/ul>\n<p data-start=\"47482\" data-end=\"47624\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Spent fuel may require separate arrangements depending on the reactor, fuel-supply agreement, intergovernmental framework and national policy. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye has regulations governing:<\/span><\/p>\n<ul data-start=\"47662\" data-end=\"47887\">\n<li data-section-id=\"8adcjo\" data-start=\"47662\" data-end=\"47708\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste and spent fuel management;<\/span><\/li>\n<li data-section-id=\"qmags9\" data-start=\"47709\" data-end=\"47740\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste facilities;<\/span><\/li>\n<li data-section-id=\"zpc7hd\" data-start=\"47741\" data-end=\"47758\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safe transport;<\/span><\/li>\n<li data-section-id=\"1ao19o3\" data-start=\"47759\" data-end=\"47782\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation protection;<\/span><\/li>\n<li data-section-id=\"4d7q9k\" data-start=\"47783\" data-end=\"47887\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and special accounts for waste management and decommissioning.<\/span><\/li>\n<\/ul>\n<p data-start=\"47889\" data-end=\"47934\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Contracts should identify responsibility for:<\/span><\/p>\n<ul data-start=\"47936\" data-end=\"48112\">\n<li data-section-id=\"1qbr467\" data-start=\"47936\" data-end=\"47962\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ownership of spent fuel;<\/span><\/li>\n<li data-section-id=\"e0duxk\" data-start=\"47963\" data-end=\"47988\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">return or reprocessing;<\/span><\/li>\n<li data-section-id=\"5p2bf4\" data-start=\"47989\" data-end=\"48001\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transport;<\/span><\/li>\n<li data-section-id=\"b827fu\" data-start=\"48002\" data-end=\"48020\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">interim storage;<\/span><\/li>\n<li data-section-id=\"fslchs\" data-start=\"48021\" data-end=\"48038\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">final disposal;<\/span><\/li>\n<li data-section-id=\"1bf61aj\" data-start=\"48039\" data-end=\"48047\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">costs;<\/span><\/li>\n<li data-section-id=\"b01id7\" data-start=\"48048\" data-end=\"48065\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">title and risk;<\/span><\/li>\n<li data-section-id=\"1akjn4k\" data-start=\"48066\" data-end=\"48079\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">safeguards;<\/span><\/li>\n<li data-section-id=\"mtff9e\" data-start=\"48080\" data-end=\"48112\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and liability during transfer.<\/span><\/li>\n<\/ul>\n<h3 data-section-id=\"5bzpop\" data-start=\"48119\" data-end=\"48156\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Emergency Preparedness and Response<\/span><\/h3>\n<p data-start=\"48158\" data-end=\"48218\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear emergency arrangements require coordination between:<\/span><\/p>\n<ul data-start=\"48220\" data-end=\"48462\">\n<li data-section-id=\"szhze\" data-start=\"48220\" data-end=\"48235\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the operator;<\/span><\/li>\n<li data-section-id=\"11mdx6z\" data-start=\"48236\" data-end=\"48246\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">the NDK;<\/span><\/li>\n<li data-section-id=\"16y7b81\" data-start=\"48247\" data-end=\"48254\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">AFAD;<\/span><\/li>\n<li data-section-id=\"qbs8ii\" data-start=\"48255\" data-end=\"48268\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ministries;<\/span><\/li>\n<li data-section-id=\"1y3n31b\" data-start=\"48269\" data-end=\"48294\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">provincial authorities;<\/span><\/li>\n<li data-section-id=\"1tnotb5\" data-start=\"48295\" data-end=\"48313\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">health services;<\/span><\/li>\n<li data-section-id=\"q07mvf\" data-start=\"48314\" data-end=\"48332\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">security forces;<\/span><\/li>\n<li data-section-id=\"u9faar\" data-start=\"48333\" data-end=\"48357\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">local administrations;<\/span><\/li>\n<li data-section-id=\"rbmgpj\" data-start=\"48358\" data-end=\"48406\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">neighbouring jurisdictions where relevant; and<\/span><\/li>\n<li data-section-id=\"1i2pywk\" data-start=\"48407\" data-end=\"48462\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">international notification and assistance mechanisms.<\/span><\/li>\n<\/ul>\n<p data-start=\"48464\" data-end=\"48492\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Emergency plans may address:<\/span><\/p>\n<ul data-start=\"48494\" data-end=\"48698\">\n<li data-section-id=\"1rj65x3\" data-start=\"48494\" data-end=\"48513\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">on-site response;<\/span><\/li>\n<li data-section-id=\"o1scqh\" data-start=\"48514\" data-end=\"48534\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">off-site response;<\/span><\/li>\n<li data-section-id=\"jow56g\" data-start=\"48535\" data-end=\"48552\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">public warning;<\/span><\/li>\n<li data-section-id=\"1k2cluu\" data-start=\"48553\" data-end=\"48580\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">evacuation or sheltering;<\/span><\/li>\n<li data-section-id=\"19n2h17\" data-start=\"48581\" data-end=\"48600\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">medical response;<\/span><\/li>\n<li data-section-id=\"qg4w7w\" data-start=\"48601\" data-end=\"48624\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radiation monitoring;<\/span><\/li>\n<li data-section-id=\"i675dn\" data-start=\"48625\" data-end=\"48651\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">food and water controls;<\/span><\/li>\n<li data-section-id=\"864x28\" data-start=\"48652\" data-end=\"48669\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">communications;<\/span><\/li>\n<li data-section-id=\"g1vljq\" data-start=\"48670\" data-end=\"48682\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">exercises;<\/span><\/li>\n<li data-section-id=\"1yu1k7i\" data-start=\"48683\" data-end=\"48698\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and recovery.<\/span><\/li>\n<\/ul>\n<p data-start=\"48700\" data-end=\"48815\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Emergency preparedness must be established before operation and cannot be treated solely as a post-accident matter.<\/span><\/p>\n<h3 data-section-id=\"gfq446\" data-start=\"48822\" data-end=\"48863\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear Project Finance and Bankability<\/span><\/h3>\n<p data-start=\"48865\" data-end=\"48943\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear projects require large, long-term capital commitments and may involve:<\/span><\/p>\n<ul data-start=\"48945\" data-end=\"49188\">\n<li data-section-id=\"rsniiz\" data-start=\"48945\" data-end=\"48961\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">state support;<\/span><\/li>\n<li data-section-id=\"amgea\" data-start=\"48962\" data-end=\"48995\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">intergovernmental arrangements;<\/span><\/li>\n<li data-section-id=\"1d4wmnq\" data-start=\"48996\" data-end=\"49005\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">equity;<\/span><\/li>\n<li data-section-id=\"r5pgop\" data-start=\"49006\" data-end=\"49026\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">shareholder loans;<\/span><\/li>\n<li data-section-id=\"124hwfa\" data-start=\"49027\" data-end=\"49052\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export-credit agencies;<\/span><\/li>\n<li data-section-id=\"xhmzdm\" data-start=\"49053\" data-end=\"49072\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">commercial banks;<\/span><\/li>\n<li data-section-id=\"hycjmm\" data-start=\"49073\" data-end=\"49101\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">multilateral institutions;<\/span><\/li>\n<li data-section-id=\"192upb6\" data-start=\"49102\" data-end=\"49125\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sovereign guarantees;<\/span><\/li>\n<li data-section-id=\"u3q1yf\" data-start=\"49126\" data-end=\"49156\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">power-purchase arrangements;<\/span><\/li>\n<li data-section-id=\"12bki8g\" data-start=\"49157\" data-end=\"49188\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and political-risk insurance.<\/span><\/li>\n<\/ul>\n<p data-start=\"49190\" data-end=\"49246\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Legal due diligence for lenders and investors may cover:<\/span><\/p>\n<ul data-start=\"49248\" data-end=\"49540\">\n<li data-section-id=\"yhv7gv\" data-start=\"49248\" data-end=\"49276\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">project-company ownership;<\/span><\/li>\n<li data-section-id=\"cag6zo\" data-start=\"49277\" data-end=\"49300\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">licences and permits;<\/span><\/li>\n<li data-section-id=\"lz5ihz\" data-start=\"49301\" data-end=\"49315\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">land rights;<\/span><\/li>\n<li data-section-id=\"z3iypr\" data-start=\"49316\" data-end=\"49342\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental approvals;<\/span><\/li>\n<li data-section-id=\"mux20f\" data-start=\"49343\" data-end=\"49368\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">construction contracts;<\/span><\/li>\n<li data-section-id=\"4wijyy\" data-start=\"49369\" data-end=\"49383\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fuel supply;<\/span><\/li>\n<li data-section-id=\"1suz0v1\" data-start=\"49384\" data-end=\"49402\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">grid connection;<\/span><\/li>\n<li data-section-id=\"1a5cczc\" data-start=\"49403\" data-end=\"49419\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">power offtake;<\/span><\/li>\n<li data-section-id=\"9qvq6h\" data-start=\"49420\" data-end=\"49432\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">insurance;<\/span><\/li>\n<li data-section-id=\"10no9h2\" data-start=\"49433\" data-end=\"49453\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear liability;<\/span><\/li>\n<li data-section-id=\"1hrlo5i\" data-start=\"49454\" data-end=\"49480\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">decommissioning funding;<\/span><\/li>\n<li data-section-id=\"s1xs5f\" data-start=\"49481\" data-end=\"49493\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sanctions;<\/span><\/li>\n<li data-section-id=\"1n6gw9r\" data-start=\"49494\" data-end=\"49514\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">currency transfer;<\/span><\/li>\n<li data-section-id=\"hbm2w9\" data-start=\"49515\" data-end=\"49540\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and dispute resolution.<\/span><\/li>\n<\/ul>\n<p data-start=\"49542\" data-end=\"49559\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Lenders may seek:<\/span><\/p>\n<ul data-start=\"49561\" data-end=\"49772\">\n<li data-section-id=\"fsqfsf\" data-start=\"49561\" data-end=\"49592\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">assignment of project rights;<\/span><\/li>\n<li data-section-id=\"16uwv8f\" data-start=\"49593\" data-end=\"49631\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">security over shares or receivables;<\/span><\/li>\n<li data-section-id=\"o65uyz\" data-start=\"49632\" data-end=\"49652\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">direct agreements;<\/span><\/li>\n<li data-section-id=\"8lltyj\" data-start=\"49653\" data-end=\"49673\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">notice of default;<\/span><\/li>\n<li data-section-id=\"1ef37no\" data-start=\"49674\" data-end=\"49689\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cure periods;<\/span><\/li>\n<li data-section-id=\"gxpy9k\" data-start=\"49690\" data-end=\"49707\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">step-in rights;<\/span><\/li>\n<li data-section-id=\"g98e24\" data-start=\"49708\" data-end=\"49772\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and restrictions on amendment or termination of key contracts.<\/span><\/li>\n<\/ul>\n<p data-start=\"49774\" data-end=\"49991\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">These rights must be structured consistently with nuclear licensing rules. A lender cannot become the operator or exercise control over a nuclear installation without satisfying the applicable regulatory requirements.<\/span><\/p>\n<h3 data-section-id=\"dpnkiz\" data-start=\"49998\" data-end=\"50062\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Corporate Power Purchase Agreements, Industrial Users and CBAM<\/span><\/h3>\n<p data-start=\"50064\" data-end=\"50170\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The commercial significance of nuclear power is not confined to sales into the general electricity market. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Energy-intensive companies may seek long-term access to low-carbon electricity or heat through:<\/span><\/p>\n<ul data-start=\"50269\" data-end=\"50444\">\n<li data-section-id=\"1r3g6gh\" data-start=\"50269\" data-end=\"50307\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">corporate power purchase agreements;<\/span><\/li>\n<li data-section-id=\"6xboyo\" data-start=\"50308\" data-end=\"50337\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">direct supply arrangements;<\/span><\/li>\n<li data-section-id=\"1sof7fs\" data-start=\"50338\" data-end=\"50363\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">industrial co-location;<\/span><\/li>\n<li data-section-id=\"1t8i806\" data-start=\"50364\" data-end=\"50386\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">private-wire models;<\/span><\/li>\n<li data-section-id=\"t4299w\" data-start=\"50387\" data-end=\"50409\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">hydrogen production;<\/span><\/li>\n<li data-section-id=\"wyhxo6\" data-start=\"50410\" data-end=\"50425\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">desalination;<\/span><\/li>\n<li data-section-id=\"n2l6i9\" data-start=\"50426\" data-end=\"50444\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">or cogeneration.<\/span><\/li>\n<\/ul>\n<p data-start=\"50446\" data-end=\"50608\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The EU Carbon Border Adjustment Mechanism increases the importance of reliable carbon data for Turkish producers exporting covered products to the European Union. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Contracts may need to address:<\/span><\/p>\n<ul data-start=\"50642\" data-end=\"50828\">\n<li data-section-id=\"7wajac\" data-start=\"50642\" data-end=\"50672\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">proof of electricity source;<\/span><\/li>\n<li data-section-id=\"1x8fgmc\" data-start=\"50673\" data-end=\"50700\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental attributes;<\/span><\/li>\n<li data-section-id=\"1pexskh\" data-start=\"50701\" data-end=\"50721\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">carbon accounting;<\/span><\/li>\n<li data-section-id=\"1pbh31e\" data-start=\"50722\" data-end=\"50737\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">availability;<\/span><\/li>\n<li data-section-id=\"x4jhp1\" data-start=\"50738\" data-end=\"50752\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">curtailment;<\/span><\/li>\n<li data-section-id=\"1ltiecb\" data-start=\"50753\" data-end=\"50763\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">pricing;<\/span><\/li>\n<li data-section-id=\"1w4n5bc\" data-start=\"50764\" data-end=\"50780\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">change in law;<\/span><\/li>\n<li data-section-id=\"1icp9c2\" data-start=\"50781\" data-end=\"50796\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">grid charges;<\/span><\/li>\n<li data-section-id=\"1k4cvjk\" data-start=\"50797\" data-end=\"50809\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">balancing;<\/span><\/li>\n<li data-section-id=\"1hcvpkp\" data-start=\"50810\" data-end=\"50828\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and termination.<\/span><\/li>\n<\/ul>\n<p data-start=\"50830\" data-end=\"51224\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The TNBP report argues that CBAM and demand from data centres and industrial consumers may strengthen the commercial case for firm low-carbon generation in T\u00fcrkiye. This is a market assessment rather than a statement of legal obligation, but it highlights the interaction between nuclear investment, energy contracting and international trade regulation.<\/span><\/p>\n<h3 data-section-id=\"g0l9hd\" data-start=\"51231\" data-end=\"51271\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Dispute Resolution in Nuclear Projects<\/span><\/h3>\n<h4 data-section-id=\"wmz50u\" data-start=\"51273\" data-end=\"51302\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nature of Nuclear Disputes<\/span><\/h4>\n<p data-start=\"51304\" data-end=\"51354\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear projects may generate disputes concerning:<\/span><\/p>\n<ul data-start=\"51356\" data-end=\"51660\">\n<li data-section-id=\"1orizyl\" data-start=\"51356\" data-end=\"51380\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">design responsibility;<\/span><\/li>\n<li data-section-id=\"1avjj5y\" data-start=\"51381\" data-end=\"51389\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">delay;<\/span><\/li>\n<li data-section-id=\"anvu46\" data-start=\"51390\" data-end=\"51412\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">defective equipment;<\/span><\/li>\n<li data-section-id=\"cxhp1s\" data-start=\"51413\" data-end=\"51442\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">failure to obtain approval;<\/span><\/li>\n<li data-section-id=\"1w4n5bc\" data-start=\"51443\" data-end=\"51459\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">change in law;<\/span><\/li>\n<li data-section-id=\"1kf93wx\" data-start=\"51460\" data-end=\"51473\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">variations;<\/span><\/li>\n<li data-section-id=\"2kh1wv\" data-start=\"51474\" data-end=\"51490\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">force majeure;<\/span><\/li>\n<li data-section-id=\"s1xs5f\" data-start=\"51491\" data-end=\"51503\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sanctions;<\/span><\/li>\n<li data-section-id=\"1jimi7d\" data-start=\"51504\" data-end=\"51514\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">payment;<\/span><\/li>\n<li data-section-id=\"esw6ex\" data-start=\"51515\" data-end=\"51530\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">localisation;<\/span><\/li>\n<li data-section-id=\"qrefl4\" data-start=\"51531\" data-end=\"51555\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">intellectual property;<\/span><\/li>\n<li data-section-id=\"p95tap\" data-start=\"51556\" data-end=\"51576\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">quality assurance;<\/span><\/li>\n<li data-section-id=\"nc6p6t\" data-start=\"51577\" data-end=\"51587\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">testing;<\/span><\/li>\n<li data-section-id=\"vbzvcy\" data-start=\"51588\" data-end=\"51613\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">performance guarantees;<\/span><\/li>\n<li data-section-id=\"3bp29z\" data-start=\"51614\" data-end=\"51628\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">termination;<\/span><\/li>\n<li data-section-id=\"sk3tr8\" data-start=\"51629\" data-end=\"51660\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and interface responsibility.<\/span><\/li>\n<\/ul>\n<p data-start=\"51662\" data-end=\"51753\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Such disputes are often technically complex and may involve multiple contracts and parties.<\/span><\/p>\n<h4 data-section-id=\"1kke289\" data-start=\"51755\" data-end=\"51799\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Litigation and Administrative Proceedings<\/span><\/h4>\n<p data-start=\"51801\" data-end=\"51933\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Regulatory decisions may be subject to Turkish administrative-law remedies under the conditions applicable to the relevant decision. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Commercial and compensation claims may fall within the jurisdiction of judicial courts unless a valid arbitration agreement applies.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear third-party liability claims are governed by the special jurisdictional rules discussed above and should not be confused with contractual disputes between project participants.<\/span><\/p>\n<h4 data-section-id=\"vhpnh8\" data-start=\"52255\" data-end=\"52283\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">International Arbitration<\/span><\/h4>\n<p data-start=\"52285\" data-end=\"52399\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">International arbitration may be selected for EPC, technology-transfer, supply, financing or shareholder disputes. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Potential rules include:<\/span><\/p>\n<ul data-start=\"52427\" data-end=\"52565\">\n<li data-section-id=\"mxabes\" data-start=\"52427\" data-end=\"52451\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ICC Arbitration Rules;<\/span><\/li>\n<li data-section-id=\"n4ved3\" data-start=\"52452\" data-end=\"52481\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">UNCITRAL Arbitration Rules;<\/span><\/li>\n<li data-section-id=\"aogssq\" data-start=\"52482\" data-end=\"52512\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">ISTAC Arbitration Rules; and<\/span><\/li>\n<li data-section-id=\"1g7tw85\" data-start=\"52513\" data-end=\"52565\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">other institutional rules selected by the parties.<\/span><\/li>\n<\/ul>\n<p data-start=\"52567\" data-end=\"52637\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A carefully drafted nuclear project arbitration clause should address:<\/span><\/p>\n<ul data-start=\"52639\" data-end=\"52914\">\n<li data-section-id=\"16nl7lc\" data-start=\"52639\" data-end=\"52646\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">seat;<\/span><\/li>\n<li data-section-id=\"15m42we\" data-start=\"52647\" data-end=\"52663\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">governing law;<\/span><\/li>\n<li data-section-id=\"yxskqp\" data-start=\"52664\" data-end=\"52675\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">language;<\/span><\/li>\n<li data-section-id=\"1i876xh\" data-start=\"52676\" data-end=\"52719\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">number and qualifications of arbitrators;<\/span><\/li>\n<li data-section-id=\"1mlv17p\" data-start=\"52720\" data-end=\"52738\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">confidentiality;<\/span><\/li>\n<li data-section-id=\"1gzcg8b\" data-start=\"52739\" data-end=\"52758\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">emergency relief;<\/span><\/li>\n<li data-section-id=\"hpjthe\" data-start=\"52759\" data-end=\"52769\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">joinder;<\/span><\/li>\n<li data-section-id=\"17jd74h\" data-start=\"52770\" data-end=\"52786\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">consolidation;<\/span><\/li>\n<li data-section-id=\"1l72ejx\" data-start=\"52787\" data-end=\"52812\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">multiparty proceedings;<\/span><\/li>\n<li data-section-id=\"dpsryo\" data-start=\"52813\" data-end=\"52851\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">coordination with related contracts;<\/span><\/li>\n<li data-section-id=\"1muljbc\" data-start=\"52852\" data-end=\"52875\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">expert determination;<\/span><\/li>\n<li data-section-id=\"1ji2oag\" data-start=\"52876\" data-end=\"52895\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">interim measures;<\/span><\/li>\n<li data-section-id=\"1mz17c9\" data-start=\"52896\" data-end=\"52914\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and enforcement.<\/span><\/li>\n<\/ul>\n<p data-start=\"52916\" data-end=\"53131\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">In a multi-contract project, identical or compatible dispute-resolution clauses are generally preferable. Conflicting seats, institutions or governing laws may prevent consolidation and produce parallel proceedings.<\/span><\/p>\n<h4 data-section-id=\"13pgafc\" data-start=\"53133\" data-end=\"53164\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Investment Treaty Protection<\/span><\/h4>\n<p data-start=\"53166\" data-end=\"53304\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Foreign investors may also examine whether an applicable bilateral investment treaty or multilateral instrument protects their investment. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Possible issues include:<\/span><\/p>\n<ul data-start=\"53332\" data-end=\"53563\">\n<li data-section-id=\"uf2zkh\" data-start=\"53332\" data-end=\"53363\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">qualification as an investor;<\/span><\/li>\n<li data-section-id=\"jyyzse\" data-start=\"53364\" data-end=\"53402\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">existence of a protected investment;<\/span><\/li>\n<li data-section-id=\"19ktg6u\" data-start=\"53403\" data-end=\"53434\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fair and equitable treatment;<\/span><\/li>\n<li data-section-id=\"123hl11\" data-start=\"53435\" data-end=\"53451\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">expropriation;<\/span><\/li>\n<li data-section-id=\"1ucbp1e\" data-start=\"53452\" data-end=\"53469\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">discrimination;<\/span><\/li>\n<li data-section-id=\"1p0wxq3\" data-start=\"53470\" data-end=\"53490\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">transfer of funds;<\/span><\/li>\n<li data-section-id=\"ti9o8d\" data-start=\"53491\" data-end=\"53519\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">observance of obligations;<\/span><\/li>\n<li data-section-id=\"em35hh\" data-start=\"53520\" data-end=\"53563\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and access to investor-state arbitration.<\/span><\/li>\n<\/ul>\n<p data-start=\"53565\" data-end=\"53646\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Investment-treaty protection does not replace proper contractual risk allocation.<\/span><\/p>\n<h3 data-section-id=\"u8jzqa\" data-start=\"53653\" data-end=\"53706\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Legal Due Diligence for Nuclear Market Participants<\/span><\/h3>\n<p data-start=\"53708\" data-end=\"53857\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">A foreign company considering participation in T\u00fcrkiye\u2019s nuclear sector should undertake legal due diligence before committing substantial resources. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The review may include:<\/span><\/p>\n<h4 data-section-id=\"1o0fsw9\" data-start=\"53884\" data-end=\"53904\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Regulatory status<\/span><\/h4>\n<ul data-start=\"53906\" data-end=\"54068\">\n<li data-section-id=\"dgu89o\" data-start=\"53906\" data-end=\"53940\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">licences, permits and approvals;<\/span><\/li>\n<li data-section-id=\"13r6lhp\" data-start=\"53941\" data-end=\"53969\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">owner and operator status;<\/span><\/li>\n<li data-section-id=\"1hzt3or\" data-start=\"53970\" data-end=\"53994\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">regulatory conditions;<\/span><\/li>\n<li data-section-id=\"hzyxmt\" data-start=\"53995\" data-end=\"54018\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">pending applications;<\/span><\/li>\n<li data-section-id=\"srqlkr\" data-start=\"54019\" data-end=\"54041\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">inspection findings;<\/span><\/li>\n<li data-section-id=\"qtl6rv\" data-start=\"54042\" data-end=\"54068\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and enforcement history.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"ya5mhw\" data-start=\"54070\" data-end=\"54103\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Corporate and ownership issues<\/span><\/h4>\n<ul data-start=\"54105\" data-end=\"54240\">\n<li data-section-id=\"7xz862\" data-start=\"54105\" data-end=\"54121\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">incorporation;<\/span><\/li>\n<li data-section-id=\"teg1at\" data-start=\"54122\" data-end=\"54137\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">shareholders;<\/span><\/li>\n<li data-section-id=\"n94n1w\" data-start=\"54138\" data-end=\"54161\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">beneficial ownership;<\/span><\/li>\n<li data-section-id=\"qgmwot\" data-start=\"54162\" data-end=\"54175\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">governance;<\/span><\/li>\n<li data-section-id=\"1tnzul9\" data-start=\"54176\" data-end=\"54198\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">state participation;<\/span><\/li>\n<li data-section-id=\"1s6iur4\" data-start=\"54199\" data-end=\"54240\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and restrictions on changes of control.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"ro2uro\" data-start=\"54242\" data-end=\"54254\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Contracts<\/span><\/h4>\n<ul data-start=\"54256\" data-end=\"54485\">\n<li data-section-id=\"amgea\" data-start=\"54256\" data-end=\"54289\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">intergovernmental arrangements;<\/span><\/li>\n<li data-section-id=\"yv852o\" data-start=\"54290\" data-end=\"54307\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EPC agreements;<\/span><\/li>\n<li data-section-id=\"aed8yp\" data-start=\"54308\" data-end=\"54327\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">supply contracts;<\/span><\/li>\n<li data-section-id=\"g11s31\" data-start=\"54328\" data-end=\"54350\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology licences;<\/span><\/li>\n<li data-section-id=\"izfzd0\" data-start=\"54351\" data-end=\"54371\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">fuel arrangements;<\/span><\/li>\n<li data-section-id=\"w682k2\" data-start=\"54372\" data-end=\"54400\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">power purchase agreements;<\/span><\/li>\n<li data-section-id=\"rebb7i\" data-start=\"54401\" data-end=\"54419\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">grid agreements;<\/span><\/li>\n<li data-section-id=\"1n2u0r5\" data-start=\"54420\" data-end=\"54458\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">operation and maintenance contracts;<\/span><\/li>\n<li data-section-id=\"210q9o\" data-start=\"54459\" data-end=\"54485\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and financing documents.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"oe1hh5\" data-start=\"54487\" data-end=\"54520\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Land and environmental matters<\/span><\/h4>\n<ul data-start=\"54522\" data-end=\"54661\">\n<li data-section-id=\"1l56osz\" data-start=\"54522\" data-end=\"54530\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">title;<\/span><\/li>\n<li data-section-id=\"123hl11\" data-start=\"54531\" data-end=\"54547\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">expropriation;<\/span><\/li>\n<li data-section-id=\"qkextq\" data-start=\"54548\" data-end=\"54557\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">leases;<\/span><\/li>\n<li data-section-id=\"1smhbzc\" data-start=\"54558\" data-end=\"54567\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">zoning;<\/span><\/li>\n<li data-section-id=\"1j44uce\" data-start=\"54568\" data-end=\"54574\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EIA;<\/span><\/li>\n<li data-section-id=\"1hutp06\" data-start=\"54575\" data-end=\"54602\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">construction permissions;<\/span><\/li>\n<li data-section-id=\"w97jqx\" data-start=\"54603\" data-end=\"54630\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">coastal and water rights;<\/span><\/li>\n<li data-section-id=\"1nhd4v7\" data-start=\"54631\" data-end=\"54661\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and remediation obligations.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"ig5zfc\" data-start=\"54663\" data-end=\"54676\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Compliance<\/span><\/h4>\n<ul data-start=\"54678\" data-end=\"54864\">\n<li data-section-id=\"7gppyb\" data-start=\"54678\" data-end=\"54696\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export controls;<\/span><\/li>\n<li data-section-id=\"s1xs5f\" data-start=\"54697\" data-end=\"54709\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">sanctions;<\/span><\/li>\n<li data-section-id=\"1do1377\" data-start=\"54710\" data-end=\"54720\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">customs;<\/span><\/li>\n<li data-section-id=\"1ilihax\" data-start=\"54721\" data-end=\"54736\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">anti-bribery;<\/span><\/li>\n<li data-section-id=\"1hi6dza\" data-start=\"54737\" data-end=\"54751\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">competition;<\/span><\/li>\n<li data-section-id=\"1bjslze\" data-start=\"54752\" data-end=\"54768\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity;<\/span><\/li>\n<li data-section-id=\"1vjbgps\" data-start=\"54769\" data-end=\"54787\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">data protection;<\/span><\/li>\n<li data-section-id=\"t8n8r8\" data-start=\"54788\" data-end=\"54797\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">labour;<\/span><\/li>\n<li data-section-id=\"mz6tdu\" data-start=\"54798\" data-end=\"54831\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">occupational health and safety;<\/span><\/li>\n<li data-section-id=\"1mbytt9\" data-start=\"54832\" data-end=\"54864\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and nuclear quality assurance.<\/span><\/li>\n<\/ul>\n<h4 data-section-id=\"1loubcm\" data-start=\"54866\" data-end=\"54893\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Disputes and liabilities<\/span><\/h4>\n<ul data-start=\"54895\" data-end=\"55049\">\n<li data-section-id=\"uc4ii6\" data-start=\"54895\" data-end=\"54916\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">pending litigation;<\/span><\/li>\n<li data-section-id=\"apwzww\" data-start=\"54917\" data-end=\"54931\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">arbitration;<\/span><\/li>\n<li data-section-id=\"prqfbs\" data-start=\"54932\" data-end=\"54960\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">regulatory investigations;<\/span><\/li>\n<li data-section-id=\"51mia2\" data-start=\"54961\" data-end=\"54970\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">claims;<\/span><\/li>\n<li data-section-id=\"9qvq6h\" data-start=\"54971\" data-end=\"54983\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">insurance;<\/span><\/li>\n<li data-section-id=\"10no9h2\" data-start=\"54984\" data-end=\"55004\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear liability;<\/span><\/li>\n<li data-section-id=\"rc68no\" data-start=\"55005\" data-end=\"55019\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">indemnities;<\/span><\/li>\n<li data-section-id=\"aosjc5\" data-start=\"55020\" data-end=\"55049\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">and contingent liabilities.<\/span><\/li>\n<\/ul>\n<p data-start=\"55051\" data-end=\"55271\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The purpose is not merely to identify problems. Due diligence should determine how each issue affects price, project structure, conditions precedent, contractual protection, insurance and the decision whether to proceed.<\/span><\/p>\n<h3 data-section-id=\"mw4qci\" data-start=\"55278\" data-end=\"55333\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Legal Issues Throughout the Nuclear Project Lifecycle<\/span><\/h3>\n<div class=\"TyagGW_tableContainer\">\n<div class=\"group TyagGW_tableWrapper flex flex-col-reverse w-fit\" tabindex=\"-1\">\n<table class=\"w-fit min-w-(--thread-content-width)\" data-start=\"55335\" data-end=\"56699\">\n<thead data-start=\"55335\" data-end=\"55377\">\n<tr data-start=\"55335\" data-end=\"55377\">\n<th class=\"last:pe-10\" data-start=\"55335\" data-end=\"55351\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Project stage<\/span><\/th>\n<th class=\"last:pe-10\" data-start=\"55351\" data-end=\"55377\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Principal legal issues<\/span><\/th>\n<\/tr>\n<\/thead>\n<tbody data-start=\"55388\" data-end=\"56699\">\n<tr data-start=\"55388\" data-end=\"55513\">\n<td data-start=\"55388\" data-end=\"55429\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">National policy and project conception<\/span><\/td>\n<td data-start=\"55429\" data-end=\"55513\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Government policy, international cooperation, state support, investment strategy<\/span><\/td>\n<\/tr>\n<tr data-start=\"55514\" data-end=\"55626\">\n<td data-start=\"55514\" data-end=\"55548\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Technology and vendor selection<\/span><\/td>\n<td data-start=\"55548\" data-end=\"55626\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Procurement, intergovernmental negotiations, export controls, localisation<\/span><\/td>\n<\/tr>\n<tr data-start=\"55627\" data-end=\"55722\">\n<td data-start=\"55627\" data-end=\"55651\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Corporate structuring<\/span><\/td>\n<td data-start=\"55651\" data-end=\"55722\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Project company, shareholder rights, governance, foreign investment<\/span><\/td>\n<\/tr>\n<tr data-start=\"55723\" data-end=\"55822\">\n<td data-start=\"55723\" data-end=\"55742\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Site development<\/span><\/td>\n<td data-start=\"55742\" data-end=\"55822\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Owner recognition, site licence, EIA, land, zoning, coastal and water rights<\/span><\/td>\n<\/tr>\n<tr data-start=\"55823\" data-end=\"55906\">\n<td data-start=\"55823\" data-end=\"55835\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Financing<\/span><\/td>\n<td data-start=\"55835\" data-end=\"55906\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Bankability, security, direct agreements, political risk, sanctions<\/span><\/td>\n<\/tr>\n<tr data-start=\"55907\" data-end=\"56000\">\n<td data-start=\"55907\" data-end=\"55930\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Design and licensing<\/span><\/td>\n<td data-start=\"55930\" data-end=\"56000\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Safety analysis, design responsibility, regulatory submissions, IP<\/span><\/td>\n<\/tr>\n<tr data-start=\"56001\" data-end=\"56100\">\n<td data-start=\"56001\" data-end=\"56033\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Procurement and manufacturing<\/span><\/td>\n<td data-start=\"56033\" data-end=\"56100\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Manufacturer approval, quality assurance, traceability, customs<\/span><\/td>\n<\/tr>\n<tr data-start=\"56101\" data-end=\"56193\">\n<td data-start=\"56101\" data-end=\"56116\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Construction<\/span><\/td>\n<td data-start=\"56116\" data-end=\"56193\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">EPC risk, interfaces, delay, variations, inspections, occupational safety<\/span><\/td>\n<\/tr>\n<tr data-start=\"56194\" data-end=\"56270\">\n<td data-start=\"56194\" data-end=\"56210\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Commissioning<\/span><\/td>\n<td data-start=\"56210\" data-end=\"56270\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Testing, fuel loading, regulator hold points, acceptance<\/span><\/td>\n<\/tr>\n<tr data-start=\"56271\" data-end=\"56359\">\n<td data-start=\"56271\" data-end=\"56283\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Operation<\/span><\/td>\n<td data-start=\"56283\" data-end=\"56359\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Operating licence, safety, security, safeguards, maintenance, employment<\/span><\/td>\n<\/tr>\n<tr data-start=\"56360\" data-end=\"56438\">\n<td data-start=\"56360\" data-end=\"56377\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Fuel and waste<\/span><\/td>\n<td data-start=\"56377\" data-end=\"56438\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Supply, transport, safeguards, storage, waste, spent fuel<\/span><\/td>\n<\/tr>\n<tr data-start=\"56439\" data-end=\"56529\">\n<td data-start=\"56439\" data-end=\"56461\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Long-term operation<\/span><\/td>\n<td data-start=\"56461\" data-end=\"56529\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Periodic reviews, ageing management, modification, cybersecurity<\/span><\/td>\n<\/tr>\n<tr data-start=\"56530\" data-end=\"56613\">\n<td data-start=\"56530\" data-end=\"56548\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Decommissioning<\/span><\/td>\n<td data-start=\"56548\" data-end=\"56613\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Funding, dismantling, waste, remediation, licence termination<\/span><\/td>\n<\/tr>\n<tr data-start=\"56614\" data-end=\"56699\">\n<td data-start=\"56614\" data-end=\"56625\" data-col-size=\"sm\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Disputes<\/span><\/td>\n<td data-start=\"56625\" data-end=\"56699\" data-col-size=\"md\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Administrative remedies, litigation, arbitration and treaty protection<\/span><\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<\/div>\n<\/div>\n<hr data-start=\"56701\" data-end=\"56704\" \/>\n<h3 data-section-id=\"hkd5a4\" data-start=\"56706\" data-end=\"56734\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Frequently Asked Questions<\/span><\/h3>\n<h4 data-section-id=\"1ou5z80\" data-start=\"56736\" data-end=\"56813\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Does T\u00fcrkiye currently have a nuclear power plant in commercial operation?<\/span><\/h4>\n<p data-start=\"56815\" data-end=\"57064\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye\u2019s first commercial nuclear power plant is being developed at Akkuyu. The project has moved into advanced construction and commissioning-related preparations, but commercial operation depends on completion of testing and regulatory approvals.<\/span><\/p>\n<h4 data-section-id=\"1con50q\" data-start=\"57066\" data-end=\"57115\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Who regulates nuclear power plants in T\u00fcrkiye?<\/span><\/h4>\n<p data-start=\"57117\" data-end=\"57251\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The Nuclear Regulatory Authority, or NDK, is the principal independent regulator for nuclear energy and ionising-radiation activities.<\/span><\/p>\n<h4 data-section-id=\"yzjst1\" data-start=\"57253\" data-end=\"57294\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">What is the principal nuclear statute?<\/span><\/h4>\n<p data-start=\"57296\" data-end=\"57395\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The principal statute is Nuclear Regulation Law No. 7381, which entered into force on 8 March 2022.<\/span><\/p>\n<h4 data-section-id=\"1xeo0v\" data-start=\"57397\" data-end=\"57443\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">What are the main nuclear licensing stages?<\/span><\/h4>\n<p data-start=\"57445\" data-end=\"57649\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The core stages include recognition of the owner, site licensing, construction licensing and operating licensing. Additional permits and regulatory hold points apply during construction and commissioning.<\/span><\/p>\n<h4 data-section-id=\"va5tdf\" data-start=\"57651\" data-end=\"57732\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Is an environmental impact assessment sufficient to construct a nuclear plant?<\/span><\/h4>\n<p data-start=\"57734\" data-end=\"57829\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">No. An EIA approval and a nuclear site or construction licence are distinct legal requirements.<\/span><\/p>\n<h4 data-section-id=\"p0ak3u\" data-start=\"57831\" data-end=\"57904\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Can a foreign company own or participate in a Turkish nuclear project?<\/span><\/h4>\n<p data-start=\"57906\" data-end=\"58100\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Foreign participation is possible, subject to the project structure, applicable intergovernmental arrangements, company law, licensing, security considerations and other regulatory requirements.<\/span><\/p>\n<h4 data-section-id=\"xw1fsu\" data-start=\"58102\" data-end=\"58162\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Are nuclear operators strictly liable for nuclear damage?<\/span><\/h4>\n<p data-start=\"58164\" data-end=\"58283\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Yes. Law No. 7381 provides for strict operator liability, subject to statutory exclusions, limits and procedural rules.<\/span><\/p>\n<h4 data-section-id=\"17d9br3\" data-start=\"58285\" data-end=\"58325\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Must the operator maintain insurance?<\/span><\/h4>\n<p data-start=\"58327\" data-end=\"58460\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The operator must maintain insurance or other acceptable financial security corresponding to the applicable nuclear-liability amount.<\/span><\/p>\n<h4 data-section-id=\"1pqpran\" data-start=\"58462\" data-end=\"58514\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Can a nuclear construction dispute be arbitrated?<\/span><\/h4>\n<p data-start=\"58516\" data-end=\"58708\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Commercial disputes may be arbitrated where the parties have concluded a valid arbitration agreement. Third-party nuclear damage claims are subject to special statutory rules and jurisdiction.<\/span><\/p>\n<h4 data-section-id=\"1fakis8\" data-start=\"58710\" data-end=\"58770\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Are nuclear equipment suppliers subject to special rules?<\/span><\/h4>\n<p data-start=\"58772\" data-end=\"58948\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Yes. Nuclear equipment procurement, manufacturer approval, quality assurance, traceability, inspection and record retention may be subject to dedicated regulatory requirements.<\/span><\/p>\n<h4 data-section-id=\"168xr2o\" data-start=\"58950\" data-end=\"59028\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Are export controls relevant even where no nuclear material is transferred?<\/span><\/h4>\n<p data-start=\"59030\" data-end=\"59128\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Yes. Controls may apply to equipment, software, drawings, technology, services and technical data.<\/span><\/p>\n<h4 data-section-id=\"16stcou\" data-start=\"59130\" data-end=\"59188\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Does T\u00fcrkiye regulate radioactive waste and spent fuel?<\/span><\/h4>\n<p data-start=\"59190\" data-end=\"59362\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Yes. Turkish legislation contains rules concerning waste facilities, radioactive waste and spent-fuel management, transport, radiation protection and decommissioning funds.<\/span><\/p>\n<h4 data-section-id=\"mqlfcl\" data-start=\"59364\" data-end=\"59425\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Are small modular reactors covered by Turkish nuclear law?<\/span><\/h4>\n<p data-start=\"59427\" data-end=\"59599\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The broad nuclear-authorisation framework can apply to SMRs, although technology-specific licensing and implementation questions may require further regulatory development.<\/span><\/p>\n<h4 data-section-id=\"u7b67l\" data-start=\"59601\" data-end=\"59633\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">What role does T\u00dcNA\u015e perform?<\/span><\/h4>\n<p data-start=\"59635\" data-end=\"59843\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00dcNA\u015e performs nuclear project-development, programme-management, supplier-development, infrastructure, owner\u2019s-requirements and technology-assessment activities, including work connected with Sinop and SMRs.<\/span><\/p>\n<h4 data-section-id=\"161ivdf\" data-start=\"59845\" data-end=\"59888\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Can the NDK suspend or revoke a licence?<\/span><\/h4>\n<p data-start=\"59890\" data-end=\"60043\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Yes. The NDK has statutory powers to impose conditions and to restrict, suspend, terminate or revoke authorisations where the legal requirements are met.<\/span><\/p>\n<h3 data-section-id=\"5uszl\" data-start=\"60050\" data-end=\"60106\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">How B\u0131\u00e7ak Assists Nuclear-Sector Participants?<\/span><\/h3>\n<p data-start=\"60108\" data-end=\"60283\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear projects require coordinated advice across public law, energy regulation, corporate transactions, construction, technology, international trade and dispute resolution. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">B\u0131\u00e7ak assists domestic and international participants with matters including:<\/span><\/p>\n<ul data-start=\"60373\" data-end=\"61269\">\n<li data-section-id=\"4jyr7h\" data-start=\"60373\" data-end=\"60421\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">interpretation of Turkish nuclear legislation;<\/span><\/li>\n<li data-section-id=\"1kk4jd1\" data-start=\"60422\" data-end=\"60458\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">regulatory and licensing strategy;<\/span><\/li>\n<li data-section-id=\"1na0pyq\" data-start=\"60459\" data-end=\"60504\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">legal review of nuclear project structures;<\/span><\/li>\n<li data-section-id=\"1x7t5qh\" data-start=\"60505\" data-end=\"60554\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">corporate establishment and foreign investment;<\/span><\/li>\n<li data-section-id=\"1keeets\" data-start=\"60555\" data-end=\"60596\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear EPC and construction contracts;<\/span><\/li>\n<li data-section-id=\"1nsym8n\" data-start=\"60597\" data-end=\"60640\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">equipment-supply and services agreements;<\/span><\/li>\n<li data-section-id=\"3zl6fj\" data-start=\"60641\" data-end=\"60678\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">project and supplier due diligence;<\/span><\/li>\n<li data-section-id=\"12awxqj\" data-start=\"60679\" data-end=\"60728\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">procurement and manufacturer-compliance issues;<\/span><\/li>\n<li data-section-id=\"it2q6z\" data-start=\"60729\" data-end=\"60788\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">technology-transfer and intellectual-property agreements;<\/span><\/li>\n<li data-section-id=\"fiw8qp\" data-start=\"60789\" data-end=\"60833\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">joint ventures and strategic partnerships;<\/span><\/li>\n<li data-section-id=\"g0l02c\" data-start=\"60834\" data-end=\"60875\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">export controls, sanctions and customs;<\/span><\/li>\n<li data-section-id=\"1up4rrz\" data-start=\"60876\" data-end=\"60912\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cybersecurity and data governance;<\/span><\/li>\n<li data-section-id=\"g477j4\" data-start=\"60913\" data-end=\"60958\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">environmental, land and permitting matters;<\/span><\/li>\n<li data-section-id=\"lhobrp\" data-start=\"60959\" data-end=\"61002\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear insurance and liability analysis;<\/span><\/li>\n<li data-section-id=\"10palrk\" data-start=\"61003\" data-end=\"61056\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">radioactive waste and decommissioning arrangements;<\/span><\/li>\n<li data-section-id=\"ku73h3\" data-start=\"61057\" data-end=\"61079\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">construction claims;<\/span><\/li>\n<li data-section-id=\"1lp0fkm\" data-start=\"61080\" data-end=\"61109\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">administrative proceedings;<\/span><\/li>\n<li data-section-id=\"megdfa\" data-start=\"61110\" data-end=\"61149\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">international commercial arbitration;<\/span><\/li>\n<li data-section-id=\"grq12n\" data-start=\"61150\" data-end=\"61179\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">investment treaty analysis;<\/span><\/li>\n<li data-section-id=\"9un3r8\" data-start=\"61180\" data-end=\"61220\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">cooperation with overseas counsel; and<\/span><\/li>\n<li data-section-id=\"sxidu7\" data-start=\"61221\" data-end=\"61269\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">nuclear-law education and compliance training.<\/span><\/li>\n<\/ul>\n<p data-start=\"61271\" data-end=\"61508\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">We also assist in evaluating whether project documents and commercial arrangements are consistent with Turkish legislation, applicable international agreements, licence conditions and nuclear safety, security and safeguards requirements. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Nuclear projects are technically complex, politically sensitive and commercially long-term. Effective legal advice must therefore begin before contracts are signed and continue throughout licensing, construction, commissioning, operation and eventual decommissioning.<\/span><\/p>\n<h3 data-section-id=\"1248z7z\" data-start=\"61784\" data-end=\"61808\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Concluding Assessment<\/span><\/h3>\n<p data-start=\"61810\" data-end=\"61883\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">T\u00fcrkiye\u2019s nuclear programme is entering a new legal and commercial phase. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">Akkuyu has transformed nuclear law from a largely prospective field into a functioning regulatory practice involving construction, inspection, commissioning preparation, supply chains and future operation. Sinop, possible additional large-scale plants and SMR initiatives may further expand the market. <\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">The key legal principle is that nuclear regulation cannot be separated from the project\u2019s commercial structure. A technically viable project may still fail if its licensing, financing, procurement, technology-transfer, sanctions or liability arrangements are defective. Equally, a carefully negotiated contract cannot override mandatory nuclear safety requirements or the NDK\u2019s regulatory powers.<\/span><\/p>\n<p data-start=\"62587\" data-end=\"62807\"><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">International investors, reactor vendors, EPC contractors, manufacturers, financiers, insurers and professional advisers should therefore approach T\u00fcrkiye\u2019s nuclear sector through an integrated legal strategy addressing: &#8220;<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\"><em>nuclear regulation, project structuring, procurement, financing, construction, localisation, technology, international compliance, liability and dispute resolution across the entire facility lifecycle<\/em>&#8220;.\u00a0<\/span><span style=\"font-family: 'times new roman', times, serif; font-size: 14pt;\">This full-lifecycle perspective is essential for participating responsibly and effectively in T\u00fcrkiye\u2019s developing nuclear energy programme.<\/span><\/p>\n","protected":false},"excerpt":{"rendered":"<p>T\u00fcrkiye\u2019s Transition to Nuclear Power T\u00fcrkiye has considered the introduction of nuclear-generated electricity since the 1950s. The Turkish Atomic Energy Commission was established in 1956, and Akkuyu on T\u00fcrkiye\u2019s Mediterranean coast was subsequently identified as a potential nuclear power plant site. Several earlier procurement and development initiatives did not result in construction, however, and T\u00fcrkiye [&hellip;]<\/p>\n","protected":false},"author":27,"featured_media":32080,"comment_status":"open","ping_status":"open","sticky":false,"template":"page-fullwidth.php","format":"standard","meta":{"rs_blank_template":"","rs_page_bg_color":"","slide_template_v7":"","footnotes":""},"categories":[25,160],"tags":[32849,32814,32778,32812,4163,32811,32813,32815,4148,4158,32883,32884,32870,4149,32803,4157,32850,32848,32845,32786,32835,32861,4147,4184,32785,32832,32802,4174,4165,32880,32879,4181,32878,32881,4173,32840,32871,4155,4185,32796,32872,32864,32831,32860,32784,32801,32828,32830,32858,32844,32847,32806,32854,32866,32856,4171,32874,4161,32790,4166,32777,32869,4153,32877,4172,32855,32788,32827,32846,32824,32842,32863,32805,32837,32834,32838,4186,4168,4167,32882,4169,4170,4159,32776,4154,4176,32783,32781,32839,32875,32859,4178,32789,32794,32886,4146,4156,32868,4145,32787,32823,32829,32810,32833,32808,32887,32867,4151,32792,4182,4160,32782,32795,32865,32791,32809,32799,4175,32862,32797,4177,32843,32798,4179,32857,32825,32826,32836,32853,4180,32807,32800,4150,32851,32817,32816,32818,32780,32820,32821,32779,32822,32852,32804,32819,4152,4162,4183,4164,32876,32885,32793,32841,32873],"class_list":["post-25158","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-en","category-insights","tag-ai-in-nuclear-energy","tag-akkuyu-epc-contracts","tag-akkuyu-legal-advisor","tag-akkuyu-npp-legal-framework","tag-akkuyu-nuclear-power-plant-in-turkey","tag-akkuyu-nuclear-power-plant-law","tag-akkuyu-nuclear-project-turkiye","tag-akkuyu-project-legal-advice","tag-atomic-energy","tag-atomic-energy-agency-turkey","tag-bicak-law-firm-nuclear-energy","tag-bicak-law-nuclear-law","tag-cbam-and-nuclear-energy-turkiye","tag-chernobyl","tag-civil-liability-for-nuclear-damage","tag-civilian-nuclear-industry-turkey","tag-critical-infrastructure-cybersecurity-turkiye","tag-digital-nuclear-systems-law","tag-dual-use-goods-nuclear-sector","tag-export-controls-nuclear","tag-foreign-investment-nuclear-energy-turkiye","tag-fuel-loading-permit-turkiye","tag-fukushima-accident","tag-future-of-nuclear-power-turkey","tag-iaea-compliance","tag-international-arbitration-nuclear-projects","tag-international-nuclear-law-turkiye","tag-law-of-nuclear-and-radiological-control","tag-league-of-nations-with-nuclear-power","tag-legal-advice-for-reactor-vendors-turkiye","tag-legal-counsel-for-epc-contractors-turkiye","tag-legal-framework-for-the-development-of-nuclear-energy-turkey","tag-legal-services-for-nuclear-companies-turkiye","tag-legal-services-for-nuclear-suppliers","tag-liability-regulations-for-nuclear-damages","tag-local-content-nuclear-projects","tag-low-carbon-electricity-turkiye","tag-multidisciplinary-approach","tag-national-bodies-on-nuclear-safety-turkey","tag-ndk-turkiye","tag-net-zero-2053-nuclear-energy","tag-nuclear-administrative-sanctions","tag-nuclear-arbitration-turkiye","tag-nuclear-commissioning-permit","tag-nuclear-compliance","tag-nuclear-compliance-turkiye","tag-nuclear-construction-contracts","tag-nuclear-construction-disputes","tag-nuclear-construction-licence-turkiye","tag-nuclear-customs-compliance-turkiye","tag-nuclear-cybersecurity-turkiye","tag-nuclear-damage-compensation-turkiye","tag-nuclear-decommissioning-law-turkiye","tag-nuclear-due-diligence-turkiye","tag-nuclear-eia-turkiye","tag-nuclear-energy","tag-nuclear-energy-investment-opportunities-turkiye","tag-nuclear-energy-law-turkey","tag-nuclear-energy-law-turkiye","tag-nuclear-energy-lawyer","tag-nuclear-energy-lawyer-turkiye","tag-nuclear-energy-ppas","tag-nuclear-energy-projects","tag-nuclear-energy-projects-in-turkiye","tag-nuclear-energy-solicitor-turkey","tag-nuclear-environmental-law-turkiye","tag-nuclear-epc-contracts","tag-nuclear-epc-contracts-turkiye","tag-nuclear-equipment-import-turkiye","tag-nuclear-equipment-procurement","tag-nuclear-export-controls-turkiye","tag-nuclear-inspections-turkiye","tag-nuclear-insurance-turkiye","tag-nuclear-intellectual-property-law","tag-nuclear-investment-turkiye","tag-nuclear-joint-ventures-turkiye","tag-nuclear-jurisprudence-turkey","tag-nuclear-law","tag-nuclear-law-advice","tag-nuclear-law-firm-turkiye","tag-nuclear-law-legal-advice","tag-nuclear-law-legal-framework","tag-nuclear-law-turkey","tag-nuclear-law-turkiye","tag-nuclear-lawyer-turkey","tag-nuclear-liability-law-turkey","tag-nuclear-liability-law-turkiye","tag-nuclear-licensing-turkiye","tag-nuclear-localisation-turkiye","tag-nuclear-market-turkiye-2026","tag-nuclear-operating-licence-turkiye","tag-nuclear-plant-construction-turkey","tag-nuclear-power-plant-law-turkiye","tag-nuclear-power-plant-licensing-turkey","tag-nuclear-power-plant-regulation-turkiye","tag-nuclear-power-plant-turkey","tag-nuclear-power-program-turkey","tag-nuclear-power-purchase-agreements-turkiye","tag-nuclear-power-turkey","tag-nuclear-procurement","tag-nuclear-procurement-turkiye","tag-nuclear-project-contracts-turkiye","tag-nuclear-project-counsel-turkiye","tag-nuclear-project-finance-turkiye","tag-nuclear-project-legal-advice-turkiye","tag-nuclear-project-lifecycle-legal-services","tag-nuclear-project-risk-assessment","tag-nuclear-proliferation","tag-nuclear-regulation-law-no-7381","tag-nuclear-regulation-law-turkey","tag-nuclear-regulations-turkey","tag-nuclear-regulatory-authority","tag-nuclear-regulatory-authority-turkiye","tag-nuclear-regulatory-compliance-lawyer","tag-nuclear-regulatory-framework-turkiye","tag-nuclear-regulatory-lawyer-turkiye","tag-nuclear-safeguards-turkiye","tag-nuclear-safety-and-control","tag-nuclear-safety-assessment-turkiye","tag-nuclear-safety-law-turkiye","tag-nuclear-safety-whistleblower-turkey","tag-nuclear-sanctions-compliance","tag-nuclear-security-law-turkiye","tag-nuclear-security-regulatory-framework-in-turkey","tag-nuclear-site-licence-turkiye","tag-nuclear-supplier-qualification-turkiye","tag-nuclear-supply-chain-law","tag-nuclear-technology-transfer-turkiye","tag-nuclear-waste-management-turkiye","tag-office-for-nuclear-regulation-turkey","tag-paris-convention-turkiye","tag-radiation-protection-law-turkiye","tag-radioactive-contaminatio","tag-radioactive-waste-law-turkiye","tag-sinop-npp-turkiye","tag-sinop-nuclear-power-plant-law","tag-sinop-nuclear-project-legal-advice","tag-small-modular-reactor-turkiye","tag-small-modular-reactors-turkiye","tag-smr-law-turkiye","tag-smr-lawyer","tag-smr-licensing-turkiye","tag-spent-nuclear-fuel-law","tag-strict-liability-nuclear-operator-turkiye","tag-thrace-nuclear-power-project","tag-top-nuclear-energy-legal-team","tag-turkeys-first-nuclear-power-plant","tag-turkeys-nuclear-program","tag-turkeys-first-nuclear-plant","tag-turkish-nuclear-industry","tag-turkish-nuclear-law-guide","tag-turkish-nuclear-legislation","tag-turkish-nuclear-suppliers","tag-turkiye-national-energy-plan-nuclear"],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v27.1 (Yoast SEO v27.8) - https:\/\/yoast.com\/product\/yoast-seo-premium-wordpress\/ -->\n<title>Nuclear power plant law in Turkey | Bicak Law Firm<\/title>\n<meta name=\"description\" content=\"nuclear power plant Turkey Lawyer solicitor attorney advocate atomic energy law firm legal team program civilian Agency T\u00fcrkiye Regulation\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Nuclear power plant law in Turkey %\" \/>\n<meta property=\"og:description\" content=\"T\u00fcrkiye\u2019s Transition to Nuclear Power T\u00fcrkiye has considered the introduction of nuclear-generated electricity since the 1950s. The Turkish Atomic Energy\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/\" \/>\n<meta property=\"og:site_name\" content=\"B\u0131\u00e7ak Hukuk\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/bicakhukuk\" \/>\n<meta property=\"article:published_time\" content=\"2023-04-28T08:48:03+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-07-25T14:16:04+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/04\/Nuclear-Power-Plant-Law-in-Turkiye-1024x683.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1024\" \/>\n\t<meta property=\"og:image:height\" content=\"683\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Admin\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@BicakHukuk\" \/>\n<meta name=\"twitter:site\" content=\"@BicakHukuk\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Admin\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"43 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/\"},\"author\":{\"name\":\"Admin\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/#\\\/schema\\\/person\\\/3ffbc31864ec806febdc7f57e5eae117\"},\"headline\":\"Nuclear power plant law in Turkey\",\"datePublished\":\"2023-04-28T08:48:03+00:00\",\"dateModified\":\"2026-07-25T14:16:04+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/\"},\"wordCount\":7171,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.bicakhukuk.com\\\/wp-content\\\/uploads\\\/2023\\\/04\\\/Nuclear-Power-Plant-Law-in-Turkiye.png\",\"keywords\":[\"AI in nuclear energy\",\"Akkuyu EPC contracts\",\"Akkuyu legal advisor\",\"Akkuyu NPP legal framework\",\"Akkuyu nuclear power plant in Turkey\",\"Akkuyu Nuclear Power Plant law\",\"Akkuyu nuclear project T\u00fcrkiye\",\"Akkuyu project legal advice\",\"atomic energy\",\"Atomic Energy Agency Turkey\",\"B\u0131\u00e7ak Law Firm nuclear energy\",\"B\u0131\u00e7ak Law nuclear law\",\"CBAM and nuclear energy T\u00fcrkiye\",\"Chernobyl\",\"civil liability for nuclear damage\",\"civilian nuclear industry Turkey\",\"critical infrastructure cybersecurity T\u00fcrkiye\",\"digital nuclear systems law\",\"dual-use goods nuclear sector\",\"export controls nuclear\",\"foreign investment nuclear energy T\u00fcrkiye\",\"fuel loading permit T\u00fcrkiye\",\"Fukushima accident\",\"Future of Nuclear Power Turkey\",\"IAEA compliance\",\"international arbitration nuclear projects\",\"international nuclear law T\u00fcrkiye\",\"Law of Nuclear and Radiological Control\",\"league of nations with nuclear power\",\"legal advice for reactor vendors T\u00fcrkiye\",\"legal counsel for EPC contractors T\u00fcrkiye\",\"Legal Framework for the Development of Nuclear Energy Turkey\",\"legal services for nuclear companies T\u00fcrkiye\",\"legal services for nuclear suppliers\",\"Liability Regulations for Nuclear Damages\",\"local content nuclear projects\",\"low-carbon electricity T\u00fcrkiye\",\"Multidisciplinary Approach\",\"National bodies on nuclear safety Turkey\",\"NDK T\u00fcrkiye\",\"net zero 2053 nuclear energy\",\"nuclear administrative sanctions\",\"nuclear arbitration T\u00fcrkiye\",\"nuclear commissioning permit\",\"nuclear compliance\",\"nuclear compliance T\u00fcrkiye\",\"nuclear construction contracts\",\"nuclear construction disputes\",\"nuclear construction licence T\u00fcrkiye\",\"nuclear customs compliance T\u00fcrkiye\",\"nuclear cybersecurity T\u00fcrkiye\",\"nuclear damage compensation T\u00fcrkiye\",\"nuclear decommissioning law T\u00fcrkiye\",\"nuclear due diligence T\u00fcrkiye\",\"nuclear EIA T\u00fcrkiye\",\"Nuclear Energy\",\"nuclear energy investment opportunities T\u00fcrkiye\",\"nuclear energy law Turkey\",\"nuclear energy law T\u00fcrkiye\",\"Nuclear Energy Lawyer\",\"nuclear energy lawyer T\u00fcrkiye\",\"nuclear energy PPAs\",\"nuclear energy projects\",\"nuclear energy projects in T\u00fcrkiye\",\"Nuclear Energy Solicitor Turkey\",\"nuclear environmental law T\u00fcrkiye\",\"nuclear EPC contracts\",\"nuclear EPC contracts T\u00fcrkiye\",\"nuclear equipment import T\u00fcrkiye\",\"nuclear equipment procurement\",\"nuclear export controls T\u00fcrkiye\",\"nuclear inspections T\u00fcrkiye\",\"nuclear insurance T\u00fcrkiye\",\"nuclear intellectual property law\",\"nuclear investment T\u00fcrkiye\",\"nuclear joint ventures T\u00fcrkiye\",\"nuclear jurisprudence Turkey\",\"Nuclear law\",\"Nuclear law advice\",\"nuclear law firm T\u00fcrkiye\",\"Nuclear Law Legal Advice\",\"Nuclear law Legal Framework\",\"nuclear law Turkey\",\"nuclear law T\u00fcrkiye\",\"nuclear lawyer Turkey\",\"nuclear liability law Turkey\",\"nuclear liability law T\u00fcrkiye\",\"nuclear licensing T\u00fcrkiye\",\"nuclear localisation T\u00fcrkiye\",\"nuclear market T\u00fcrkiye 2026\",\"nuclear operating licence T\u00fcrkiye\",\"nuclear plant construction Turkey\",\"nuclear power plant law T\u00fcrkiye\",\"nuclear power plant licensing Turkey\",\"nuclear power plant regulation T\u00fcrkiye\",\"nuclear power plant Turkey\",\"nuclear power program Turkey\",\"nuclear power purchase agreements T\u00fcrkiye\",\"nuclear power Turkey\",\"nuclear procurement\",\"nuclear procurement T\u00fcrkiye\",\"nuclear project contracts T\u00fcrkiye\",\"nuclear project counsel T\u00fcrkiye\",\"nuclear project finance T\u00fcrkiye\",\"nuclear project legal advice T\u00fcrkiye\",\"nuclear project lifecycle legal services\",\"nuclear project risk assessment\",\"nuclear proliferation\",\"Nuclear Regulation Law No. 7381\",\"Nuclear Regulation Law Turkey\",\"nuclear regulations Turkey\",\"nuclear regulatory authority\",\"Nuclear Regulatory Authority T\u00fcrkiye\",\"nuclear regulatory compliance lawyer\",\"nuclear regulatory framework T\u00fcrkiye\",\"nuclear regulatory lawyer T\u00fcrkiye\",\"nuclear safeguards T\u00fcrkiye\",\"Nuclear Safety and Control\",\"nuclear safety assessment T\u00fcrkiye\",\"nuclear safety law T\u00fcrkiye\",\"Nuclear Safety Whistleblower Turkey\",\"nuclear sanctions compliance\",\"nuclear security law T\u00fcrkiye\",\"Nuclear Security Regulatory Framework in Turkey\",\"nuclear site licence T\u00fcrkiye\",\"nuclear supplier qualification T\u00fcrkiye\",\"nuclear supply chain law\",\"nuclear technology transfer T\u00fcrkiye\",\"nuclear waste management T\u00fcrkiye\",\"Office for Nuclear Regulation Turkey\",\"Paris Convention T\u00fcrkiye\",\"radiation protection law T\u00fcrkiye\",\"radioactive contaminatio\",\"radioactive waste law T\u00fcrkiye\",\"Sinop NPP T\u00fcrkiye\",\"Sinop Nuclear Power Plant law\",\"Sinop nuclear project legal advice\",\"small modular reactor T\u00fcrkiye\",\"small modular reactors T\u00fcrkiye\",\"SMR law T\u00fcrkiye\",\"SMR lawyer\",\"SMR licensing T\u00fcrkiye\",\"spent nuclear fuel law\",\"strict liability nuclear operator T\u00fcrkiye\",\"Thrace nuclear power project\",\"top nuclear energy legal team\",\"Turkey's first nuclear power plant\",\"Turkey's Nuclear Program\",\"Turkey\u2019s first nuclear plant\",\"Turkish nuclear industry\",\"Turkish nuclear law guide\",\"Turkish nuclear legislation\",\"Turkish nuclear suppliers\",\"T\u00fcrkiye National Energy Plan nuclear\"],\"articleSection\":[\"@en\",\"Insights\"],\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/\",\"url\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/\",\"name\":\"Nuclear power plant law in Turkey | Bicak Law Firm\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.bicakhukuk.com\\\/wp-content\\\/uploads\\\/2023\\\/04\\\/Nuclear-Power-Plant-Law-in-Turkiye.png\",\"datePublished\":\"2023-04-28T08:48:03+00:00\",\"dateModified\":\"2026-07-25T14:16:04+00:00\",\"description\":\"nuclear power plant Turkey Lawyer solicitor attorney advocate atomic energy law firm legal team program civilian Agency T\u00fcrkiye Regulation\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#primaryimage\",\"url\":\"https:\\\/\\\/www.bicakhukuk.com\\\/wp-content\\\/uploads\\\/2023\\\/04\\\/Nuclear-Power-Plant-Law-in-Turkiye.png\",\"contentUrl\":\"https:\\\/\\\/www.bicakhukuk.com\\\/wp-content\\\/uploads\\\/2023\\\/04\\\/Nuclear-Power-Plant-Law-in-Turkiye.png\",\"width\":1536,\"height\":1024,\"caption\":\"nuclear power plant Turkey Lawyer solicitor attorney advocate atomic energy law firm legal team program civilian Agency T\u00fcrkiye Regulation\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Ana sayfa\",\"item\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Nuclear power plant law in Turkey\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/#website\",\"url\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/\",\"name\":\"B\u0131\u00e7ak Hukuk\",\"description\":\"T\u00fcrkiye Merkezli Global Hukuk B\u00fcrosu\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/#organization\"},\"alternateName\":\"B\u0131\u00e7ak Hukuk, Ankara Avukat, Ankara Hukuk B\u00fcrosu\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":[\"Organization\",\"Place\"],\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/#organization\",\"name\":\"B\u0131\u00e7ak Hukuk | T\u00fcrkiye Merkezli Global Hukuk Firmas\u0131\",\"alternateName\":\"B\u0131\u00e7ak Hukuk, Ankara Avukat, Ankara Hukuk B\u00fcrosu\",\"url\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/\",\"logo\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#local-main-organization-logo\"},\"image\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#local-main-organization-logo\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/bicakhukuk\",\"https:\\\/\\\/x.com\\\/BicakHukuk\",\"https:\\\/\\\/www.instagram.com\\\/bicakhukuk\\\/\",\"https:\\\/\\\/tr.linkedin.com\\\/company\\\/b-ak-law-firm\",\"https:\\\/\\\/www.youtube.com\\\/channel\\\/UCodktEWFyJmIp3i1BH9aM2A\\\/\"],\"description\":\"K\u00fcresel, b\u00f6lgesel ve ulusal \u015firketlere, kurulu\u015flara ve ki\u015filere uzmanl\u0131k alanlar\u0131m\u0131zda uyu\u015fmazl\u0131k \u00f6nleyici hukuk dan\u0131\u015fmanl\u0131\u011f\u0131, uyu\u015fmazl\u0131k \u00e7\u00f6z\u00fcm s\u00fcre\u00e7lerinde ise arabuluculuk, arabuluculukta taraf vekilli\u011fi, mahkemelerde taraf vekilli\u011fi ve avukatl\u0131k, tahkim hakemli\u011fi, tahkimde taraf vekilli\u011fi, hukuki konularda m\u00fctalaa ve hukuki konularda e\u011fitim hizmetleri vermekteyiz. Uluslararas\u0131, b\u00f6lgesel ve ulusal hukuka ili\u015fkin inceleme, ara\u015ft\u0131rma ve tecr\u00fcbeye dayal\u0131 hukuk hizmetlerimizi sunarken teknolojinin imkan sa\u011flad\u0131\u011f\u0131 g\u00f6rsel (video konferans) veya i\u015fitsel (sesli konferans) ileti\u015fim teknolojilerinin elverdi\u011fi t\u00fcm olanaklar\u0131 kullanmaktay\u0131z. Dan\u0131\u015fanlar\u0131m\u0131z veya m\u00fcvekkillerimiz, D\u00fcnyan\u0131n, b\u00f6lgemizin veya \u00fclkemizin neresinde olurlarsa olsunlar hizmetlerimizden uzaktan eri\u015fim yoluyla yararlanabilmektedir. Muhtemel ihtilaflar\u0131 \u00f6nlemek veya en aza indirmek gayesiyle m\u00fcvekkillerimize sundu\u011fumuz dinamik, etkili ve \u00f6nleyici dan\u0131\u015fmanl\u0131k hizmetlerimizin yan\u0131nda, uyu\u015fmazl\u0131k \u00e7\u00f6z\u00fcm s\u00fcre\u00e7lerinde arabuluculuk, tahkim veya mahkemelerde dava takibi hizmetleri de sunmaktay\u0131z. Ba\u015far\u0131n\u0131n s\u0131rr\u0131, do\u011fru bilgiye h\u0131zl\u0131 eri\u015fimdir. M\u00fcvekkil ihtiya\u00e7lar\u0131 tam ve eksiksiz tan\u0131mlayarak y\u00fcksek standartlarda, kaliteli, h\u0131zl\u0131 ve sonu\u00e7 odakl\u0131 esas\u0131na dayanan bir \u00e7al\u0131\u015fma anlay\u0131\u015f\u0131 benimsemi\u015f bulunuyoruz. G\u00fcvenilirlik, itibar, etik de\u011ferler ve kalite standartlar\u0131 gibi unsurlar, vazge\u00e7ilmezlerimiz olu\u015fturur.\",\"legalName\":\"B\u0131\u00e7ak Hukuk\",\"foundingDate\":\"2002-01-01\",\"numberOfEmployees\":{\"@type\":\"QuantitativeValue\",\"minValue\":\"1\",\"maxValue\":\"10\"},\"address\":{\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#local-main-place-address\"},\"geo\":{\"@type\":\"GeoCoordinates\",\"latitude\":\"39.90985903589262\",\"longitude\":\"32.81218744448808\"},\"telephone\":[\"0 (312) 473 39 60\",\"0 (553) 223 32 90\"],\"openingHoursSpecification\":[{\"@type\":\"OpeningHoursSpecification\",\"dayOfWeek\":[\"Monday\",\"Tuesday\",\"Wednesday\",\"Thursday\",\"Friday\",\"Saturday\"],\"opens\":\"08:00\",\"closes\":\"18:00\"},{\"@type\":\"OpeningHoursSpecification\",\"dayOfWeek\":[\"Sunday\"],\"opens\":\"00:00\",\"closes\":\"00:00\"}],\"email\":\"iletisim@bicakhukuk.com\",\"faxNumber\":\"0 (312) 473 39 62\",\"areaServed\":\"Hukuk\"},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/#\\\/schema\\\/person\\\/3ffbc31864ec806febdc7f57e5eae117\",\"name\":\"Admin\",\"sameAs\":[\"https:\\\/\\\/www.bicakhukuk.com\"],\"url\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/author\\\/vahit-bicak\\\/\"},{\"@type\":\"PostalAddress\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#local-main-place-address\",\"streetAddress\":\"Next Level Loft Ofis, Kat 9-10, Daire 29, K\u0131z\u0131l\u0131rmak Mahallesi, Ufuk \u00dcniversitesi Caddesi S\u00f6\u011f\u00fct\u00f6z\u00fc \\\/ \u00c7ankaya\",\"addressLocality\":\"Ankara\",\"postalCode\":\"06530\",\"addressCountry\":\"TR\"},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.bicakhukuk.com\\\/en\\\/nuclear-power-plant-law-in-turkey\\\/#local-main-organization-logo\",\"url\":\"https:\\\/\\\/www.bicakhukuk.com\\\/wp-content\\\/uploads\\\/2023\\\/05\\\/bicak_hukuk_logo_kare.png\",\"contentUrl\":\"https:\\\/\\\/www.bicakhukuk.com\\\/wp-content\\\/uploads\\\/2023\\\/05\\\/bicak_hukuk_logo_kare.png\",\"width\":2000,\"height\":2000,\"caption\":\"B\u0131\u00e7ak Hukuk | T\u00fcrkiye Merkezli Global Hukuk Firmas\u0131\"}]}<\/script>\n<meta name=\"geo.placename\" content=\"Ankara\" \/>\n<meta name=\"geo.position\" content=\"39.90985903589262;32.81218744448808\" \/>\n<meta name=\"geo.region\" content=\"Turkey\" \/>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"Nuclear power plant law in Turkey | Bicak Law Firm","description":"nuclear power plant Turkey Lawyer solicitor attorney advocate atomic energy law firm legal team program civilian Agency T\u00fcrkiye Regulation","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/","og_locale":"en_US","og_type":"article","og_title":"Nuclear power plant law in Turkey %","og_description":"T\u00fcrkiye\u2019s Transition to Nuclear Power T\u00fcrkiye has considered the introduction of nuclear-generated electricity since the 1950s. The Turkish Atomic Energy","og_url":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/","og_site_name":"B\u0131\u00e7ak Hukuk","article_publisher":"https:\/\/www.facebook.com\/bicakhukuk","article_published_time":"2023-04-28T08:48:03+00:00","article_modified_time":"2026-07-25T14:16:04+00:00","og_image":[{"width":1024,"height":683,"url":"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/04\/Nuclear-Power-Plant-Law-in-Turkiye-1024x683.png","type":"image\/png"}],"author":"Admin","twitter_card":"summary_large_image","twitter_creator":"@BicakHukuk","twitter_site":"@BicakHukuk","twitter_misc":{"Written by":"Admin","Est. reading time":"43 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#article","isPartOf":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/"},"author":{"name":"Admin","@id":"https:\/\/www.bicakhukuk.com\/en\/#\/schema\/person\/3ffbc31864ec806febdc7f57e5eae117"},"headline":"Nuclear power plant law in Turkey","datePublished":"2023-04-28T08:48:03+00:00","dateModified":"2026-07-25T14:16:04+00:00","mainEntityOfPage":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/"},"wordCount":7171,"commentCount":0,"publisher":{"@id":"https:\/\/www.bicakhukuk.com\/en\/#organization"},"image":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#primaryimage"},"thumbnailUrl":"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/04\/Nuclear-Power-Plant-Law-in-Turkiye.png","keywords":["AI in nuclear energy","Akkuyu EPC contracts","Akkuyu legal advisor","Akkuyu NPP legal framework","Akkuyu nuclear power plant in Turkey","Akkuyu Nuclear Power Plant law","Akkuyu nuclear project T\u00fcrkiye","Akkuyu project legal advice","atomic energy","Atomic Energy Agency Turkey","B\u0131\u00e7ak Law Firm nuclear energy","B\u0131\u00e7ak Law nuclear law","CBAM and nuclear energy T\u00fcrkiye","Chernobyl","civil liability for nuclear damage","civilian nuclear industry Turkey","critical infrastructure cybersecurity T\u00fcrkiye","digital nuclear systems law","dual-use goods nuclear sector","export controls nuclear","foreign investment nuclear energy T\u00fcrkiye","fuel loading permit T\u00fcrkiye","Fukushima accident","Future of Nuclear Power Turkey","IAEA compliance","international arbitration nuclear projects","international nuclear law T\u00fcrkiye","Law of Nuclear and Radiological Control","league of nations with nuclear power","legal advice for reactor vendors T\u00fcrkiye","legal counsel for EPC contractors T\u00fcrkiye","Legal Framework for the Development of Nuclear Energy Turkey","legal services for nuclear companies T\u00fcrkiye","legal services for nuclear suppliers","Liability Regulations for Nuclear Damages","local content nuclear projects","low-carbon electricity T\u00fcrkiye","Multidisciplinary Approach","National bodies on nuclear safety Turkey","NDK T\u00fcrkiye","net zero 2053 nuclear energy","nuclear administrative sanctions","nuclear arbitration T\u00fcrkiye","nuclear commissioning permit","nuclear compliance","nuclear compliance T\u00fcrkiye","nuclear construction contracts","nuclear construction disputes","nuclear construction licence T\u00fcrkiye","nuclear customs compliance T\u00fcrkiye","nuclear cybersecurity T\u00fcrkiye","nuclear damage compensation T\u00fcrkiye","nuclear decommissioning law T\u00fcrkiye","nuclear due diligence T\u00fcrkiye","nuclear EIA T\u00fcrkiye","Nuclear Energy","nuclear energy investment opportunities T\u00fcrkiye","nuclear energy law Turkey","nuclear energy law T\u00fcrkiye","Nuclear Energy Lawyer","nuclear energy lawyer T\u00fcrkiye","nuclear energy PPAs","nuclear energy projects","nuclear energy projects in T\u00fcrkiye","Nuclear Energy Solicitor Turkey","nuclear environmental law T\u00fcrkiye","nuclear EPC contracts","nuclear EPC contracts T\u00fcrkiye","nuclear equipment import T\u00fcrkiye","nuclear equipment procurement","nuclear export controls T\u00fcrkiye","nuclear inspections T\u00fcrkiye","nuclear insurance T\u00fcrkiye","nuclear intellectual property law","nuclear investment T\u00fcrkiye","nuclear joint ventures T\u00fcrkiye","nuclear jurisprudence Turkey","Nuclear law","Nuclear law advice","nuclear law firm T\u00fcrkiye","Nuclear Law Legal Advice","Nuclear law Legal Framework","nuclear law Turkey","nuclear law T\u00fcrkiye","nuclear lawyer Turkey","nuclear liability law Turkey","nuclear liability law T\u00fcrkiye","nuclear licensing T\u00fcrkiye","nuclear localisation T\u00fcrkiye","nuclear market T\u00fcrkiye 2026","nuclear operating licence T\u00fcrkiye","nuclear plant construction Turkey","nuclear power plant law T\u00fcrkiye","nuclear power plant licensing Turkey","nuclear power plant regulation T\u00fcrkiye","nuclear power plant Turkey","nuclear power program Turkey","nuclear power purchase agreements T\u00fcrkiye","nuclear power Turkey","nuclear procurement","nuclear procurement T\u00fcrkiye","nuclear project contracts T\u00fcrkiye","nuclear project counsel T\u00fcrkiye","nuclear project finance T\u00fcrkiye","nuclear project legal advice T\u00fcrkiye","nuclear project lifecycle legal services","nuclear project risk assessment","nuclear proliferation","Nuclear Regulation Law No. 7381","Nuclear Regulation Law Turkey","nuclear regulations Turkey","nuclear regulatory authority","Nuclear Regulatory Authority T\u00fcrkiye","nuclear regulatory compliance lawyer","nuclear regulatory framework T\u00fcrkiye","nuclear regulatory lawyer T\u00fcrkiye","nuclear safeguards T\u00fcrkiye","Nuclear Safety and Control","nuclear safety assessment T\u00fcrkiye","nuclear safety law T\u00fcrkiye","Nuclear Safety Whistleblower Turkey","nuclear sanctions compliance","nuclear security law T\u00fcrkiye","Nuclear Security Regulatory Framework in Turkey","nuclear site licence T\u00fcrkiye","nuclear supplier qualification T\u00fcrkiye","nuclear supply chain law","nuclear technology transfer T\u00fcrkiye","nuclear waste management T\u00fcrkiye","Office for Nuclear Regulation Turkey","Paris Convention T\u00fcrkiye","radiation protection law T\u00fcrkiye","radioactive contaminatio","radioactive waste law T\u00fcrkiye","Sinop NPP T\u00fcrkiye","Sinop Nuclear Power Plant law","Sinop nuclear project legal advice","small modular reactor T\u00fcrkiye","small modular reactors T\u00fcrkiye","SMR law T\u00fcrkiye","SMR lawyer","SMR licensing T\u00fcrkiye","spent nuclear fuel law","strict liability nuclear operator T\u00fcrkiye","Thrace nuclear power project","top nuclear energy legal team","Turkey's first nuclear power plant","Turkey's Nuclear Program","Turkey\u2019s first nuclear plant","Turkish nuclear industry","Turkish nuclear law guide","Turkish nuclear legislation","Turkish nuclear suppliers","T\u00fcrkiye National Energy Plan nuclear"],"articleSection":["@en","Insights"],"inLanguage":"en-US","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/","url":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/","name":"Nuclear power plant law in Turkey | Bicak Law Firm","isPartOf":{"@id":"https:\/\/www.bicakhukuk.com\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#primaryimage"},"image":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#primaryimage"},"thumbnailUrl":"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/04\/Nuclear-Power-Plant-Law-in-Turkiye.png","datePublished":"2023-04-28T08:48:03+00:00","dateModified":"2026-07-25T14:16:04+00:00","description":"nuclear power plant Turkey Lawyer solicitor attorney advocate atomic energy law firm legal team program civilian Agency T\u00fcrkiye Regulation","breadcrumb":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#primaryimage","url":"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/04\/Nuclear-Power-Plant-Law-in-Turkiye.png","contentUrl":"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/04\/Nuclear-Power-Plant-Law-in-Turkiye.png","width":1536,"height":1024,"caption":"nuclear power plant Turkey Lawyer solicitor attorney advocate atomic energy law firm legal team program civilian Agency T\u00fcrkiye Regulation"},{"@type":"BreadcrumbList","@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Ana sayfa","item":"https:\/\/www.bicakhukuk.com\/en\/"},{"@type":"ListItem","position":2,"name":"Nuclear power plant law in Turkey"}]},{"@type":"WebSite","@id":"https:\/\/www.bicakhukuk.com\/en\/#website","url":"https:\/\/www.bicakhukuk.com\/en\/","name":"B\u0131\u00e7ak Hukuk","description":"T\u00fcrkiye Merkezli Global Hukuk B\u00fcrosu","publisher":{"@id":"https:\/\/www.bicakhukuk.com\/en\/#organization"},"alternateName":"B\u0131\u00e7ak Hukuk, Ankara Avukat, Ankara Hukuk B\u00fcrosu","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.bicakhukuk.com\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":["Organization","Place"],"@id":"https:\/\/www.bicakhukuk.com\/en\/#organization","name":"B\u0131\u00e7ak Hukuk | T\u00fcrkiye Merkezli Global Hukuk Firmas\u0131","alternateName":"B\u0131\u00e7ak Hukuk, Ankara Avukat, Ankara Hukuk B\u00fcrosu","url":"https:\/\/www.bicakhukuk.com\/en\/","logo":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#local-main-organization-logo"},"image":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#local-main-organization-logo"},"sameAs":["https:\/\/www.facebook.com\/bicakhukuk","https:\/\/x.com\/BicakHukuk","https:\/\/www.instagram.com\/bicakhukuk\/","https:\/\/tr.linkedin.com\/company\/b-ak-law-firm","https:\/\/www.youtube.com\/channel\/UCodktEWFyJmIp3i1BH9aM2A\/"],"description":"K\u00fcresel, b\u00f6lgesel ve ulusal \u015firketlere, kurulu\u015flara ve ki\u015filere uzmanl\u0131k alanlar\u0131m\u0131zda uyu\u015fmazl\u0131k \u00f6nleyici hukuk dan\u0131\u015fmanl\u0131\u011f\u0131, uyu\u015fmazl\u0131k \u00e7\u00f6z\u00fcm s\u00fcre\u00e7lerinde ise arabuluculuk, arabuluculukta taraf vekilli\u011fi, mahkemelerde taraf vekilli\u011fi ve avukatl\u0131k, tahkim hakemli\u011fi, tahkimde taraf vekilli\u011fi, hukuki konularda m\u00fctalaa ve hukuki konularda e\u011fitim hizmetleri vermekteyiz. Uluslararas\u0131, b\u00f6lgesel ve ulusal hukuka ili\u015fkin inceleme, ara\u015ft\u0131rma ve tecr\u00fcbeye dayal\u0131 hukuk hizmetlerimizi sunarken teknolojinin imkan sa\u011flad\u0131\u011f\u0131 g\u00f6rsel (video konferans) veya i\u015fitsel (sesli konferans) ileti\u015fim teknolojilerinin elverdi\u011fi t\u00fcm olanaklar\u0131 kullanmaktay\u0131z. Dan\u0131\u015fanlar\u0131m\u0131z veya m\u00fcvekkillerimiz, D\u00fcnyan\u0131n, b\u00f6lgemizin veya \u00fclkemizin neresinde olurlarsa olsunlar hizmetlerimizden uzaktan eri\u015fim yoluyla yararlanabilmektedir. Muhtemel ihtilaflar\u0131 \u00f6nlemek veya en aza indirmek gayesiyle m\u00fcvekkillerimize sundu\u011fumuz dinamik, etkili ve \u00f6nleyici dan\u0131\u015fmanl\u0131k hizmetlerimizin yan\u0131nda, uyu\u015fmazl\u0131k \u00e7\u00f6z\u00fcm s\u00fcre\u00e7lerinde arabuluculuk, tahkim veya mahkemelerde dava takibi hizmetleri de sunmaktay\u0131z. Ba\u015far\u0131n\u0131n s\u0131rr\u0131, do\u011fru bilgiye h\u0131zl\u0131 eri\u015fimdir. M\u00fcvekkil ihtiya\u00e7lar\u0131 tam ve eksiksiz tan\u0131mlayarak y\u00fcksek standartlarda, kaliteli, h\u0131zl\u0131 ve sonu\u00e7 odakl\u0131 esas\u0131na dayanan bir \u00e7al\u0131\u015fma anlay\u0131\u015f\u0131 benimsemi\u015f bulunuyoruz. G\u00fcvenilirlik, itibar, etik de\u011ferler ve kalite standartlar\u0131 gibi unsurlar, vazge\u00e7ilmezlerimiz olu\u015fturur.","legalName":"B\u0131\u00e7ak Hukuk","foundingDate":"2002-01-01","numberOfEmployees":{"@type":"QuantitativeValue","minValue":"1","maxValue":"10"},"address":{"@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#local-main-place-address"},"geo":{"@type":"GeoCoordinates","latitude":"39.90985903589262","longitude":"32.81218744448808"},"telephone":["0 (312) 473 39 60","0 (553) 223 32 90"],"openingHoursSpecification":[{"@type":"OpeningHoursSpecification","dayOfWeek":["Monday","Tuesday","Wednesday","Thursday","Friday","Saturday"],"opens":"08:00","closes":"18:00"},{"@type":"OpeningHoursSpecification","dayOfWeek":["Sunday"],"opens":"00:00","closes":"00:00"}],"email":"iletisim@bicakhukuk.com","faxNumber":"0 (312) 473 39 62","areaServed":"Hukuk"},{"@type":"Person","@id":"https:\/\/www.bicakhukuk.com\/en\/#\/schema\/person\/3ffbc31864ec806febdc7f57e5eae117","name":"Admin","sameAs":["https:\/\/www.bicakhukuk.com"],"url":"https:\/\/www.bicakhukuk.com\/en\/author\/vahit-bicak\/"},{"@type":"PostalAddress","@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#local-main-place-address","streetAddress":"Next Level Loft Ofis, Kat 9-10, Daire 29, K\u0131z\u0131l\u0131rmak Mahallesi, Ufuk \u00dcniversitesi Caddesi S\u00f6\u011f\u00fct\u00f6z\u00fc \/ \u00c7ankaya","addressLocality":"Ankara","postalCode":"06530","addressCountry":"TR"},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.bicakhukuk.com\/en\/nuclear-power-plant-law-in-turkey\/#local-main-organization-logo","url":"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/05\/bicak_hukuk_logo_kare.png","contentUrl":"https:\/\/www.bicakhukuk.com\/wp-content\/uploads\/2023\/05\/bicak_hukuk_logo_kare.png","width":2000,"height":2000,"caption":"B\u0131\u00e7ak Hukuk | T\u00fcrkiye Merkezli Global Hukuk Firmas\u0131"}]},"geo.placename":"Ankara","geo.position":{"lat":"39.90985903589262","long":"32.81218744448808"},"geo.region":"Turkey"},"_links":{"self":[{"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/posts\/25158","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/users\/27"}],"replies":[{"embeddable":true,"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/comments?post=25158"}],"version-history":[{"count":0,"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/posts\/25158\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/media\/32080"}],"wp:attachment":[{"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/media?parent=25158"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/categories?post=25158"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.bicakhukuk.com\/en\/wp-json\/wp\/v2\/tags?post=25158"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}